This document provides questions and answers related to a solicitation for upgrading building complexes at Hilo Air National Guard Base in Hawaii. The solicitation seeks a fixed-price contract to upgrade envelopes, lighting, and HVAC systems across five buildings. Scope includes replacing windows and doors, roof repairs, and new HVAC systems. Optional line items include additional roof coating. The pre-proposal conference is scheduled for March 25, 2022 with questions due by March 22. Proposals are due April 21, 2022 and the contract is set aside for small businesses. The selected contractor must coordinate work with the 154th Civil Engineer Squadron.

View the file

Other files

File Type Posted
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (10-May-2022).pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (9-May-2022).pdf PDF
Solicitation RFP W50SLF22R0001 (5.5.2022 Conformed Document).pdf PDF
ATTCH 15_ 22-0503 HIANG_ADDENDUM_004.pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (4-May-2022).pdf PDF
Solicitation Amendment W50SLF22R0001 0003.pdf PDF
Solicitation Amendment W50SLF22R0001 0002.pdf PDF
Solicitation RFP W50SLF22R0001 (Conformed Document).pdf PDF
ATTCH 12_22-0427_HIANG_ADDENDUM_003.pdf PDF
ATTCH 13_ 22-0428_HIANG_ADDENDUM_003.pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (28-Apr-2022).pdf PDF
ATTCH 14_22-0428-HIANG-Drwgs-ADD_3.pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (13-Apr-2022).pdf PDF
Solicitation Amendment W50SLF22R0001 0001.pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (12-Apr-2022).pdf PDF
5. A10-KTR Laydown Area.xlsx XLSX spreadsheet
3. Pre-Proposal Meeting PPT Upgrade Bldg Complex Hilo.pptx PPTX presentation
1. MFR - Pre-Proposal Conference Site Visit.pdf PDF
2. Attendance Sheet - Upgrade Bldg Complex Hilo.pdf PDF
ATTCH 5_Addendum 01 - Clarification Minor Construction_dwgs.pdf PDF
ATTCH 7_Addendum 02 - SOW Add Haz Matl Survey Info.pdf PDF
ATTCH 9_88127 - Basis of Design - Mechanical.pdf PDF
EXHIBIT D_Letter of Commitment.docx DOCX document
ATTCH 10_88127 - Drawings - Mechanical R02 - Certified.pdf PDF
ATTCH 2_Appendix B - Drawings FINAL.pdf PDF
ATTCH 3_Appendix F - Calcs (FOUO).pdf PDF
ATTCH 1_SOW_MABE152003 Upgrade Building Complex Hilo.docx DOCX document
EXHIBIT C_Reference_Questionnaire_Package.docx DOCX document
ATTCH 8_Narrative of changes (Mech).pdf PDF
ATTCH 4_Appendix G - Specs FINAL.pdf PDF
Solicitation RFP W50SLF22R0001.pdf PDF
ATTCH 11_22-0128-HILO-ARCH-FINAL-PERMIT.pdf PDF
EXHIBIT A_Performance Relevancy Questionnaire.docx DOCX document
ATTCH 6_Addendum 01 - Drawings.pdf PDF
EXHIBIT B_Subcontractor Information and Consent Form.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Related To:

MABE152003 UPGRADE BUILDING COMPLEX, HILO

Solicitation W50SLF-22-R-0001

Dated 27-Mar-2022

Q1: Please confirm if the original bid bond with wet signatures needs to be mailed to the Kapolei office.

A1: A copy of bid bond will suffice when submitting your bid response electronically. We require bid bond with submission of proposal. The bid bond is due on the date as stated on the SF1442 block 13. The bid bond must be on a SF24 form. Rejection of a bid bond shall be in accordance with FAR 28.101-4 Noncompliance with bid guarantee requirements. An Original Bid Bond with wet signatures mailed to the Kapolei office is not required.

Q2: The RFI deadline is 03/22/2022 which is prior to the scheduled pre-proposal conference/site visit on 03/25/2022. Will there be another RFI deadline after the pre-proposal conference/site visit?

A2: If you have RFI’s you’d like me to address at Pre-Proposal Conference/Site Visit, they are due 3/22/2022. For Solicitation RFP, please reference SECTION 00100, 3. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS, 3.3 The Contracting Officer reserves the right to address questions received after the fifth day prior to solicitation closing with those offers deemed compliant and/or in the competitive range after closing. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing and will be posted not later than two working days prior to closing. OFFERORS ARE STRONGLY

ENCOURAGED TO SUBMIT QUESTIONS EARLY IN THIS PROCESS.

For Questions 3 & 4 below. Volume 2, Part 2 deals with Past/Present Performance Information and correlates with Exhibit A and Exhibit C. Volume 2, Part 1, Subfactor 1, Experience and Capability correlates with Exhibit B and D. Exhibit B and D are not required if your key construction personnel are already part of your organization, i.e. Project Manager, Site Superintendent(s), Quality Control Manager (on site) and Safety Manager. Refer to pgs. 106- 107, Section 01000, paragraph 35 of RFP, for the minimum qualification requirements for key personnel. You would need to provide Exhibit B and D only in the event the intended person is not part of the offeror’s organization at the time the proposal is submitted.

Q3: Are key personnel references required for Volume 2, Part 2 if the Prime Contractor is not relying on key personnel experience for Subfactor 1 – Experience and Capability?

A3: If you do not have relevant past performance and are using experience of key personnel, predecessor companies or subcontractors to obtain this, ensure you clearly state this in the proposal. To be considered, Subcontractor must complete a consent form – Exhibit B.

Q4: Are key personnel references required for Volume 2, Part 2 for the resumes that are submitted in Part 1?

A4: No if your key personnel are part of your organization, however please refer to section

2.5.3.9. and 2.5.3.10 on pages 21 and 22 of solicitation if it applies.

2.5.3.9. Offerors lacking relevant present/past performance experience may submit information regarding predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement if such information is relevant to this acquisition.

Such information shall, as a minimum, include:

Name(s) of Predecessor Company/Subcontractor and/or Key Personnel Complete Address Telephone, Fax Number and email address Brief synopsis of the experience- A resume may be submitted for "Key Personnel" Describe relevancy to this project

2.5.3.10 Provide three (3) references, for each Predecessor Company, Subcontractor or Key Personnel.

Clearly identify the contractor/individual for whom the reference information concerns.

Q5: Will you please confirm that the Mechanical and Architectural drawings included as Attachment #s 10 and 11 supersede the same-named drawing pages in attachment #2 and those revised in Addendum #1?

A5: Yes, the Mechanical and Architectural drawings included as Attachment #s 10 and 11 supersede the same-named drawing pages in attachment #2 and those revised in Addendum #1

Q6: Will the Contractor or 291st CBCS be responsible moving any furniture/office equipment out of the rooms that require scope of work to be done for this project.

A6: The 291st CBCS is responsible in moving any furniture/office equipment out of the rooms that require work to be done and back into the rooms when the work is complete.