This solicitation is seeking proposals for the construction of a Commercial Inspection Facility project at the Tulsa Air National Guard Base in Tulsa, Oklahoma. The project magnitude is estimated between $1,000,000 to $5,000,000. The North American Industry Classification code is 236220 with a size standard of $39,500,000. This project is set aside 100% for small businesses. The pre-proposal conference is strongly encouraged for offerors intending to submit a proposal. Award will be made based on best value as outlined in the solicitation. Funding is not presently available but is anticipated to be appropriated prior to award, as this project has been identified on the National Guard's priority list. No award will be made until funding is available. The response date for proposals is August 4, 2022.

View the file

Other files

File Type Posted
Pre-Bid RFI CIF_1August22.pdf PDF
ADDENDUM 2.pdf PDF
Brand_Name_Justification Gibralter 1.1_Redacted.pdf PDF
Brand_Name_Justification (Telecor_PA) 1.0_Redacted.pdf PDF
Brand_Name_Justification (Cisco_infrastructure) 1.0_Redacted.pdf PDF
Brand_Name_Justification (Aruba_Wireless) 1.0_Redacted.pdf PDF
Brand_Name_Justification (Bosch_Camera) 1.0_Redacted.pdf PDF
Brand_Name_Justification ALC 1.0_Redacted.pdf PDF
Brand_Name_Justification (Corning_FODP) 1.0 s_Redacted.pdf PDF
Brand_Name_Justification Ameristar 1.1_Redacted.pdf PDF
Brand_Name_Justification Delta Scientific 1.1_Redacted.pdf PDF
Pre-Proposal RFI CIF_26July22.pdf PDF
Brand_Name_Justification Panduit_infrastructure) 1.0_Redacted.pdf PDF
W50S8U-22-R-0001 Amend 02 Extend Proposal Due Date.pdf PDF
Pre-Bid RFI CIF_20July22.pdf PDF
Addendum 1.pdf PDF
W50S8U-22-R-0001 Amend 01 Proposal Due Dates.pdf PDF
Pre-Proposal RFI CIF_7July22.pdf PDF
CIF Pre-proposal slides.pptx PPTX presentation
PreProposal Site Visit Minutes.pdf PDF
CIF Pre-proposal Attendance Sheet 23Jun22_Redacted.pdf PDF
Attachment 3 Statement of Work.pdf PDF
Attachment 1b Electronic Submittals-Addendum 2.pdf PDF
W50S8U-22-R-0001 Solicitation.pdf PDF
EXHIBIT_D_Letter of Commitment.docx DOCX document
EXHIBIT_A_Performance_Questionnaire.doc DOC document
EXHIBIT_C_Reference_Questionnaire_Package.docx DOCX document
Attachment 1d Final Design Submittal Specs from Pages 29-30.pdf PDF
Attachment 1a Electronic Submittals-Addendum 1.pdf PDF
Attachment 1c Final Design Submittal Specs.pdf PDF
Attachment 2 Commercial Inspection Facility Drawings.pdf PDF
EXHIBIT_B_Subktr_InfoandConsent.doc DOC document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

XHZG159052

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose for Amendment 0003 is for the follow ing: 1) to consolidate the answ ers to questions received that are posted on SAM. 2) incorporate the most recent Wage Determination dated 17 Jun 2022. 3) Justif ications and Approvals posted on SAM. 4) Revise the cable system specification draw ing at CS504 from Gibraltar TL-3 to Gibraltar TL-4 Tamper Proof System. 5) Revise Addendum 2. 6) and Extend the proposal due date to August 4, 2022 at 1:00 P.M. CST.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 13

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jul-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S8U22R0001

X 9B. DATED (SEE ITEM 11)

10-Jun-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jul-2022

CODE

USPFO OK 138 MISSION SUPPORT CONTRACTING

4200 N 93RD EAST AVE

TULSA OK 74115-1699

W50S8U 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S8U22R0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

ANSWERS TO QUESTIONS

1. QUESTION: SPEC SECTION 01 30 00 – Paragraph 1.7.2. “Paragraph 1.7.2 states that superintendent can also fulfill the role of QCM. This contradicts OKANG DIVISION 01 SPECIFICATIONS - Paragraph 36 which states that individual team members may not hold more than one position on the project. Please clarify the desired staffing for Contractor on this project.”

ANSWER: Based on the magnitude of the project, the superintendent is not permitted to act as the QCM.

2. QUESTION: SPEC SECTION 01 35 26 – Paragraph 1.5.1.1 . “Paragraph 1.5.1.1 calls to provide a SSHO for the site and additionally states that the SSHO may also serve as QCM. This contradicts OKANG DIVISION 01 SPECIFICATIONS - Paragraph 36 which states that individual team members may not hold more than one position on the project. Please clarify the desired staffing for Contractor on this project.”

ANSWER: An individual may act as both the QCM and SSHO, if qualifications are met for both positions. Ref 01 35 26 Para 1.5.1.1., any alternate SSHO must also meet qualification for both positions.

3. QUESTION: SPEC SECTION 01 45 00 – Paragraph 3.4.2 . “Paragraph 3.4.2 states that the QCM can also fulfill the role of Superintendent. This contradicts OKANG DIVISION 01 SPECIFICATIONS - Paragraph 36 which states that individual team members may not hold more than one position on the project. Please clarify the desired staffing for Contractor on this project.”

ANSWER: Based on the magnitude of the project, the QCM is not permitted to act as the superintendent.

4. QUESTION: “Will this project utilize USACE RMS project management system? If not, should contractors include the cost for a system similar to Submittal Exchange to manage electronic documents and submittals?”

ANSWER: This project will not utilize USACE RMS. Reference Attachment 1a, Addendum 1 of the solicitation for contractor provided project management collaboration website.

5. QUESTION: SPEC SECTION 01 78 00 – Paragraph 1.2.1 . “Paragraph 1.2.1 calls for the contractor to provide electronically formatted as-built drawings. Will the Owner provide CAD files for base contract design after project award?”

ANSWER: CAD files will be provided after award.

6. QUESTION: SPEC SECTION 01 78 00 – Paragraph 3.1.3. “Paragraph 3.1.3 calls for the contractor to provide GIS information in a satisfactory manner for the installations GIS database. What is the current methods for GIS management at this installation?”

ANSWER: Esri ArcGIS

7. QUESTION: SPEC SECTION 09 06 00 – SCHEDULES FOR FINISHES. “SCHEDULES FOR FINISHES does not include any color information for exterior and interior. The specification does provide designations for items on the project, but no color information. Please provide desired colors for the project.”

ANSWER: Color selection will be made as part of the submittal review/approval process, after award.

8. QUESTION: SPEC SECTION 01 33 29 – Paragraph 1.2. “Paragraph 1.2 states that a HPSB checklist would be furnished to outline overall point strategy for high performance and sustainable building practice requirements.

There was no checklist within the specifications. Please provide”

ANSWER: Bidders can assume all HPSB requirements are incorporated in the appropriate portions of the specification.

9. QUESTION: SPEC SECTION 05 05 23.16 – Paragraph 1.3.1 and SPEC SECTION 05 12 00 – 1.3. “Spec calls for a AISC certified steel fabricator and erector. Please confirm that bidders should include the additional costs associated with AISC certified fabricators and erectors.”

ANSWER: Prospective bidders should include pricing for AISC certified steel fabricator and erector.

10. QUESTION: “Will the Owner provide a commissioning agent for the project? Should Contractors plan on coordination of the Owners commissioning agent?”

ANSWER: The owner will not provide a commissioning agent. This is not a LEED project.

11. QUESTION: “We'd like to submit our equal light fixture package for prior approval review by the design team on the Commercial Inspection Facility project. Please find our lighting package included in the link below. Please let me know if we also need to complete and return Substitution Request Forms along with our lighting package.”

ANSWER: Product submittals will be reviewed after award.

12. QUESTION: “Is there any chance the AISC Certification for steel fabricators can be waived? There aren't very many fabricators in the area with this certification.”

ANSWER: This requirement will not be waived.

13. QUESTION: Solicitation Para 11 (pg 10-11). “Are there any Name Brand Items as part of this solicitation.”

ANSWER: Bidders should pay special attention to brand name items annotated in para 11 of the solicitation and cross reference with design and specifications.

14. QUESTION: “Par: 10 of Statement of Work states “The contractor is responsible for marking/locating all underground utilities…all other utilities to include base communications fiber optic lines, electric, sewer and water will be the contractor’s responsibility to mark.”

ANSWER: Contractor will be provided base utility maps for reference.

15. QUESTION: “Will the Government provide AutoCAD drawings post award?”

ANSWER: Yes.

16. QUESTION: “Sheet CS-401 shows the existing OHP voltage regulators are in the same location as the proposed southern radius of the approach to Mingo Road. Is voltage regulator stand to be relocated? If not, will an alternate solution be provided?”

ANSWER: Contractor will coordinate with PSO to relocate regulators and stand as necessary.

17. QUESTION: “If authorized, an on-site office trailer may be utilized, and availability of utilities is a consideration. Is there a location on or off site that an office trailer can be set up? If so, are any utilities available for hook up (elect, water, sewer, comm, etc.)?”

ANSWER: The Contractor will be authorized to place a job trailer in the annotated lay down are. Contractors should anticipate that utilities are not available.

18. QUESTION: “Per the drawings provided, the site will have direct entry/exit access to off base roadways. When considering material temps and placement times, special attention is placed on the round-trip timing and material placement requirements for asphalt & concrete. Will this site be classified as an “On-Base” of Off-Base” site? Will the delivery vehicles be sent through the SF inspection process?”

ANSWER: This area of the installation is currently considered off installation due to on-going POL project. That project is anticipated to complete in spring 2023. At that point, a portion of the project site will be considered on installation. The government can work with the contractor to delineate the CIF project site to remain off installation to the maximum extent possible.

19. QUESTION: “What are the landscape and irrigation requirements for the project?”

ANSWER: Reference drawing and specifications for landscape/irrigation requirements associated with this project.

20. QUESTION: “Are fencing and gates to be crash rated? These type of entries typically have a M50/P1 rating.

Please confirm desired rating.”

ANSWER: Reference drawing and specifications for fencing and gate construction requirements.

21. QUESTION: “Ameristar fence is typically a 3 rail fence system. Please confirm this project desires a custom 4 rail fence system”

ANSWER: The government is unsure where reference for 4 rail system is located. The installation currently uses a 3 rail system offered by Ameristar.

22. QUESTION: “Upon speaking with the manufacturer, it appears the Gibraltar Cable Barrier System specified is not correct for this application and will not be able to fit the curves of the road and still be functional. Gibraltar makes a tamper-proof cable barrier system that they recommend to better suit this project. Please advise”

ANSWER: This is correct, the TL-3 is not able to be used for this project. Please see the attached addendum changing the cable system to the Gibraltar TL-4

23. QUESTION: “Clarification on the specs for the reinforcement for the irregular shaped concrete panels.”

ANSWER: Use concrete reinforcement specification found in section 1.6.2.2 & 2.6.1 reinforcement bars.

24. QUESTION: “Is ASR testing required?”

ANSWER: No.

25. QUESTION: “Key Note 4 Sheet CS412 calls for concrete pilasters as shown on the structural plans. Detail 9 on Sheet S-004 provides detail on masonry veneer pilaster. The plans do not mention masonry veneer other than structural detail note. Please confirm that Key Note 4 correlates with detail 9/S-0004 and if masonry should be included.”

ANSWER: Please see the attached updated detail 9 on sheet S-400.

26. QUESTION: “Detail 10 on Sheet S-004 is for the pilaster @ fence post. I cannot find a correlating location on sheet CS412. Please provide location of the pilaster @ fence posts.”

ANSWER: The posts for detail 10 are the two end posts that intersect the fence leaders 86 and 87 on Sheet CS402.

27. QUESTION: “There is no mention of a foundation under the rolling gate sections or in between pilasters on Sheet CS412. What should contractors include at the gate openings?”

ANSWER: For the gate areas over the roadway the road paving shall continue. If it is not over a roadway use 5' wide mow strip that covers both the fence section and the area the gate hangs over.

28. QUESTION: “Key Note 14 on Sheet calls for a hybrid beacon safety traffic signal pole. Sheet CS505 indicates the use of a Stop Control system with standard poles with red lights. Please confirm the desired type of signal poles for the project.”

ANSWER: 3.25" square anodized aluminum +/- 3/4" in bronze color.

29. QUESTION: “Past performance relevancy is based on projects completed within last 5 years on Exhibit A, however section 2.3. Past/Present Performance Evaluation subsection 2.3.3. states that the definition of "Current" means performance occurring within the last (10) years prior to the solicitation date. With the requirements in this same section being one (1) project with magnitude over $3.5 million, one (1) project with a minimum of 5000 SY asphalt, one (1) project with a minimum of 5000 SY concrete paving, one (1) project that included installation of Vehicle Barrier cable system, how are we to narrow that into the limit of only three (3) exhibit A & exhibit C projects as written?”

ANSWER: Projects within the last 10 years are acceptable. Please disregard the 5 years statement in Section

2.4.3.6. If 5 separate projects are needed to show past performance for the 5 criteria the contractor can submit 5 projects to show past performance.

30. QUESTION: “The 10 year requirement in subsection 2.3.3 would allow more flexibility to meet the relevancy of the scope requirements of the solicitation limited to only three projects within last 5 years. Will projects meeting the relevancy requirements completed within last 10 years be acceptable for evaluation? - Please advise.”

ANSWER: Projects within the last 10 years are acceptable.

31. QUESTION: “Elevation 10 on Sheet A-401 shows a pass thru window. There is no information about the type of pass thru window. This window is within a ballistic rated wall. Please provide information on window and pass through counter.”

ANSWER: Use a bullet resistant window with the same rating as the exterior window that slides. The short counter can be integral or be SS1. window size is approximately 2' wide x 4'.

32. QUESTION: “BR1 appears to be different than what is used on base.”

ANSWER: BR1 is incorrect use ACME Garnet Modular with Ruff face.

33. QUESTION: “Is the road section on viper road that ties into the POL project to be the same concrete or asphalt as the rest of the project.”

ANSWER: No, use 9" 4000 PSI steel reinforced concrete as the base bid for this area . Reinforcing steel is to be #4 bars at 18" O.C, E.W. This treatment is to take place between points 160 & 164 on sheet CS406.

34. QUESTION: “Specific systems and type are called out in this spec with drawings? Does the AF only want one system from one vendor? This increases the price to the government? This should be a generic barrier system.”

ANSWER: The government specified the systems it requires for this solicitation. Special attention should be applied to solicitation to understand brand names specified.

35. QUESTION: “Is this project sales tax exempt”

ANSWER: No, it is not tax exempt

36. QUESTION: “The site layout of the active vehicle barrier system is set up for a 7-Second Hybrid Beacon Safety Scheme as per the 2019 version of the SDDCTEA Pamphlet 55-15. There are two contradicting items in the documents to this safety scheme.

* Sheet CS505 shows a Stop Control Safety scheme.

* Specification 34 41 26.00 calls for a Signs and Signals safety scheme which is an older version of the 7-second Hybrid Beacon from the 2014 version of the SDDCTEA Pamphlet 55-15.”

ANSWER: Yes, please use the 2019 version.

37. QUESTION: “All Electrical site plan sheets have note “A” which states that below grade conduits under pav’t and within 8’ of paved areas will be concrete encased. Does this include all conduits (for example light pole circuits)? Or is the note for certain conduits only?”

ANSWER: Please see addendum 2 for answers.

38. QUESTION: “CU 402 thru CU 406 show a F.O. communication line w/ boxes. How many conduits are involved with this line? Is it concrete encased? At the West end of this line it appears to cross under some existing paved areas, will these areas be bored or open cut and patched?”

ANSWER: Please see addendum 2 for answers

39. QUESTION: “All civil site plans make reference key note to a OKANG monument sign. There are no details provided for what the sign is. Can you clarify?”

ANSWER: Please see addendum 2 for answers.

40. QUESTION: “Sheet CA402 & CA404 make reference to irregular panel shapes. Are these panels to have reinforcing steel in them? Can you please provide detail on bar size & spacing if required?”

ANSWER: Please see addendum 2 for answers.

41. QUESTION: “Ref. Sheet CP502 Sign #18 Do not Enter sign. Do you want the sign to have LED lights on the perimeter and solar powered? Also, the 12” Red Beacon shown, is it solar powered? Are they to be on 4-1/2” poles the same as radar sign?”

ANSWER: Please see addendum 2 for answers.

42. QUESTION: “Ref. Sheet CP502 Sign #1 Are these the sizes of the signs. Can you verify the sizing of these signs? W3-10a 36” x 36”? W16-9P 12” x 30”?”

ANSWER: Please see addendum 2 for answers.

43. QUESTION: “Ref. Sheet CP502 Sign #2 Are these the sizes of the signs. Can you verify the sizing of these signs? W1-5R 36”x36”, W1-5P 12” x 36”?”

ANSWER: Please see addendum 2 for answers.

44. QUESTION: “Ref. sheet CP502 Sign #7 What size is the sign? What type of post does this sign get?”

ANSWER: Please see addendum 2 for answers.

45. QUESTION: “Ref. Sheet CP502 Sign #8 The red and white is how long? And how high?”

ANSWER: Please see addendum 2 for answers.

46. QUESTION: “Ref Sheet CP502 Signs numbers 9,12,13,14,15,16,19 and 20 What size are these signs?”

ANSWER: Please see addendum 2 for answers.

47. QUESTION: “Ref Sheet CP502 Signs numbers 1,2,3,4,6,7,12,13,14,15,16,17,19, and 20 What type of posts do these signs go on?? Detail 2 on sheet CP503 only references Stop, yield, and speed. Is the pole mounting for the other signs in question?”

ANSWER: Please see addendum 2 for answers.

WAGE DETERMINATION 17 JUN 2022

"General Decision Number: OK20220053 06/17/2022

Superseded General Decision Number: OK20210053

State: Oklahoma

Construction Type: Building Building Construction -does not include residential construction consisting of single family homes and apartments up to and including 4 stories. (Including building projects on industrial sites and treatment plants)

County: Tulsa County in Oklahoma.

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658. Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered into on or after January 30, 2022, or the contract is renewed or extended (e.g., an option is |exercised) on or after January 30, 2022:

|Executive Order 14026 generally applies to the contract. The contractor must pay all covered workers at least |$15.00 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent |performing on the contract in 2022.

|If the contract was awarded on or between January 1, 2015 and January 29, 2022, and the contract is not renewed or |extended on or after January 30, 2022:

|Executive Order 13658 generally applies to the contract. The contractor must pay all covered workers at least |$11.25 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent |performing on that contract in 2022.

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.

Modification Number Publication Date 0 01/07/2022 1 02/18/2022 2 02/25/2022 3 06/17/2022

BROK0005-004 06/01/2021

Rates Fringes

BRICKLAYER....................... $ 25.92 11.89

ELEC0584-006 06/01/2021

Rates Fringes

ELECTRICIAN (Excludes Low Voltage Wiring and Installation of Alarms and Sound and Communication Systems)......................... $ 32.38 7%+10.15

ELEV0083-003 01/01/2022

Rates Fringes

ELEVATOR MECHANIC............$ 44.93 36.885+a+b

PAID HOLIDAYS:

a. New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.

b. Employer contributes 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; 6% for less than 5 years' service.

ENGI0627-020 10/15/2021

Rates Fringes

POWER EQUIPMENT OPERATOR:

Group 1.....................$ 32.05 15.30 Group 2.....................$ 30.35 15.30 Group 3.....................$ 29.80 15.30 Group 4.....................$ 29.00 15.30 Group 8.....................$ 24.45 15.30 Group10.....................$ 23.00 15.30

POWER EQUIPMENT OPERATOR

GROUP 1: All Crane Type Equipment 200 ton and larger and including 400 ton capacity cranes. All Tower Cranes.

GROUP 2: All Crane Type Equipment 100 ton capacity and larger cranes, and less than 200 ton capacity.

GROUP 3: All Crane Type Equipment 50 ton capacity and larger cranes, and less than 100 ton capacity. Crane Equipment (as rated by mfg.) 3 cu. yd. and over Guy derrick Whirley Power Driven Hole Digger (with 30' and longer mast).

GROUP 4: CRANES with Boom Incl. Jib less than 100 ft and less than 3 cu. Yd.; Overhead Monorail Crane

GROUP 8: FORK-LIFT

GROUP 10:OILER; SEMI-TRAILER TRUCK DRIVER

* IRON0584-025 06/01/2021

Rates Fringes

IRONWORKER (Ornamental, Reinforcing and Structural)......$ 26.25 15.35

PLUM0430-010 07/01/2021

Rates Fringes

PLUMBER (Excludes HVAC Pipe and Unit Installation)...........$ 32.85 14.08

PLUM0430-019 10/01/2020

Rates Fringes

HVAC MECHANIC (Installation of HVAC Unit Only, Excludes Installation of HVAC Pipe and Duct)............................ $ 32.25 13.98

PLUM0430-020 07/01/2021

Rates Fringes

PIPEFITTER (Including HVAC Pipe Installation, excluding HVAC Unit Installation)..........$ 32.85 14.08

ROOF0143-001 07/01/2021

Rates Fringes

ROOFER...........................$ 22.65 9.30

SHEE0270-006 06/01/2020

Rates Fringes

SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 35.49 14.60

* SUOK2012-033 07/30/2012

Rates Fringes

CARPENTER (Drywall Hanging Only)............................ $ 15.08 1.21

CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 14.96 ** 1.55

CAULKER.......................... $ 20.00 1.61

CEMENT MASON/CONCRETE FINISHER... $ 13.72 ** 1.27

DRYWALL FINISHER/TAPER........... $ 13.00 ** 0.00

ELECTRICIAN (Alarm Installation).................... $ 19.48 3.34

ELECTRICIAN (Low Voltage Wiring).......................... $ 20.65 3.06

ELECTRICIAN (Sound and Communications Systems Installation)..$ 21.11 2.47

FORM WORKER...................... $ 12.69 ** 0.38

LABORER: Common or General...... $ 12.44 ** 2.71

LABORER: Mason Tender - Brick... $ 12.43 ** 0.00

LABORER: Mason Tender - Cement/Concrete.................. $ 13.00 ** 1.91

LABORER: Pipelayer.............. $ 12.39 ** 0.00

OPERATOR: Asphalt Paver......... $ 16.25 0.00

OPERATOR: Backhoe/Excavator/Trackhoe....... $ 16.96 4.22

OPERATOR: Bulldozer............. $ 21.07 2.48

OPERATOR: Grader/Blade.......... $ 14.28 ** 1.70

OPERATOR: Loader (Front End).... $ 16.18 0.00

PAINTER: Brush, Roller and Spray, Excludes Drywall Finishing/Taping................. $ 12.22 ** 0.00

SHEET METAL WORKER, Excludes HVAC Duct Installation........$ 22.11 4.93

SPRINKLER FITTER (Fire Sprinklers)...................... $ 21.86 1.19

TRUCK DRIVER: Dump and Flatbed Truck.................... $ 11.00 ** 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($15.00) or 13658 ($11.25). Please see the Note at the top of the wage determination for more information.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH- 0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time 04-Aug-2022 01:00 PM has been added.

The Issued By organization has changed from

USPFO OK 138 MISSION SUPPORT CONTRACTING

4200 N 93RD EAST AVE

TULSA OK 74115-1699

to

USPFO OK PURCHASING & CONTRACTING

3501 MILITARY CIRCLE

OKLAHOMA CITY OK 7111-4398

(End of Summary of Changes)