Attachment 3 Statement of Work.pdf
PDF 101 KB Posted
- Attached to
- Commercial Inspection Facility - Construction Federal contract opportunity
- Solicitation number
- W50S8U-22-R-0001
- Issued by
- Department of the Army National Guard
About this file
This statement of work and related federal contract opportunity are for construction of a Commercial Inspection Facility for the Tulsa Air National Guard in Oklahoma. Key requirements include providing all labor, materials, equipment and transportation to complete the project; disposing of all debris off-base; complying with base security and antiterrorism training policies; and inputting project data in the BUILDER SMS template. Optional line items include replacing asphalt with concrete pavement, adding a visitor parking area, upgrading the perimeter fencing, and installing mow strips. The solicitation number is W50S8U-22-R-0001 and was issued by the Department of the Army National Guard for the $1-5M project. The NAICS code is 236220 for commercial and institutional building construction. The acquisition is set aside 100% for small businesses and the pre-proposal conference is strongly encouraged for interested offerors to attend. Award will be based on best value. Funding is not presently available but is expected to be appropriated before contract award.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Commercial Inspection Facility
PROJECT XHZG159052
18 October 2021
1. The contractor shall provide all labor, material, tools, equipment and transportation necessary to complete the work identified in this Statement of Work.
2. All debris is to be disposed of off Base with proper documentation in accordance with the waste plan generated by the contractor after the project is awarded.
3. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency
Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection
Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
a. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index
(NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
4. All contractor employees, to include subcontractor employees, requiring access to Government
Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism
Representative.
5. This project is to be in accordance with the current version of the EMS Environmental Protection
Statement. A copy of this document will be provided to bidding contractors via beta.sam.gov as an attachment.
6. This This project is to be in accordance with the current version of the 138FW Safety and Accident
Prevention Guide. A copy of this document will be provided to bidding contractors via https://sam.gov as an attachment.
7. The contractor shall apply all environmental health and safety procedures required by local, state and federal regulations.
8. All work to be performed 7:00 AM to 5:30 PM Monday thru Thursday in accordance with the general conditions stated in the general conditions of the specifications. If alternate work schedule is desired, it must be requested in writing and approved by CE and Security 48 hours prior to the desired schedule.
9. The contractor is required to provide an AF Form 103 (Dig Permit) prior to any earthwork.
10. The contractor is responsible for marking/locating all underground utilities. All base underground utilities are not covered by the Call OKIE service, contractor will be responsible for locating and marking those utilities as well. The only utilities that Call OKIE service will mark is Natural gas and
Cox communications. All other utilities to include base communications fiber optic lines, electric, sewer and water will be the contractor’s responsibility to mark. Contractor must have all utilities marked in an area before a dig permit is issued.
11. If a utility is damaged, the contractor will repair per current code specifications.
12. Prior to any work, the contractor shall submit for approval by CE, one electronic copy of technical literature for all products to be used. Provide Safety Data Sheets for all appropriate products. Provide form 889 for all equipment/items that can need maintenance or repairs where parts will need to be purchased to maintain or repair the equipment at a later date.
13. All DBIDS Contractor passes will be approved by the BCE and issued by SFS after completion of required background checks. Final payment to the general contractor will not be made at the completion of the construction project until all contractor badges have been returned or the continuing need is validated and documented in writing by SFS and BCE personnel.
14. Contractor will be responsible for keeping a log of all debris disposed of off base to include tonnage, volume, and disposal site. This data will need to be readily available through the project for semi-annual data calls or inspections.
15. Contractor will be responsible for submitting an interim 1354 when project is 50% completed and a final 1354 when the project is 100% complete as part of closeout documents.
CLIN 1 BASE BID
16. Perform all work stated or shown in plan set marked Commercial Inspection Facility and
Specifications marked OKANG Commercial Inspection Facility posted on beta.sam.gov with this solicitation.
a. Note options below are to be priced separately and are not to be included in CLIN 1 Base Bid pricing
17. In support of the Air Force/Air National Guard objective of capturing all built infrastructure in the
BUILDER Sustainment Management System (SMS), the contractor shall input data in the provided
Template for SMS BUILDER inputs. All data input will be in accordance with UNIFORMAT II structure. The contractor shall provide detail down to the component section level but include sufficient detail in the section sub-types and section name. Contractor shall provide data for columns
D-X. Any deviation will require concurrence from the government. If further options are exercised under the prescribed CLIN structure, contractor shall perform the same data input on the provided
Template for SMS BUILDER inputs.
CLIN 2 OPTION 1
18. SEE OPTION #1 on sheet CA101. All pavement shown as asphalt to be 6”PCC see detail 1 on sheet
CP 501 for the 6”PCC detail.
CLIN 3 OPTION 2
19. See OPTION #2 on sheet CA101. Addition of a visitor’s parking area NW of gates.
CLIN 4 OPTION 3
20. See OPTION # 3 on sheet CA101. Addition of Ameristar Impasse II fence with barrier cable at front entry in lieu of standard fence that is shown in details on sheet CS502.
CLIN 5 OPTION 4
21. See OPTION # 4 on sheet CA101. Mow Strip under all fencing and passive barrier throughout the project site.