EXHIBIT_A_Performance_Questionnaire.doc

DOC document 49 KB Posted

Attached to
Commercial Inspection Facility - Construction Federal contract opportunity
Solicitation number
W50S8U-22-R-0001
Issued by
Department of the Army National Guard

About this file

This solicitation is seeking proposals for construction of a Commercial Inspection Facility at the Tulsa Air National Guard Base in Tulsa, Oklahoma. The project magnitude is between $1,000,000 and $5,000,000, and has a North American Industry Classification System code of 236220 with a small business size standard of $39,500,000. The solicitation is 100% set aside for small businesses and offers options including different pavement and parking area configurations as well as fencing. Proposals are due in accordance with the solicitation, and award will be made based on best value as outlined in the document. Funds have been identified but are not yet available, so no award will be made until appropriations are in place.

View the file

Other files for this federal contract opportunity

Other files attached to Commercial Inspection Facility - Construction, newest first.
File Type Posted
Pre-Bid RFI CIF_1August22.pdf PDF
Brand_Name_Justification (Cisco_infrastructure) 1.0_Redacted.pdf PDF
Brand_Name_Justification (Corning_FODP) 1.0 s_Redacted.pdf PDF
Brand_Name_Justification Ameristar 1.1_Redacted.pdf PDF
W50S8U-22-R-0001 Amend 03 QA Extend Proposal Due Date.pdf PDF
Brand_Name_Justification (Telecor_PA) 1.0_Redacted.pdf PDF
Pre-Proposal RFI CIF_26July22.pdf PDF
Brand_Name_Justification Delta Scientific 1.1_Redacted.pdf PDF
Brand_Name_Justification Panduit_infrastructure) 1.0_Redacted.pdf PDF
ADDENDUM 2.pdf PDF
Brand_Name_Justification Gibralter 1.1_Redacted.pdf PDF
Brand_Name_Justification ALC 1.0_Redacted.pdf PDF
Brand_Name_Justification (Bosch_Camera) 1.0_Redacted.pdf PDF
Brand_Name_Justification (Aruba_Wireless) 1.0_Redacted.pdf PDF
Addendum 1.pdf PDF
W50S8U-22-R-0001 Amend 01 Proposal Due Dates.pdf PDF
W50S8U-22-R-0001 Amend 02 Extend Proposal Due Date.pdf PDF
Pre-Bid RFI CIF_20July22.pdf PDF
Pre-Proposal RFI CIF_7July22.pdf PDF
PreProposal Site Visit Minutes.pdf PDF
CIF Pre-proposal Attendance Sheet 23Jun22_Redacted.pdf PDF
CIF Pre-proposal slides.pptx PPTX presentation
EXHIBIT_D_Letter of Commitment.docx DOCX document
W50S8U-22-R-0001 Solicitation.pdf PDF
Attachment 3 Statement of Work.pdf PDF
Attachment 1c Final Design Submittal Specs.pdf PDF
Attachment 2 Commercial Inspection Facility Drawings.pdf PDF
Attachment 1a Electronic Submittals-Addendum 1.pdf PDF
Attachment 1d Final Design Submittal Specs from Pages 29-30.pdf PDF
Attachment 1b Electronic Submittals-Addendum 2.pdf PDF
EXHIBIT_B_Subktr_InfoandConsent.doc DOC document
EXHIBIT_C_Reference_Questionnaire_Package.docx DOCX document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912L6-22-R-0001 COMMERCIAL INSPECTION FACILITY (CIF)

EXHIBIT A PERFORMANCE RELEVANCY QUESTIONNAIRE

PART 1: Prepare questionnaires in the format provided.

Provide the following information requested in this format for each of the projects/contracts being described. Prepare not more than three (3) of these documents. Contractors should select their projects carefully because the quality of the contractor’s relevant performance is more important than the quantity of projects submitted. Projects may be on going, if complete to 70 %, and cannot have been completed any earlier than 5 years prior to the solicitation issue date. Provide frank, concise comments regarding your performance on the contracts you identify. Use as much space as required.

A. Offeror (Your) Name (Company/Division):

B. Project/Contract Title:

C. Contract Specifics:

1. Description of Effort as ___ Prime or ___ Subcontractor

2. Contract Number: _________________________________________

3. Original Contract Value $_______________ Current/Final Contract Value $____________________

4. If amounts in 3 above are different, provide a brief description of the reason:

5. Completion Date: ________________________________

6. Original Date: ______________

7. Current Schedule____________________

8. Estimated/Final Completion Date:________________________________

9. Primary cause for Contract Modifications__________________________________

D. Provide detailed description of the work performed under the contract including, but not limited to your past performance. Note that your description will be evaluated for similarity of the construction methods, particularly ________________ project scope; cost magnitude, and complexity of work performed to those required for the proposed effort. The Government may also consider similarity of the client type (i.e. federal government) and/or the project sustainability requirements. ANG projects will consider United States Green Building Council (USGBC) LEED®. The location at which work was performed to the location(s) at which work will be performed may also be considered.

1. Describe the specific elements of the work performed by your firm.

2. Indicate what elements of work were performed by your major subcontractors and if those same subcontractors will be used on this project. If you intend to use these subcontractors, please list name and principal areas of work they will perform. Indicate if you do not intend on utilizing any of these subcontractors.

3. Address any technical areas about this project you consider uniquely relevant to this project. Include in your discussion if project had sustainability requirements. Of particular interest are USGBC LEED® and the level of recognition received. Indicate if no such requirements.

4. If you intend to use any of the same key personnel on this solicitation’s project, indicate by name and position those personnel proposed to be utilized on the referenced contract. (Project Manager, Site Superintendent, Quality Control Manager). Indicate what position they will have on this solicitation’s contract. Indicate if you do not intend on utilizing any of these same personnel.

5. Describe why you believe the work is very relevant, relevant or semi-relevant to this solicited project. (see Section 00120 for information.) (Use as much space as necessary)

E. List a point of Contact for Owner/Government agency Contracting Officer and/or inspector; include a current phone number and email address. (This information is required here even though you will be sending Exhibit C letters and questionnaires to these references. (Do NOT include a copy of the Exhibit Cs you sent to your references.)) End of Part 1 - Questionnaire Requirements – Prepare and send Exhibit C Package to the reference(s) for each of projects discussed in the Exhibit As.

PART 2: Provide the following information one time.

Additional offeror information required, but not project specific. This information need only be provided once in your submission package.

2 A. Applicable to all offerors - Describe your compliance with the requirements of FAR clause 52.219-8 Utilization of Small Business Concerns. Even if you are a Small or Small Disadvantaged Business, this clause in Federal Contracts applies. It is the policy of the United States that small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns shall have the maximum practicable opportunity to participate in performing contracts let by any Federal agency, including contracts and subcontracts for subsystems, assemblies, components, and related services for major systems. It is also policy to establish procedures to ensure the timely payment of amounts due pursuant to the terms of their subcontracts. Describe below the methods you have used to comply with this policy on prior federal contracts. Include any evidence, or a point of contact to verify this information, if available.

2B: Offerors are strongly encouraged to include with their proposals information on problems encountered on relevant projects and the specific corrective actions taken to remedy the problem(s).

2C: List any projects within the last five (5) years that have been assessed Liquidated damages. If none have been assessed, make a positive statement to that effect.

2D: List any projects within the last five (5) years that have been terminated, for any reason. Provide an explanation. If none, make a positive statement to that effect.

2E. Compliance with Safety Standards. Provide proof of your Experience Modification Rate (EMR).

End of Questionnaire Requirements