NJ ANG F-16 MTC Flight Sim - AQRC 189015 Addm No 5 - Spec Sect 01_45_00 - Attmts.pdf

PDF 355 KB Posted

Attached to
Construction of F16 Mission Training Center
Solicitation number
W50S8F-26-R-A011
Issued by

About this file

This document is Addendum No. 5 (dated July 10, 2026) to a federal construction contract for the NJANG F-16 MTC (Flight Simulator Facility) at Atlantic City Air National Guard Base, New Jersey. It specifies Quality Control (QC) specialist qualifications, areas of responsibility, and surveillance frequency requirements for eight distinct construction disciplines, and provides a detailed Schedule of Fire Protection System Inspections by the Fire Protection QC (FPQC) Specialist.

The QC Specialist Experience Matrix establishes minimum qualifications for Civil, Structural, Architectural, Mechanical, Electrical, Fire Protection, Communications/ESS, and Roofing specialists. Requirements vary by discipline—for example, Civil requires a graduate Civil Engineer with PE and 2 years experience or a technician with 5 years experience; Structural requires a graduate Structural Engineer with 2 years experience or 5 years inspection experience; and Fire Protection requires NICET Level III/IV certification or Registered Fire Protection Engineer status. All specialists must perform weekly surveillance during their respective installation phases. The Fire Protection QC schedule divides surveillance into three phases: (1) Surveillance During Construction, including visual inspections and observations of fire suppression systems, special fire suppression systems, passive fire protection, and fire alarm systems; (2) Pre-Final Acceptance Inspection, requiring the FPQC to inspect all fire protection and life safety systems, witness functional testing, identify deficiencies, and certify conformance; and (3) Final Acceptance Inspection, requiring verification of proper installation and operation, end-to-end fire alarm testing, and certification that all deficiencies have been corrected. Documentation in FPQC Reports per UFGS 01 45 00 is mandatory for all inspections and observations, with deficiencies recorded in a rework list.

View the file

Other files

File Type Posted
Solicitation Amendment W50S8F26RA0110004 SF 30.pdf PDF
Solicitation Amendment (SF1442) - W50S8F26RA0110004.pdf PDF
Solicitation Amendment W50S8F26RA0110003 SF 30.pdf PDF
2025 Projectmates ANG.pdf PDF
NJ ANG F-16 MTC Flight Sim - AQRC 189015 Addm No 5 - Drawing.pdf PDF
F16 MTC Pre-Proposal RFI Log as of 10 July 2026.pdf PDF
Solicitation Amendment W50S8F26RA0110002 SF 30.pdf PDF
NJ ANG F-16 MTC Flight Sim - AQRC 189015 Addm No 5 - Narrative.pdf PDF
Solicitation Amendment W50S8F26RA0110001 SF 30-Proposal due date extension to 17 July 2026.pdf PDF
F16 MTC Pre-Proposal RFI Log as of 24 June 2026.pdf PDF
Pre-Proposal - Site Visit Sign_In.pdf PDF
MTC Pre-Proposal Conf Presentation.pdf PDF
SAM RFI update - F16 MTC 23 June 26.pdf PDF
Addendum No. 4 - AQRC 189015 Addm No 4 - Narrative.pdf PDF
013.5 - Geotechnical Engineering Report.pdf PDF
012.1 - AQRD 189015 - NJ ANG F-16 MTC - Specifications Vol. 1 - Type B-3.pdf PDF
EXHIBIT C Reference Questionnaire Package - MTC.docx DOCX document
012.2 - AQRD 189015 - NJ ANG F-16 MTC - Specifications Vol. 2 - Type B-3.pdf PDF
Exhibit A MTC.docx DOCX document
Addendum No.3 - Updated Specs and Drawings 0136.pdf PDF
EXHIBIT B MTC.docx DOCX document
Solicitation - W50S8F26RA011-Construction of F-16 MTC.pdf PDF
013.1 - AQRD 189015 - NJ ANG F-16 MTC - Drawings - Type B-3.pdf PDF
Exhibit D_Letter of Commitment MTC.docx DOCX document
Addendum No. 1 - Boring log info for Storm water 013.3.pdf PDF
Addendum No. 4-Excess Haul Route - Drawings.pdf PDF
Addendum No. 2 - Security Items Clarification 013.4.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AFB JV | Atkins / Black & Veatch / FSB

QC Specialist Experience Matrix Addendum No. 5 July 10, 2026

Project: NJANG F-16 MTC (Flight Simulator Facility – Atlantic City ANGB, NJ

QC Area Minimum Qualifications Area of Responsibility QC Surveillance Frequency

Assigned QC Specialist

Civil Graduate Civil Engineer or Construction Man-ager with PE (preferred) and 2 years experi-ence, or Technician with 5 years experience

Earthwork, utilities, paving, grad-ing, erosion control

Weekly during site work; periodic thereafter

(TBD)

Structural Graduate Structural Engineer or PE with 2 years experience, or 5 years structural in-spection experience

Foundations, reinforcing steel, anchor bolts, structural steel, welding, concrete placement

Weekly during structural work

(TBD)

Architectural 5 years experience inspecting architectural finishes

Masonry, drywall, ceilings, doors, hardware, finishes, roofing, water-proofing

Weekly during ar-chitectural work

(TBD)

Mechanical Graduate Mechanical Engineer or Licensed Mechanical Contractor with 2 years experi-ence, or 5 years field supervision

HVAC, plumbing, TAB, controls, insulation, piping, equipment startup

Weekly during in-stallation and startup

(TBD)

Electrical Graduate Electrical Engineer or Licensed Master Electrician with 2 years experience, or 5 years field supervision

Power distribution, lighting, grounding, generators, UPS, fire alarm interfaces

Weekly during electrical installa-tion

(TBD)

Fire Protec-tion

NICET Level III/IV or Registered Fire Protec-tion Engineer

Sprinkler systems, fire alarm, ac-ceptance testing

Weekly installation and all testing

(TBD)

Communica-tions/ESS

BICSI RCDD or manufacturer-certified techni-cian with 5 years experience

Structured cabling, IDS, ACS, CCTV, fiber optic systems

Weekly during in-stallation and com-missioning

(TBD)

Roofing Manufacturer-certified roofing inspector Roofing installation, flashing, test-ing, warranty inspections

Weekly during roof-ing work

(TBD)

SCHEDULE OF FIRE PROTECTION SYSTEM

INSPECTIONS BY FPQC SPECIALIST

1. INSTRUCTIONS for FPQC Specialist:

Perform surveillance of fire protection system installation during construction and during pre-final and final acceptance inspections. Surveillance includes either visual inspections or observations performed by the FPQC as indicated in the following Schedule of Fire Protection System Inspections.

Check boxes in the schedule indicate the inspections or observations that are applicable to this project, which must be performed and documented by the FPQC.

Surveillance of fire protection system inspections is divided into three phases:

Surveillance During Construction – Includes periodic on-site visits by the FPQC during construction

Pre-Final Acceptance Inspection – FPQC must be onsite during pre-final acceptance inspection

Final Acceptance inspection – FPQC must be onsite during final acceptance inspection

2. INSPECTION TYPE

VISUAL INSPECTION:

Perform on-site visual inspections as indicated in the Schedule of Fire Protection System Inspections as construction progresses to confirm work conforms with the contract requirements including but not limited to verifying proper installation of equipment and materials in accordance with applicable codes. Where work will be covered up by finished walls and ceilings, inspections must be scheduled and performed when work is still visible.

OBSERVATION:

Observe component and system testing in person on-site as indicated in the Schedule of Fire Protection System Inspections. Confirm testing is completed in accordance with applicable codes and that testing was successful.

DOCUMENTATION:

Document all inspections and observations in the FPQC Report in accordance with UFGS 01 45 00.

Document any deficiencies and all work observed that has been successfully performed in accordance with the contract documents. Record deficiencies in the rework list.

Addedum No. 5, dated July 10, 2026

PERFORM SURVEILLANCE DURING CONSTRUCTION

~ FIRE SUPPRESSION SYSTEM ~

PERFORM

TASK IF

CHECKED

TASK

INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper installation of underground service main and service; laterals, thrust blocks, tie-rods and connection to above ground piping.

VISUAL

INSPECTION

✓ Visually inspect materials

✓ Visually inspect installation

☒ 2. Verify proper orientation of fire hydrants and fire department access

VISUAL

INSPECTION

✓ Visually inspect installation and orientation

☐ 3. Verify proper installation of interior and exterior attachments, coatings, and vortex plate prior to filling fire protection water tank

VISUAL

INSPECTION

✓ Visually inspect fire protection water tank installation

☒ 4. Hydrostatic/leak test for underground piping

OBSERVE ✓ Verify proper test method

✓ Confirm test was successful

☒ 5. Hydrostatic/leak test for above ground piping prior to ceiling installation

OBSERVE ✓ Verify proper test method

✓ Confirm test was successful

☒ 6. Underground system flush prior to connection to the riser

OBSERVE ✓ Verify system was properly flushed

☒ 7. Forward flow and cross connection control test for Backflow preventer

OBSERVE ✓ Verify proper test method

✓ Confirm test was successful

☒ 8. Suction pipe flush prior to fire pump startup

OBSERVE ✓ Verify system was properly flushed

☒ 9. Hydrostatic test fire pump suction and discharge piping

OBSERVE ✓ Verify proper test method

✓ Confirm test was successful

☒ 10. Fire pump startup OBSERVE ✓ Confirm successful startup

☒ 11. Verify proper installation of sprinkler piping prior to wall or ceiling installation

VISUAL

INSPECTION

✓ Inspect pipe hangars, bracing, sprinkler heads

✓ Inspect for sprinkler obstructions;

damaged, painted or covered heads

✓ Verify proper location of control valves, drains, vents, backflow, test header

✓ Verify proper component mounting heights

☒ 12. Document inspections and observations in FPQC Report

DOCUMENT ✓ Submit report for each day inspections or observations occur

✓ Annotate deficiencies and satisfactory work observed

✓ Record rework items in FPQC report

~ SPECIAL FIRE SUPPRESSION SYSTEM ~

PERFORM

TASK IF

CHECKED

TASK

INSPECTION

TYPE DESCRIPTION

☐ 1. Verify proper installation of gaseous fire suppression system

VISUAL

INSPECTION

✓ Inspect gas cylinders, initiating controls, shutdowns, aborts, and visual warning

☐ 2. Verify proper installation of IR hangar detector

VISUAL

INSPECTION

✓ Inspect detector and nozzle layout

✓ Inspect for obstructions, abort stations

✓ Inspect riser piping

☐ 3. Verify proper installation of elevator fire protection

VISUAL

INSPECTION

✓ Inspect elevator recall functions

✓ Inspect two-way communication

☒ 4. Verify proper installation of fire suppression in secure spaces

VISUAL

INSPECTION

✓ Inspect location of sprinkler piping and sprinklers

☒ 5. Document inspections and observations in FPQC Report

DOCUMENT ✓ Submit report for each day inspections or observations occur

✓ Document deficiencies and satisfactory work observed in FPQC Report

✓ Record deficiencies in rework list

~ PASSIVE FIRE PROTECTION SYSTEMS ~

PERFORM

TASK IF

CHECKED

TASK

INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper construction of fire rated assemblies

VISUAL

INSPECTION

✓ Inspect partitions for proper fire rated construction per design

✓ Inspect doors and door hardware for proper fire rating

✓ Inspect glass for proper fire rating

☐ 2. Verify proper installation of fireproofing

VISUAL

INSPECTION

✓ Inspect for use of proper fireproofing materials

✓ Inspect for cracking, spalling or delaminating

✓ Inspect for proper application thickness

☒ 3. Verify proper installation of firestopping

VISUAL

INSPECTION

✓ Inspect to confirm firestopping system is UL tested or an engineering judgement has been obtained and submitted

✓ Inspect for use of proper firestopping materials

✓ Inspect penetrations through fire rated walls, partitions and ceilings

✓ Inspect construction joints and gaps

☒ 4. Document inspections and observations in FPQC Report

DOCUMENT ✓ Submit report for each day inspections or observations occur

✓ Document deficiencies and satisfactory work observed in FPQC Report

✓ Record deficiencies in rework list

~ FIRE ALARM SYSTEMS ~

PERFORM

TASK IF

CHECKED

TASK

INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper installation of fire alarm system after conduit is installed and wiring pulled, but before devices are installed

VISUAL

INSPECTION

✓ Inspect conduit, wiring, conduit fill, wire type

✓ Inspect installation heights of back boxes

☒ 2. Document inspections and observations in FPQC Report

DOCUMENT ✓ Submit report for each day inspections or observations occur

✓ Document deficiencies and satisfactory work observed in FPQC Report

✓ Record deficiencies in rework list

~ END OF SURVEILLANCE DURING CONSTRUCTION SECTION

PERFORM DURING PRE-FINAL ACCEPTANCE INSPECTION

PERFORM

TASK IF

CHECKED

TASK

INSPECTION

TYPE DESCRIPTION

☒ 1. Inspect all fire protection systems and all life safety features

VISUAL

INSPECTION

✓ Verify proper installation of fire protection and life safety systems

☒ 2. Witness functional testing of all fire protection and life safety systems

OBSERVE ✓ Verify proper testing is performed on fire protection and life safety systems

☒ 3. Identify deficiencies that require correction

VISUAL

INSPECTION

✓ Document deficiencies in FPQC Report and record in rework list

☒ 4. Verify rework items have been corrected

VISUAL

INSPECTION

✓ Record re-inspection results on FPQC Report

☒ 5. Document results of pre-final inspection and photograph unsatisfactory conditions

DOCUMENT ✓ Document results of pre-final inspection in FPQC Report

☒ 6. Certify installation and operation of all fire protection and life safety systems conform to the contract documents

DOCUMENT ✓ Provide separate letter certifying conformance with contract requirements

~ END OF PRE-FINAL INSPECTION SECTION

PERFORM DURING FINAL ACCEPTANCE INSPECTION

PERFORM

TASK IF

CHECKED

TASK

INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper installation and operation of all fire protection systems and all life safety features

VISUAL

INSPECTION

✓ Witness final acceptance testing

✓ End-to-end testing of fire alarm system

☒ 2. Note any deficiencies identified by Government FPE on deficiency list

DOCUMENT ✓ Document deficiencies identified by Government FPE on deficiency list

☒ 3. Verify all deficiencies have been corrected

VISUAL

INSPECTION

✓ Inspect rework to confirm all deficiencies have been corrected

☒ 4. Certify that all deficiencies have been corrected

DOCUMENT ✓ Document inspection results on FPQC Report

~ END OF FINAL ACCEPTANCE INSPECTION SECTION