Specifications - Vol 1.pdf

PDF 4 MB Posted

Attached to
Repair and Add to Maintenance Complex - Hangar B Project Federal contract opportunity
Solicitation number
W50S8E22B0001
Issued by
Department of the Army New York Army National Guard

About this file

This pre-solicitation notice describes an upcoming Invitation for Bid for repair and addition services at a maintenance hangar complex. The 106th Rescue Wing of the New York Air National Guard will issue the solicitation to award a single firm fixed-price contract. Services will include renovating and adding to an existing aircraft hangar, with an option to install new communications wiring. The contract duration is 365 days with a magnitude of construction over $10 million. The project is set aside 100% for small businesses under NAICS code 236220 with a size standard of $39.5 million. The tentative solicitation date is October 25, 2021 with a pre-bid conference on November 10, 2021 and bid opening on November 23, 2021. Interested offerors must register in SAM and check the website periodically for any amendments.

View the file

Other files for this federal contract opportunity

Other files attached to Repair and Add to Maintenance Complex - Hangar B Project, newest first.
File Type Posted
Abstract of Offers Page 1.pdf PDF
Abstract of Offers Page 3.pdf PDF
Abstract of Offers Page 2.pdf PDF
Attendance Sheet.pdf PDF
RFI 50.pdf PDF
10 22 19.pdf PDF
Attachment A Modified - Specifications Addendum.pdf PDF
W50S8E22B0001 0003.pdf PDF
RFI 48-49.pdf PDF
WS0S8E22B0001 - Blank Vetting Form.xlsx XLSX spreadsheet
RFI 45-47.pdf PDF
RFI 36-44.pdf PDF
RFI 32-35.pdf PDF
W50S8E22B0001 0002.pdf PDF
RFI 17-31.pdf PDF
10 51 13 - Metal Lockers.pdf PDF
W50S8E22B0001 0001.pdf PDF
RFI 1-16.pdf PDF
Attendance Sheet Page 2.pdf PDF
PREBID Conference Slides.pdf PDF
Attendance Sheet Page 1.pdf PDF
PreBid Site Visit Photos_20220518.pdf PDF
Attachment A - Specifications Addendum.pdf PDF
Drawings.pdf PDF
Specifications - Vol 2.pdf PDF
Solicitation W50S8E22B0001.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

New York Air National Guard

Project No’s. WKVB122004 & WKVB139002

Repair and Add To Building 358

Gabreski Air National Guard Base

Westhampton Beach, NY

Project Manual Volume 1 of 2

April 2022

100% B-3 Submittal (Issue for Bid)

Proposer’s Name and Address

ADD TO & REPAIR MAINTENANCE HANGAR

BUILDING 358

PROJECT NUMBERS: WKVB139002 & WKVB122004

106TH RESCUE WING

NEW YORK AIR NATIONAL GUARD

GABRESKI AIR NATIONAL GUARD BASE

WESTHAMPTON BEACH, NY

INDEX AND CERTIFICATION PAGE

SPECIFICATION INDEX

DOCUMENT / DIVISION

DESCRIPTION

DIVISION 01 GENERAL REQUIREMENTS

DIVISION 02 EXISTING CONDITIONS

DIVISION 03

DIVISION 04

CONCRETE

MASONRY

DIVISION 05

DIVISION 06

METALS

WOOD, PLASTICS, AND COMPOSITES

DIVISION 07 THERMAL AND MOISTURE PROTECTION

DIVISION 08 OPENINGS

DIVISION 09

DIVISION 10

DIVISION 11

DIVISION 12

DIVISION 13

FINISHES

SPECIALITIES

EQUIPMENT

FURNISHINGS

SPECIAL CONSTRUCTION

DIVISION 21 FIRE SUPPRESSION

DIVISION 22 PLUMBING

DIVISION 23 HEATING, VENTILATING AND AIR

CONDITIONING

DIVISION 26 ELECTRICAL

DIVISION 27 COMMUNICATIONS

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

DIVISION 31 EARTHWORK

DIVISION 32 EXTERIOR IMPROVEMENTS

DIVISION 33

UTILITIES

CERTIFICATION(S)

WKVB139002/WKVB122004 Add To & Repair MXG Hangar, Building 358 79722 Gabreski ANGB, Westhampton Beach, NY

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 08/15 SUMMARY OF WORK

01 14 00 11/11 WORK RESTRICTIONS

01 30 00 08/15 ADMINISTRATIVE REQUIREMENTS

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY

SUPPORT CONTRACT MANAGEMENT SYSTEM

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18 SUBMITTAL PROCEDURES

01 33 29 02/15 SUSTAINABILITY REPORTING

01 35 26 11/15 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 02/10 QUALITY CONTROL

01 45 35 02/15 SPECIAL INSPECTIONS

01 50 00 08/09 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 11/15 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.00 20 04/16 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 20.00 10 04/06 ENVIRONMENTAL PROTECTION

01 57 23 04/08 TEMPORARY STORM WATER POLLUTION CONTROL

01 58 00 04/16 PROJECT IDENTIFICATION

01 74 19 01/07 CONSTRUCTION AND DEMOLITION WASTE

MANAGEMENT

01 75 00.00 40 05/15 STARTING AND ADJUSTING

01 78 00 08/11 CLOSEOUT SUBMITTALS

01 78 23 08/15 OPERATION AND MAINTENANCE DATA

01 91 00.00 40 11/12 COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 05/10 DEMOLITION

DI VI SI ON 03 - CONCRETE

03 11 13.00 10 05/14 STRUCTURAL CAST-IN-PLACE CONCRETE

FORMING

03 15 00.00 10 05/14 CONCRETE ACCESSORIES

03 20 00.00 10 05/14 CONCRETE REINFORCING

03 30 00 02/19 CAST-IN-PLACE CONCRETE

03 35 00.00 10 05/14 CONCRETE FINISHING

03 39 00.00 10 05/14 CONCRETE CURING

DI VI SI ON 04 - MASONRY

04 20 00 11/15 UNIT MASONRY

DI VI SI ON 05 - METALS

05 12 00 08/18 STRUCTURAL STEEL

05 50 13 05/10 MISCELLANEOUS METAL FABRICATIONS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 02/12 ROUGH CARPENTRY

06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/10 SOLID POLYMER (SOLID SURFACING)

PROJECT TABLE OF CONTENTS Page 1

FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 11 13 08/11 BITUMINOUS DAMPPROOFING

07 21 13 05/11 BOARD AND BLOCK INSULATION

07 21 16 11/11 MINERAL FIBER BLANKET INSULATION

07 27 36 05/17 SPRAY FOAM AIR BARRIERS

07 42 63 05/11 FABRICATED WALL PANEL ASSEMBLIES

07 53 23 05/12 ETHYLENE-PROPYLENE-DIENE-MONOMER

ROOFING

07 60 00 08/08 FLASHING AND SHEET METAL

07 61 14.00 20 05/11 STEEL STANDING SEAM ROOFING

07 72 53 03/16 SNOW GUARDS

07 84 00 05/10 FIRESTOPPING

07 92 00.00 06 06/15 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 02/10 STEEL DOORS AND FRAMES

08 14 00 08/16 WOOD DOORS

08 33 23 08/15 OVERHEAD COILING DOORS

08 51 13 05/11 ALUMINUM WINDOWS

08 71 00 02/16 DOOR HARDWARE

08 81 00 08/11 GLAZING

08 91 00 05/11 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 06 00 05/09 SCHEDULES FOR FINISHES

09 22 00 02/10 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 05/11 GYPSUM BOARD

09 30 10 11/13 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 08/10 ACOUSTICAL CEILINGS

09 65 00 08/10 RESILIENT FLOORING

09 68 00 11/13 CARPETING

09 90 00 05/11 PAINTS AND COATINGS

DI VI SI ON 10 - SPECI ALTI ES

10 11 00 02/09 VISUAL DISPLAY UNITS

10 14 00.20 11/12 INTERIOR SIGNAGE

10 21 13 01/07 TOILET COMPARTMENTS

10 26 00 08/17 WALL AND DOOR PROTECTION

10 28 13 07/06 TOILET ACCESSORIES

DI VI SI ON 11 - EQUI PMENT

11 81 29 03/16 AIRCRAFT MAINTENANCE FALL PROTECTION

SYSTEMS

DI VI SI ON 12 - FURNI SHI NGS

12 21 00 08/10 WINDOW BLINDS

12 93 00 02/09 SITE FURNISHINGS

DI VI SI ON 13 - SPECI AL CONSTRUCTI ON

13 34 19 11/11 METAL BUILDING SYSTEMS

PROJECT TABLE OF CONTENTS Page 2

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13.00 10 05/09 WET PIPE SPRINKLER SYSTEM, FIRE

PROTECTION

DI VI SI ON 22 - PLUMBI NG

22 00 00 11/15 PLUMBING, GENERAL PURPOSE

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 00 00 08/18 AIR SUPPLY, DISTRIBUTION, VENTILATION,

AND EXHAUST SYSTEMS

23 03 00.00 20 08/10 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 02/14 COMMON PIPING FOR HVAC

23 05 48.00 40 08/15 VIBRATION AND SEISMIC CONTROLS FOR

HVAC PIPING AND EQUIPMENT

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 09 00 02/19 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 11 25 11/08 FACILITY GAS PIPING

23 21 23 08/17 HYDRONIC PUMPS

23 23 00 10/07 REFRIGERANT PIPING

23 31 13.00 40 05/16 METAL DUCTS

23 35 19.00 20 02/10 INDUSTRIAL VENTILATION AND EXHAUST

23 52 00 04/08 HEATING BOILERS

23 54 16.00 10 04/08 HEATING SYSTEM; GAS-FIRED HEATERS

23 74 33.00 40 05/17 PACKAGED, OUTDOOR, HEATING AND COOLING

MAKEUP AIR-CONDITIONERS

23 81 00 05/18 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 81 23.00 20 02/10 COMPUTER ROOM AIR CONDITIONING UNITS

23 82 46.00 40 05/17 ELECTRIC UNIT HEATERS

DI VI SI ON 26 - ELECTRI CAL

26 00 00.00 20 07/06 BASIC ELECTRICAL MATERIALS AND METHODS

26 20 00 02/14 INTERIOR DISTRIBUTION SYSTEM

26 24 13 05/15 SWITCHBOARDS

26 29 23 04/06 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER

600 VOLTS

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 51 00 05/16 INTERIOR LIGHTING

26 56 00 05/13 EXTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 28.36 40 05/17 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 05 29.00 10 08/11 PROTECTIVE DISTRIBUTION SYSTEM (PDS)

FOR SIPRNET COMMUNICATION SYSTEMS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

PROJECT TABLE OF CONTENTS Page 3

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 05 26.00 40 08/13 GROUNDING AND BONDING FOR ELECTRONIC

SAFETY AND SECURITY

28 08 10 05/16 ELECTRONIC SECURITY SYSTEM ACCEPTANCE

TESTING

28 31 76 08/11 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM

DI VI SI ON 31 - EARTHWORK

31 00 00 08/08 EARTHWORK

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 16.17 08/08 COLD MILLING OF BITUMINOUS PAVEMENTS

32 11 23 08/08 AGGREGATE BASE COURSE

32 12 10 08/08 BITUMINOUS TACK AND PRIME COATS

32 12 16 08/09 HOT-MIX ASPHALT (HMA) FOR ROADS

32 16 13 04/08 CONCRETE SIDEWALKS AND CURBS AND

GUTTERS

32 92 19 10/06 SEEDING

DI VI SI ON 33 - UTI LI TI ES

33 11 00 02/11 WATER DISTRIBUTION

33 30 00 04/08 SANITARY SEWERS

33 31 23.00 10 08/18 SANITARY SEWER FORCE MAIN PIPING

33 40 00 02/10 STORM DRAINAGE UTILITIES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests

Utility Connection Requests

Borrow Permits

Excavation Permits

Welding Permits

Burning Permits

Salvage Plan; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

Building 358, Hangar B, is an existing hangar facility, which requires both renovation under Project Number WKVB122004 and an addition under Project Number WKVB139002. For the renovation, the Project includes to renovate and reconfigure interior shop spaces, utility, mechanical, electrical and fire protection/protection systems. The Project also includes to isolate the maintenance hangar bay from non-associated shop and administrative spaces and replace HVAC and fume extraction systems.

Provide new mass notification system for the entire building. The Project shall also comply with all required sustainability requirements.

For the addition, the Project Scope is to construct a general purpose maintenance shop addition to the existing hangar and maintenance shop complex utilizing a pre-engineered metal building. The facility will be compatible with applicable DOD, Air Force, and base standards. The addition will be architecturally compatible with the existing hangar facility.

This Project also includes modifications to the site surrounding the facility inclusive of, but not limited to, pavement removal, utility relocation, and stormwater management upgrades.

SECTION 01 11 00 Page 1

The Contractor shall refer to the Contract Documents (both plans and Specifications) for the complete scope of the Project.

The following bid options have been identified: WKVB122004:

a. Option 1 - Communication Work:

(1) All work under WKVB122004 "Repair" to include cable, faceplates, terminations, testing, etc., as described in the Contract Document Plan Set Drawings.

The Project required compliance with LEED requirements set forth by the U.S. Green Building Council to obtain silver certification.

1.2.2 Location

The work is located at the Gabreski Air National Guard Base in Westhampton Beach, New York, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 CONTRACT DRAWINGS

The following Drawings accompany this Specification and are a part thereof.

Two sets of full size Contract Drawings, maps, and Specifications will be furnished to the Contractor without charge. Reference publications will not be furnished. Immediately check furnished Drawings and notify the Government of any discrepancies.

1.4 WORK RESCHEDULING

Contractor shall allow time in their anticipated schedule to submit and procure all required permits for the renovation/construction and site work for the Project. The Schedule shall be submitted to the Government for approval prior to the start of construction activities.

Normal duty hours for work are from 7:30 a.m. to 5 p.m., Monday through Friday. Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.

1.5 OCCUPANCY OF PREMISES

The building will not be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.6 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as

SECTION 01 11 00 Page 2 approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.7 ON-SITE PERMITS

1.7.1 Utility Outage Requests and Utility Connection Requests

Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 21 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.7.2 Borrow, Excavation, Welding, and Burning Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Excavation Permits 14 calendar days prior to work Base Safety and Environmental Office

Post permits at a conspicuous location in the construction area.

Burning of trash or rubbish is not permitted on Project Site.

1.8 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 72 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on Contract Drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.8.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting

SECTION 01 11 00 Page 3 excavation work.

1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

Pursuant to Contract Clause "FAR 52.245-1, Government Property", the Government will furnish the following materials and equipment for installation by the Contractor:

Contractor shall be provided with certain materials and equipment from the Government to be installed in the facility. The Contractor shall coordinate with the Base Civil Engineer and Contracting Officer. Items have been identified in the Contract Document Drawings.

Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary.

Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Provide any additional quantities that are required.

1.9.1 Delivery Schedule

Notify the Contracting Officer in writing at least 30 calendar days in advance of the date on which the materials and equipment are required.

Pick up materials and equipment no later than 30 calendar days after such date.

1.10 GOVERNMENT-INSTALLED WORK

Materials and equipment that is Government-installed shall be coordinated with the Contractor in alignment with their Construction Schedule.

1.11 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver, and off-load the salvaged property at the Government designated storage area located within 2 miles of the construction site.

Provide a salvage plan, listing material, and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

-- End of Section --

SECTION 01 11 00 Page 4

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 State

"State" when used in reference to states of the United States.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval or for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

A list of items shall be provided to the Contractor by the Contracting Officer at the preconstruction meeting. The Contracting Officer shall identify items, which shall be submitted prior to construction activity at said meeting.

1.3 SPECIAL SCHEDULING REQUIREMENTS

a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:

(1) Site clearing, site demolition, and building demolition.

b. The facility will not remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity. Other facilities on-base.

c. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.

d. The work under this Contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the Construction Schedule each factor which constitutes a potential interruption to operations.

The following conditions apply:

(1) Temporary Power.

SECTION 01 14 00 Page 1

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic, and security regulations. Keep within the limits of the work and avenues of ingress and egress. Ingress and egress of Contractor vehicles at the Activity is limited to the main Base entry gate. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.4.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and Subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.1.2 Identification Badges and Installation Access

The Contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services, or local Security Office. The Contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

a. All Contractor employees and Subcontractors shall register through the Defense Biometric Identification System (DBIDS) website through the following link to request entry to the installation:

https://dbids-global-enroll.dmdc.mil/preenrollui/

b. Unscheduled gate closures by the Security Forces may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. The Contractor is responsible for requesting compensation for any lost time through the CO for approval. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations.

Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

c. The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt

SECTION 01 14 00 Page 2 evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

d. The Contractor is responsible for ensuring proper documentation is received for personnel passes in time to avoid any delay in project start of performance. Any additional time required for obtaining badges and passes as required for access to the installation will not necessarily be grounds for additional time granted to complete the project, if passes are delayed due to Contractor actions. All traffic will enter through the Main Gate. The Government reserves the right to deny access to any person, with no consequence to the contract. All contractor personnel shall prominently display the visitor’s badge at all times while on the installation.

e. All vehicles entering the installation must have a valid registration in the respective state of registration, proof of insurance, safety inspection, and car rental agreement, if applicable.

1.4.1.3 Employee List

The Contractor must provide to the Contracting Officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and Subcontractor's employees prior to commencement of work under this Contract.

1.4.1.4 Personnel Entry Approval

Failure to obtain entry approval will not affect the Contract Price or time of completion.

1.4.1.5 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.4.2 Working Hours

Regular working hours must consist of an 9 hour period established by the Contractor Officer, between 7:30 a.m. and 5 p.m., Monday through Friday, excluding Government holidays.

1.4.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 7 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, Contract Number and Project Title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, unless directed otherwise.

SECTION 01 14 00 Page 3

1.4.4 Exclusionary Period

No work must be performed during the period 5 p.m. to 7 a.m., inclusive, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this Contract.

1.4.5 Occupied and Existing Building

The Contractor shall be working in an existing building and around existing buildings which are occupied. Do not enter the building without prior approval of the Contracting Officer.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains and Government material during the construction period.

Government shall relocate movable furniture away from the Contractor's working area as required to perform the work. Leave attached equipment in place, and protect against damage, or temporarily disconnect, relocate, protect, and reinstall at the completion of the work. Contractor to coordinate this effort with Contracting Officer.

The Government will remove other Government property in the areas of the building scheduled to receive work.

1.4.6 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays. Conform to procedures required Paragraph "Work Outside Regular Hours".

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the Paragraph "Work Outside Regular Hours".

d. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain. Obtain Installation's Sanitary Sewer Connection Permit 2 weeks prior to connection and in accordance with Section 33 30 00 SANITARY SEWERS.

1.5 SECURITY REQUIREMENTS

1.5.1 Personnel List

Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the Project. Furnish for each person:

a. Name.

SECTION 01 14 00 Page 4

b. Date and place of birth.

c. Citizenship.

d. Home address.

e. Social security number.

f. Current pass expiration date.

g. Naturalization or Alien Registration number.

h. Passport number, place of issue, and expiration date.

The request for personnel passes must be accompanied with the following certification:

"I hereby certify that all personnel on this list are either born U.S.

citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."

1.5.2 Vehicle List

Submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:

a. Make.

b. Year.

c. Model.

d. License number.

e. Registered owner.

1.6 PERSONALLY OWNED PORTABLE ELECTRONIC DEVICE (PED) FUNCTIONALITY MATRIX

PED Funct i onal i t y/ Devi ce Type Exampl e Devi ce PSNS & I MF Wor k Ar eas

Any photographic or image capturing capability

Camera, Video Recorder Camera Cell Phone, Scanner

Allowed with Restrictions

Single-function cell phone Allowed

Multi-function cell phone Allowed

Wireless transmitting capabilities

WIFI, 802.xx, Bluetooth

Allowed if turned off

RF receivers Pager, AM/FM Radio, Satellite Radio

Allowed

SECTION 01 14 00 Page 5

PED Funct i onal i t y/ Devi ce Type Exampl e Devi ce PSNS & I MF Wor k Ar eas

RF transmitter RF Radio Transceiver Written

Walkie-talkie Approval Required

Primary function audio recording devices

Digital voice recorders

Prohibited

Play-Only Devices without removable memory

MP3 players, CD Players, Digital Picture Frames, Digital Books

Allowed

Removable storage media Memory Sticks, Thumb Drives, Flash Memory, SD Card

Prohibited

PEDs capable of connecting to Government-owned systems without interface cables or cradles

Built-in USB Adapter Prohibited

Cables and cradles for privately owned PEDs connecting to a computer system

MP3 Player to USB Cable

Prohibited

No PED device is allowed within 10 ft of Classified Information/Work.

The use of personally owned PEDs to process or store Government data/information is prohibited.

Additional Definitions on PED Functionality/Device Types

Single-function cell phones are defined as cellular devices with no additional photographic or network capabilities (can only be used for voice or text message communications over a cellular network, storage of speed dial caller ID information, and limited voice recording). SIM cards/embedded memory for cell phones are permitted.

Multi-function cell phone and PEDs with more than one functionality are controlled based on the most restrictive capability identified in this matrix.

An RF transmitter is defined as any radio frequency transmitter with the exception of single-function cell phones, which are addressed separately.

CD Players capable of playing CD, CD-R, CD-RW, and MP3 formats are permitted.

SECTION 01 14 00 Page 6

1.7 DELAYS

Contractor operations are subject to reasonable delays, suspensions, and restrictions because of emergencies, alerts, drills, equipment movements, and other such activities. Contractor must expect 8 hours per month due to these delays. Incorporate anticipated delay into Construction Schedule.

1.8 SEARCHES AND INSPECTIONS

Persons entering onto Government Property are, as a condition of access, subject to searches of all vehicles and personal belongings. This includes briefcases, handbags, tool chests, boxes, sealed packages, and personal articles. Random Administrative Vehicle Inspections are conducted by Security Police each day at various hours and locations on base. If selected for a vehicle inspection, be prepared to open your glove box, hood, trunk, and other personal items requested by Security.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 14 00 Page 7

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 14 00 Page 8

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600 by 1200 by 24 bit true color in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire Project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 "Liability", during the entire period of performance under this Contract. Provide other insurance coverage as required by the State of New York law.

SECTION 01 30 00 Page 1

1.6 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS

Accomplish all Contract Requirements of Section 02 82 16.00 20 ENGINEERING

CONTROL OF ASBESTOS CONTAINING MATERIALS, 02 82 13.00 10 ASBESTOS

ABATEMENT, assigned to the Private Qualified Person, Designated Competent Person, directly with a first tier Subcontractor.

1.7 SUPERVISION

1.7.1 Minimum Communication Requirements

Have at least one qualified Superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract Work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.7.2 Superintendent Qualifications

The Project Superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and Construction Drawings.

The qualification requirements for the Alternate Superintendent are the same as for the Project Superintendent. The Contracting Officer may request proof of the Superintendent's qualifications at any point in the Project if the performance of the Superintendent is in question.

For routine projects where the Superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 10 QUALITY CONTROL, the Superintendent must have qualifications in accordance with that Section.

1.7.2.1 Duties

The Project Superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the Project.

The Superintendent is required to attend meetings, partnering meetings, and quality control meetings. The Superintendent or qualified alternative must be on-site at all times during the performance of this Contract until the work is completed and accepted.

1.7.3 Project Manager

Assign a Project Manager with the responsibility for the overall management of the Project. The Contracting Officer may request proof of the Project Manager's qualifications at any point in the Project if the performance of the Project Manager is in question.

1.7.3.1 Project Manager Qualifications

The Project Manager must have a minimum 10 years experience as a Project Manager or Superintendent on projects of similar size and complexity.

SECTION 01 30 00 Page 2

1.7.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the Contract and for failure to manage the Project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.8 PRECONSTRUCTION MEETING/CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, Shop Drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major Subcontractors who will engage in the work must also attend.

1.9 WAIVER FOR WORKER'S COMPENSATION

In addition to "FAR 52.228-4, Workers' Compensation and War Hazard Insurance Overseas," the Secretary of Labor has granted a waiver. The waiver does not apply to employees who are hired in the United States, or who are residents, or citizens of the United States.

1.10 PARTNERING

To most effectively accomplish this Contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.10.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the Project Team, including Contractor personnel and Government personnel.

The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the PWD FEAD/ROICC Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the

SECTION 01 30 00 Page 3 frequency of the follow-on sessions, at no more than 3 to six month intervals.

1.11 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after Contract Award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this Contract including, but not limited to Contract Documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 30 00 Page 4

SECTION 01 31 23.13 20

ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

The Contractor shall utilize the Government's choice of electronic construction management system for the transfer, sharing, and management of all electronic technical submittals and documents. The web-based system will be the primary means of trasnferring technical documents between the Contractor and the Government.

Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where electronic construction management system is unavailable, non-functional, or specifically requested in addition to electronic submission.

1.2 USER PRIVILEGES

The Contractor will be provided access to the selected electronic construction management system. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contractor's Personnel; G

1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY

1.4.1 General

The electronic construction management system is cloud-based and only requires internet access. The Contractor will be provided with user credentials and access to required modules within the system. Provide and maintain computer hardware and software throughout the duration of the contract for all Contractor-designated users.

1.4.2 Contractor Personnel List

Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic design, technical submittals and documents and will require access to the electronic construction management system. Project personnel roles to be filled in the electronic construction management system include the Contractor's

SECTION 01 31 23.13 20 Page 1

Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:

First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)

1.5 ELECTRONIC CONSTRUCTION MANAGEMENT SYSTEM UTILIZATION

Establish, maintain, and update data and documentation in the electronic construction management system throughout the duration of the contract.

Personally Identifiable Information (PII) transmittal is not permitted in the electronic construction management system.

1.5.1 Information Security Classification/Identification

Table 1 - Project Documentation Types

SUBJECT/NAME ELECTRONI C CONSTRUCTI ON MANAGEMENT SYSTEM

APPLICATION

As-Built Drawings Submittals and Transmittals

Building Information Modeling (BIM) Submittals and Transmittals

Construction Permits Submittals and Transmittals

Construction Schedules (Activities and Milestones)

Submittals, Transmittals and Scheduling App

SECTION 01 31 23.13 20 Page 2

SUBJECT/NAME ELECTRONI C CONSTRUCTI ON MANAGEMENT SYSTEM

APPLICATION

Construction Schedules (Cost-Loaded) Submittals, Transmittals and Scheduling App

Construction Schedules (3-Week Lookahead) Scheduling App

DD 1354 Transfer of Real Property Submittals and Transmittals

Daily Production Reports Daily Report

Daily Quality Control (QC) Reports Daily Report

Designs and Specifications Submittals and Transmittals

Environmental Notice of Violation (NOV), Corrective Action Plan

Submittals and Transmittals

Environmental Protection Plan (EPP) Submittals and Transmittals

Invoice (Supporting Documentation) Submittals and Transmittals

Jobsite Documentation, Bulletin Board, Labor Laws, SDS

Submittals and Transmittals

SECTION 01 31 23.13 20 Page 3

SUBJECT/NAME ELECTRONI C CONSTRUCTI ON MANAGEMENT SYSTEM

APPLICATION

Meeting Minutes Meeting Minutes

Modification Documents Document Management

Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet

Submittals and Transmittals

Photographs Submittals and Transmittals

QCM Initial Phase Checklists Checklists (Site Management)

QCM Preparatory Phase Checklists Checklists (Site Management)

Quality Control Plans Submittals and Transmittals

QC Certifications Submittals and Transmittals

QC Punch List Punch Lists (Testing Logs)

Red-Zone Checklist Checklists (Site Management)

Rework Items List Punch Lists (Testing Logs)

Request for Information (RFI) Post-Award RFIs

Safety Plan Daily Report

Safety - Activity Hazard Analyses (AHA) Daily Report

SECTION 01 31 23.13 20 Page 4

SUBJECT/NAME ELECTRONI C CONSTRUCTI ON MANAGEMENT SYSTEM

APPLICATION

Safety - Mishap Reports Daily Report

SCIF/SAPF Accreditation Support Documents Submittals and Transmittals

Shop Drawings Submittals and Transmittals

Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)

Submittals and Transmittals

Submittals and Submittal Log Submittals and Transmittals

Testing Plans, Logs, and Reports Submittals and Transmittals

Training/Reference Materials Submittals and Transmittals

Training Records (Personnel) Submittals and Transmittals

Utility Outage/Tie-In Request/Approval Submittals and Transmittals

Warranties/BOD Letter Submittals and Transmittals

Quality Assurance Reports Checklists (Government initiated)

Non-Compliance Notices Non-Compliance Notices (Government initiated)

SECTION 01 31 23.13 20 Page 5

SUBJECT/NAME ELECTRONI C CONSTRUCTI ON MANAGEMENT SYSTEM

APPLICATION

Other Government- prepared documents GOV ONLY

All Othere Documents electronic construction management system

1.6 QUALITY ASSURANCE

Requested Government response dates on Transmittals and Submittals must be in accordance with the terms and conditions of the Contract. Requesting response dates earlier than the required review and response time, without concurrence by the Government COR, may be cause for rejection.

Incomplete submittals will be rejected without further review and must be resubmitted. Required Government response dates for resubmittals must reflect the date of resubmittal, not the original submittal date.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 31 23.13 20 Page 6

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this Project with scheduling software that meets the requirements of this Specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

SECTION 01 32 01.00 10 Page 1

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this Specification.

2.1.1 Government Default Software

The Government intends to use Microsoft Project.

2.1.2 Contractor Software

Scheduling software used by the Contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Microsoft Project

If Microsoft Project is selected for use, provide the "MPP" export file in a version of Microsoft Project importable by the Government system.

2.1.2.2 Other Than Project

If the Contractor chooses software other than Microsoft Project, that is compliant with this Specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at Project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 "Schedule For Construction Contracts". Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire Project is required. The scheduling of construction design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development.

Subcontractors and suppliers Designers, Subcontractors and suppliers working on the Project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a Project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining Contract Earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a Contract CLIN must equal the value of the CLIN.

SECTION 01 32 01.00 10 Page 2

3.2.1 Activity Cost Loading

Activity…

This is the start of the file's text. The full file is on GovTribe.