- Renovation of Automated Fuels Service Station
- Solicitation number
- W50S8D21B0001
- Issued by
-
Department of the Army National Guard
About this file
This document contains responses to questions regarding a federal contract opportunity to renovate an automated fuels service station for the Department of the Army National Guard. The contractor will be responsible for removing existing underground storage tanks and installing new aboveground storage tanks, including furnishing site plans and closure reports. Additional requirements include replacing bollards surrounding the new tanks, extending compressed air lines, and relocating the existing fuel management system controls. While the contractor must provide design plans and a quality control plan, the government will separately contract for installation of a new tank monitoring system and fuel management system integration.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Is the Contractor to include the costs associated with end‐point sampling, soil analytical reporting and tank closure reports to the NYSDEC as part of the tank removal process?
Yes
2. Drawing P‐4 recently provided appears to detail a 1’‐6” thick concrete bottom slab with #4 rebar @12” o.c.e.w. Please confirm that this detail was provided as a response to RFI #3, question #7 regarding removal of an existing concrete bottom slab beneath the existing UST’s and that this slab must be removed after the tanks are removed as part of this Contract
3. With regard to the steel pipe bollards that surround the proposed AST’s;
How many steel pipe bollards is the Contractor responsible to include? 6’ OC as necessary, contractor to include in design What diameter & length are the pipe bollards? Please see detail Is there a detail for the concrete bollard foundations below grade? Please see detail Is the Contractor responsible to paint the pipe bollards? yes
4. The Scope of Work appears to describe extending the existing air compressor lines to the location of the new AST’s. Please advise;
At what location is the contractor responsible to tie the new compressed air piping in to the existing? Please see the attached plan showing the utility lines servicing the existing station What type piping is the contractor to use for the compressed air piping? Existing utilizes 3/4” branch supply galvanized
5. Please confirm that the contractor is responsible to furnish, install, program & commission a new Veeder Root tank gauging & leak detection system inclusive of all necessary probes, sensors, high level alarms, etc
No. Only replace current RONAN automatic tank gauging with 2 each, one‐inch conduit with pull strings, prepped and capped to building 208. A separate DLA Contractor will be handling the rest to furnish and install the Veeder‐Root Tank monitoring system.
6. It was discussed at the pre‐bid meeting that the contractor is responsible to provide a complete set of construction drawings and specifications detailing to proposed scope of work. Please confirm that this is the responsibility of the contractor
It is the responsibility of the contractor to provide design
7. The Contract documents appear to specify that the contractor is responsible to provide a Quality Control Plan. Is the contractor also responsible to provide site specific safety and / or spill containment plans?
8. Is the existing fuel‐master fuel management system to be relocated by the contractor or is the contractor to furnish and install a new system?
The current system is to be relocated, but the contractor will only need to reroute communication lines and electric lines and mount the fuelmaster pedestal head between the two newly installed tanks and dispensers. A separate FuelMaster Contractor will be handling the rest to make it sync to the tanks.