This document contains a request for information regarding a federal contract opportunity to renovate an automated fuels service station for the Department of the Army National Guard. The request for information includes questions about extending the bid period by 12 weeks, providing tank measurements and specifications from the supplier, responsibilities for offloading and installing fuel tanks and a canopy, and specifications for the fuel management and VeederRoot tank monitoring systems. Contractor will replace the existing automatic tank gauging system with new conduit and caps in preparation for a separate contractor to furnish and install the VeederRoot Tank monitoring system.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please consider the following additional RFIs regarding your proposed project:
1) Can you consider extending the bid another 1‐2 weeks?
Extended per contracting
2) Can we have all the tank measurements from your supplier?
Please see attached tank specs
3) Will you need us (the Contractor) to off‐load the tanks?
Yes
4) How are you approaching the canopy and associated footings? The PWS mentions that the canopy cannot be approved without the tanks first being installed. If that means the canopy submittal and subsequent orders cannot be approved until the tanks are installed, this has a significant impact on overall schedule, and it also impacts the installation and size of the concrete tank mat.
The PWS has been revised to state “canopy cannot be installed without the tanks first being installed”.
5) Please provide the spec for the fuel management system.
Specifications attached (FM‐010_FMU_Installation_Manual(052413).pdf)
6) Please provide the spec for the Veeder‐Root tank monitoring system.
Contractor to replace current RONAN automatic tank gauging with 2 each, one‐inch conduit with pull strings, prepped and capped to building 208. A separate DLA Contractor will be handling the rest to furnish and install the Veeder‐Root Tank monitoring system.
7) Who will furnish and install the Veeder‐Root tank monitoring system?
Please refer to response #6 above