This is a Technical Exhibit (TE 0009) detailing Levels of Service requirements for a Base Operations Support Services contract at Fort Hamilton, NY. The document outlines 20 performance requirements with their associated performance standards, acceptable quality levels (AQL), methods of surveillance, and incentives.

The exhibit specifies key service requirements including: program management with 24/7 point of contact availability, quality control plan maintenance, employee conduct standards, facility maintenance standards, waste management with a 10% deviation allowance, grounds maintenance requirements, snow/ice removal services for primary and secondary pavements, preventive maintenance execution for facilities and utilities, and pest management services for both indoor and outdoor areas. Most requirements have either a 5% or 10% deviation allowance from performance standards, with surveillance conducted through random sampling and customer complaints validated by the COR/ACOR. Non-conforming services generally result in non-conformance reports, potential negative CPARS ratings, and requirements to re-perform services at no additional cost to the government.

View the file

Other files

File Type Posted
Attachment 0075 - CBA October 1 2023 - September 30 2026.pdf PDF
SCA_WD_New York_2015-4187_Rev._No._29_Rev._Date_07.22.2024.txt TXT text file
25-R-5001 - Industry Questions List w. Answers (Final).xlsx XLSX spreadsheet
Attachment 0003 - Price Matrix (Rev. 2)(d. 12.18.2024).xlsx XLSX spreadsheet
Tech Exhibit 0806 Secretary of the Interior Standards for the Treatment of Historic Places.pdf PDF
25-R-5001 - GFP List (d 12.09.2024).xlsx XLSX spreadsheet
25-R-5001 - BASOPS CDRLs A001_A057.pdf PDF
25-R-5001 - Solicitation Amendment 0006.pdf PDF
25R5001 - Attachment 0073 - Personnel Licensing and Certs (v1).pdf PDF
DBA_WD_New York_NY20240003_Mod._No._9_Rev._Date_09.27.2024.txt TXT text file
25R5001 - Tech Exhibit 0605 GSA VEHICLES Updated (v.2).pdf PDF
25R5001 - Tech Exhibit 0803 Special Services and Events.docx DOCX document
25-R-5001 - Site Visit Attendees List.docx DOCX document
25R5001 - Tech Exhibit 0419 Elevators_dumbwaiters_wheelchair lifts.docx DOCX document
25R5001 - Tech Exhibit 0004 Integrated Cultural Resources Management Plan.pdf PDF
25R5001 - Tech Exhibit 0204 Tree and Shrub Locations.pdf PDF
25-R-5001 - Solicitation Amendment 0005.pdf PDF
25-R-5001 - Solicitation Amendment 0004.pdf PDF
25-R-5001 - Solicitation Amendment 0003.pdf PDF
25-R-5001 - Solicitation Amendment 0002.pdf PDF
25-R-5001 - Solicitation Amendment 0001.pdf PDF
25R5001 - Tech Exhibit 0605 GSA VEHICLES.pdf PDF
25R5001 - Tech Exhibit 0008 Personnel Licensing and Certs.docx DOCX document
25R5001 - Tech Exhibit 0410 Gas and Oil fired boilers.docx DOCX document
25R5001 - Annex F - Grounds Maintenance PWS.pdf PDF
25R5001 - Tech Exhibit 0420 Swimming and wading pools.docx DOCX document
25R5001 - Tech Exhibit 0804 Waste Water Management.docx DOCX document
Attachment 0003 - Price Matrix.xlsx XLSX spreadsheet
25R5001 - Tech Exhibit 0203 Parade Area Taylor Field.pdf PDF
25R5001 - Annex M - Pest Management PWS.pdf PDF
25R5001 - Tech Exhibit 0402 Eye Washes and Safety Showers.docx DOCX document
25R5001 - Tech Exhibit 0010 Priority Facilities.docx DOCX document
25R5001 - Tech Exhibit 0205 Irrigation Systems.docx DOCX document
25R5001 - Tech Exhibit 0403 Automatic Doors.docx DOCX document
25R5001 - Tech Exhibit 0415 Sprinkler Systems.docx DOCX document
25R5001 - Tech Exhibit 0601 IBE list per building GFEBS 2019_Revised.xlsx XLSX spreadsheet
25R5001 - Tech Exhibit 0407 Sump Pumps.docx DOCX document
25R5001 - Tech Exhibit 0414 Fire Alarm Systems.docx DOCX document
25R5001 - Tech Exhibit 0505 Builder.docx DOCX document
25R5001 - Tech Exhibit 0401 Publications and Forms.docx DOCX document
25R5001 - Tech Exhibit 0412 Auxiliary Generators.xlsx XLSX spreadsheet
25R5001 - Tech Exhibit 0003 RCI Housing Locations.pdf PDF
25R5001 - Tech Exhibit 0101 Estimated Container Sizes and Frequencies.docx DOCX document
25R5001 - Annex J - Facility Maintenance Horizontal PWS.pdf PDF
25R5001 - Annex B - Facilities Maintenance Instruction.pdf PDF
25R5001 - Attachment 0074 - Accounting System Checklist.pdf PDF
25R5001 - Tech Exhibit 0408 Hot Water Tanks.docx DOCX document
25R5001 - Tech Exhibit 0805 Heating and Cooling.docx DOCX document
25R5001 - Tech Exhibit 0416 Hood Systems.docx DOCX document
25R5001 - Tech Exhibit 0509 Backflow Preventers.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 92 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Exhibit 0009

Levels of Service

October 2023

# 2.

The Program Manager shall be available after normal duty hours to serve as the central point of contact for Contractor operations.

The Contractor shall provide a central point of contact IAW PWS, para.

2.1.4.1.

Zero Deviation from performance standard

100% daily and verification/confirmation by the COR/ACOR.

Non-conforming services will result in Non- Conforming Reports issued to Contractor and potential negative CPARS report.

#3.

The Contractor shall develop and maintain a Quality Control Plan approved by the KO.

The Contractor shall provide a

QCP IAW PWS,

para, 4.2.

Zero Deviation from performance standard.

Review and acceptance by the by the KO on submission of QCP and each revised QCP.

Non-conforming services will result in Non- Conforming Reports issued and a potential negative CPARS narrative.

# 4.

The Contractor shall remove, from the job site, any employee for reasons of misconduct or security.

Employee conduct complies with 41 U.S.C. 423, Procurement Integrity, IAW PWS para.

2.1.11.1.6.

Zero Deviation from performance standard.

The COR/ACOR will review 100% of Contractor reported occurrences of Contractor employee misconduct, including but not limited to violations of any provision indicated at 41 U.S.C. 423, and/or security violation to ensure the offending employee is removed from the job site.

Non-conforming services will result in Non- Conforming Reports issued to Contractor and potential equitable adjustment by the Contracting Officer.

Required Services

Performance Standard

Acceptable Quality Level

(AQL)

Method of Surveillance

Incentive (Positive and/or Negative)

# 1.

Contractor shall ensure all work accomplished meets all maintenance and repair standards listed in all applicable Federal, State, and local laws, regulations and directives to include, but not limited to applicable publications in Section 7, Related Documents.

The Contractor shall provide services IAW PWS, para. 1.2.

5% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#5.

Damages caused by Contractor employees shall be repaired at no cost to the Government.

The Contractor shall notify the COR/ACOR and return the damaged area to its previous condition AW PWS, para.

3.1.1.1.

Zero Deviation from performance standard

COR/ACOR will review 100% of damage reports.

Non-conforming services will result in Non- Conforming Reports issued and a potential negative CPARS narrative.

#6.

The Contractor will ensure that the licenses or certificates and training of Contractor personnel are kept current. Copies of these licenses or certifications will be provided to the

COR/ACOR.

The Contractor shall perform IAW PWS, para.

2.3.4.1.

Zero Deviation from performance standard (Risk assessed high risk)

100 Percent Inspection of copies of these licenses or certifications

Non-conforming services will result in Non- Conforming Reports issued and a potential negative CPARS narrative

#7.

Percentage of Non-hazardous solid waste diverted from the waste stream meets annual diversion goal of the DoD Strategic Sustainability Performance Plan 403-

AC-03-03-B

The Contractor shall perform

IAW PWS,

Annex E – 403 Solid Waste Management

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#8.

Percentage of improved grounds maintained IAW Enterprise Municipal Ground Maintenance Performance standards.

Intellicode 404-AC-01- 01-A

The Contractor shall perform

IAW PWS,

Annex F – 404 Grounds Maintenance

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall

#9 Clear snow, sleet, ice, and sand from primary roads, and sidewalks parking lots for critical building access, and ports. Intellicode 408-

AC-03-04-A

The Contractor shall perform

IAW PWS,

Annex G – 408 Pavement Clearance

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall

#10 Secondary pavements made passable within 12 hours of onset of event. Intellicode 408-

AC-06-07-D

The Contractor shall perform

IAW PWS,

Annex G – 408 Pavement Clearance

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#11 Percentage of validated emergency demand work orders completed IAW established completion times.

Intellicode 411-AC-01- 01-A

The Contractor shall perform

IAW PWS,

Annex H – 411 Facilities Maintenance Vertical

5% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#12 Percentage of validated urgent and routine demand work orders completed IAW established completion times. Intellicode 411-

AC-01-02-B

The Contractor shall perform

IAW PWS,

Annex H – 411 Facilities Maintenance Vertical

5% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#13 Preventive Maintenance executed compared to required PM. Intellicode

411-AC-02-03-C

The Contractor shall perform

IAW PWS,

Annex H – 411 Facilities Maintenance Vertical

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall

#14 Percentage of emergency DMOs completed within standard IAW established completion times. Intellicode 420-

AC-01-01-A

The Contractor shall perform

IAW PWS,

Annex J – 420 Facilities Maintenance Horizontal

5% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#15 Percentage of validated urgent and routine demand work orders completed IAW established completion times. Intellicode 420-

AC-01-02-B

The Contractor shall perform

IAW PWS,

Annex J – 420 Facilities Maintenance Horizontal

5% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#16 Percentage of preventive maintenance executed compared to requuired PM.

Intellicode 420-AC-02- 03-C

The Contractor shall perform

IAW PWS,

Annex J – 420 Facilities Maintenance Horizontal

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall

#17 Percentage of preventive maintenance executed compared to required PM.

The Contractor shall perform

IAW PWS,

Annex K – 420 Heating & Cooling Services

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#18 Percentage of preventive maintenance executed compared to required PM.

The Contractor shall perform

IAW PWS,

Annex L – 420 Wastewater Services

10% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#19 Percentage of scheduled Indoor Pest Management Services completed. Intellicode

510-AC-04-04-B

The Contractor shall perform

IAW PWS,

Annex M – 510 Pest Management Services

5% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall re-perform the service.

#20 Percentage of scheduled Outdoor Pest Management Services completed. Intellicode

510-AC-05-05-C

The Contractor shall perform

IAW PWS,

Annex M – 510 Pest Management Services

5% Deviation from performance Standard;

% calculated by dividing the number of defects by the number of observations.

Random Sampling and Customer Complaints;

Inspections and complaint validations performed by QA and the COR/ACOR.

Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System;

Contractor shall