This is a vessel information form template from the Massachusetts Bay Transportation Authority (MBTA) for the Hingham Ferry Route F1 service. The Excel spreadsheet contains multiple worksheets designed to capture detailed information about vessels proposed for the ferry service, including a Vessel Summary sheet, Vessel List, Fuel Consumption data, and individual Vessel Information sheets. The form requires bidders to provide specific details for up to six vessels including vessel names, U.S. Coast Guard Registration Numbers, ownership status, make, model, year built, passenger capacity, seating information, and fuel consumption data.

The form focuses on technical specifications and operational data, particularly fuel consumption metrics, requiring details on average fuel use per hour (both idling and operating), one-way trip times between Hingham and Rowes Wharf, and one-way fuel usage. The document emphasizes the importance of accuracy in data entry, with auto-filling features between sheets and requirements for certification signatures for each vessel proposed. The form is part of RFP 225-24 for Ferry Service in Massachusetts.

View the file

Other files

File Type Posted
RFP 225-24 Commuter Ferry Service~1.docx DOCX document
Appendix 2-Route F2H - updated.docx DOCX document
Vessel Forms_F3_rev. 3.xlsx XLSX spreadsheet
Appendix 0 General Technical Specification~1.docx DOCX document
Form D - Price Proposal Forms updated 2024-12-09.xlsx XLSX spreadsheet
Attachment - Dock Agreement-LWC-LWN-CTown.pdf PDF
Attachment - Dock Agreement - Charlestown Marina.pdf PDF
Attachment - Dock Agreement-Lewis Wharf.pdf PDF
Attachment - Dock Agreement-Rowes Wharf w Amendment.pdf PDF
Safety Changes.docx DOCX document
Appendix 6-Route F6~1.docx DOCX document
Exhibit A - MBTA Minimum Insurance Requirements.docx DOCX document
Appendix 1-Route F1~1.docx DOCX document
RFP 225-24 Commuter Ferry Service - updated 2.docx DOCX document
Intermodal Center visit.docx DOCX document
Appendix 3-Route F3 - updated.docx DOCX document
Appendix 0 - Attachment H - Witness Statement Form.docx DOCX document
Appendix 0 General Technical Specification -updated.docx DOCX document
Attachment - Dock Agreement-Lynn.pdf PDF
Pre-Bid Conference1~3.pptx PPTX presentation
Attachment - Vessel and Dock Agreement-Valkyrie and Lewis Wharf.pdf PDF
Appendix 2-Route F2H~1.docx DOCX document
Appendix 0 - Attachment G - FTA Safety and Security Form.pdf PDF
Appendix 5-Route F5~1.docx DOCX document
Appendix 1-Route F1 - updated~1.docx DOCX document
Attachment - Vessel Agreement-Ava Pearl.pdf PDF
Appendix 3-Route F3~1.docx DOCX document
Appendix 4-Route F4~1.docx DOCX document
Appendix 5-Route F5 - updated.docx DOCX document
Ferry engine data rev 1.xlsx XLSX spreadsheet
Vessel Forms_F4_rev. 3.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Vessel Summary 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Instructions:
1. Complete the information below in the yellow spaces for each vessel that will be supplied for this route, all other rows can be left blank.
The information in this sheet will be auto-filled into the remaining documents where applicable.
2. Verify the accuracy of the auto-filled data in the Vessel List and the Fuel Consumption Form.
3. For each vessel being proposed, complete the information in the vessel's tab in yellow.
4. Print all completed sheets to PDF. (This Vessel Summary sheet does not need to be printed or submitted to the MBTA)
5. Sign the certification for each vessel.
6. Submit with proposal as required.
Route F1: Hingham FerryAverage Fuel Use
(gallons per hour)One-Way

Trip Time (minutes)* One-Way Fuel Usage (gallons)**

Vessel NumberVessel NameU.S. Coast Guard Registration NumberDoes Offeror Own, Lease, or Charter this Vessel?OwnerMakeModelYear BuiltPassenger CapacityQty of Fixed Passenger SeatsAre Passenger Seats Upholstered?Qty of Passenger Seats At TablesTop Speed
(knots)Fuel TypeIdlingOperatingHingham

Rowes Wharf Hingham Rowes Wharf

1
2
3
4
5
6

&A

Vessel List

VESSEL LIST
Route F1: Hingham Ferry
Provide the name and U.S. Coast Guard Registration Number for each vessel proposed for this contract.
Vessel NumberVessel NameU.S. Coast Guard Registration NumberDoes Offeror Own, Lease, or Charter this Vessel?Owner
1----
2----
3----
4----
5----
6----
This sheet should auto-fill from the information provided in the Vessel Summary tab. Offeror should review and confirm the accuracy of this information.

Fuel Consumption

VESSEL FUEL CONSUMPTION
Route F1: Hingham Ferry
Vessel Number
(per Vessel Information Sheet)Vessel NameTop Speed
(knots)Fuel TypeAverage Fuel Use
(gallons per hour)One-Way

Trip Time (minutes) One-Way Fuel Usage (gallons) Idling Operating Hingham Rowes Wharf Hingham Rowes Wharf

1-------
2-------
3-------
4-------
5-------
6-------
This sheet auto-fills from the information provided in the Vessel Summary tab.
Offeror should review and confirm the accuracy of this information.

Vessel 1

VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)1Vessel Name:0
USCG Registration Number:0Current Owner:0
Make:0Passenger Capacity:0
Model:0Year Vessel Built:0
Fuel Type:0
Vessel Usage
Will this vessel be dedicated to this service?<-- Select Yes or No
If it will be used for other purposes please briefly describe:
<-- Enter N/A or description
Vessel Measurements
Length Overall (ft.):Draft (ft):<-- Enter dimensions
Beam (ft.):Gross Tonnage (GT):<-- Enter dimension/tonnage
Vessel Measurements - Passenger Loading Areas
Distance from bow to forwardmost passenger loading gate (ft):<-- Enter dimension, or N/A
Distance from forwardmost passenger loading gate to aft gate (ft.):<-- Enter dimension, or N/A
Freeboard at bow loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at forward loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at aft loading gate, if present (ft-in):<-- Enter dimension, or N/A
Description of Features
Description of hydraulic, sewage, sanitary, electrical, firefighting, and safety features aboard vessel:
<-- Enter description of this equipment and features
Other special features:
<-- Enter description of any other notable features
VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)1Vessel Name:0
USCG Registration Number:0Current Owner:0
Description of Accessibility Features
Bridgeplate:<-- Describe accessible features
Bathrooms:<-- Describe accessible features
Telephones:<-- Describe accessible features
Wheelchair Tie-Down Equipment:
Type of Securement:
(i.e. belts, clamps, etc.)<-- Describe type(s) of wheelchair tie down equipment
Manufacturer:No. of wheelchair positions:<-- Enter Manufacturer of wheelchair tie-down equipment and enter the number of wheelchair positions
Model:Date Installed:<--Enter model of wheelchair tie-down equipment and the date it was installed.
List other features which make vessel accessible to persons with disabilities:
<-- Describe accessible features
PROPOSED VESSEL UTILIZATION SHEETMake font BOLD for the trips that would be operated by this vessel:<--- follow these directions
Route F1: Hingham Ferry
Complete one sheet for each vesselHinghamLong WharfLong WharfHingham
The purpose of this sheet is to identify which of the proposed vessels will be used for each trip, in the full service schedule. Which vessels are designated for each trip will be a factor in determining whether the proposed vessels will meet the required passenger capacities in the evaluation of each proposal. The successful operator will be expected to operate service in accordance with this vessel listing.(depart)(arrive)(depart)(arrive)
6:00 AM6:30 AM6:50 AM7:20 AM
6:30 AM7:10 AM7:15 AM7:55 AM
6:50 AM7:30 AM7:35 AM8:15 AM
7:15 AM7:45 AM8:00 AM8:30 AM
7:45 AM8:15 AM8:30 AM9:00 AM
8:00 AM8:40 AM--
8:20 AM9:00 AM--
8:45 AM9:15 AM--
9:15 AM9:45 AM10:00 AM10:40 AM
Vessel Identification11:00 AM11:40 AM--
Vessel List Number:1--1:30 PM2:10 PM
Vessel Name:02:30 PM3:10 PM3:25 PM4:05 PM
Max. Vessel Speed:0 knots--4:00 PM4:40 PM
--4:30 PM5:00 PM
Passenger Capacity4:10 PM4:50 PM5:00 PM5:40 PM
Passenger Capacity:0--5:20 PM5:50 PM
Fixed Passenger Seats (Qty):04:45 PM5:25 PM5:40 PM6:20 PM
Upholstered Seats (Yes or No):05:15 PM5:45 PM6:00 PM6:30 PM
Passenger Seats At Tables (Qty):05:45 PM6:25 PM6:30 PM7:10 PM
6:10 PM6:40 PM7:00 PM7:30 PM
Average Vessel Fuel Use: (Gallons Per Hour)6:40 PM7:10 PM7:30 PM8:00 PM
Idling:07:40 PM8:10 PM8:30 PM9:00 PM
Operating:0
Vessel Trip Time
Hingham - Rowes Wharf:0 minutes
Fuel Consumption per Trip
Hingham - Rowes Wharf:0 gallons
Fuel Type:
0
The above listed vessel is able to operate the specified ferry service with no modifications to the schedule listed in the RFP: (select Yes or No)<-- Select Yes or No from the dropdown menu
If NO, list all modifications that would be required to the schedule of operated with this vessel:
<-- If applicable, enter any necessary schedule modifications -->
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)1Vessel Name:0
Is this vessel already constructed and ready for service (yes or no):<-- Select Yes or No
For: Existing Vessels<-- Complete this section unless you are proposing to use vessels that are currently under construction.
Vessel History(For vessels under construction, complete the "Vessels to be Constructed" section below)
Year Vessel Built:0
Vessel Age (years):2024 years
Estimated remaining vessel service life (years):<-- Enter estimate years
Type and quantity of power plant:<-- Enter type and quantity
Number of hours logged on each engine to date:<-- Enter hours on each engine
Date and nature of most recent routine maintenance or repair:
<-- Enter description
Date and nature of most recent major vessel maintenance or repair:
<-- Enter description
Date and nature of most recent external hull maintenance above the water line:
<-- Enter description
Date and nature of most recent internal or external hull maintenance below the waterline:
<-- Enter description
Date of most recent marine survey of this vessel:<-- Enter date
USCG Inspections
Offerer must attach the most recent Coast Guard Inspection, deficiencies found and date of repairs.<-- Attach USCG inspection documentation with proposal
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)1Vessel Name:0
For: Vessels To Be Constructed<-- Complete this section only if you are proposing to use vessels that are currently under construction.
Vessel Identification
Make:0Passenger Capacity:0
Model:0Power Plant
Type and Qty:<--Enter type and quantity of power plant
Vessel Construction
Vessel construction schedule including confirmation of proposed delivery date by shipbuilder:
(Offeror must include attachments verifying this information)
<--indicate the construction and delivery schedule, AND attach documentation.
PROPOSED VESSEL CERTIFICATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel List Number:1Vessel Top Speed:0 knots
Vessel Name:0
Name of Firm:<-- Enter the Offeror's Corporate Name

I, , hereby certify that: <-- Enter the Signer's Name

1. The dimensions and maneuvering capabilities of the above listed vessel will allow for safe and efficient docking at the designated terminal and intermediate stop locations for the designated route at all tide conditions.

2. I am familiar with the physical conditions and navigational constraints at the existing docking facilities for the above listed route.

3. The above listed vessel can operate safely and efficiently at these berthing facilities and meet all requirements of this specification for the above listed route.

4.The draft of the above listed vessel, when fully loaded, shall be shallow enough to operate where required to operate their assigned ferry services during all tide conditions.
Signature:<-- Sign this form

Name: <-- Enter the Signer's Name

Name of Firm: <-- Enter the Offeror's Corporate Name

NOTE: THIS INFORMATION TO BE INCLUDED IN THE CONTRACT

Vessel 2

VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)2Vessel Name:0
USCG Registration Number:0Current Owner:0
Make:0Passenger Capacity:0
Model:0Year Vessel Built:0
Fuel Type:0
Vessel Usage
Will this vessel be dedicated to this service?<-- Select Yes or No
If it will be used for other purposes please briefly describe:
<-- Enter N/A or description
Vessel Measurements
Length Overall (ft.):Draft (ft):<-- Enter dimensions
Beam (ft.):Gross Tonnage (GT):<-- Enter dimension/tonnage
Vessel Measurements - Passenger Loading Areas
Distance from bow to forwardmost passenger loading gate (ft):<-- Enter dimension, or N/A
Distance from forwardmost passenger loading gate to aft gate (ft.):<-- Enter dimension, or N/A
Freeboard at bow loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at forward loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at aft loading gate, if present (ft-in):<-- Enter dimension, or N/A
Description of Features
Description of hydraulic, sewage, sanitary, electrical, firefighting, and safety features aboard vessel:
<-- Enter description of this equipment and features
Other special features:
<-- Enter description of any other notable features
VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)2Vessel Name:0
USCG Registration Number:0Current Owner:0
Description of Accessibility Features
Bridgeplate:<-- Describe accessible features
Bathrooms:<-- Describe accessible features
Telephones:<-- Describe accessible features
Wheelchair Tie-Down Equipment:
Type of Securement:
(i.e. belts, clamps, etc.)<-- Describe type(s) of wheelchair tie down equipment
Manufacturer:No. of wheelchair positions:<-- Enter Manufacturer of wheelchair tie-down equipment and enter the number of wheelchair positions
Model:Date Installed:<--Enter model of wheelchair tie-down equipment and the date it was installed.
List other features which make vessel accessible to persons with disabilities:
<-- Describe accessible features
PROPOSED VESSEL UTILIZATION SHEETMake font BOLD for the trips that would be operated by this vessel:<--- follow these directions
Route F1: Hingham Ferry
Complete one sheet for each vesselHinghamLong WharfLong WharfHingham
The purpose of this sheet is to identify which of the proposed vessels will be used for each trip, in the full service schedule. Which vessels are designated for each trip will be a factor in determining whether the proposed vessels will meet the required passenger capacities in the evaluation of each proposal. The successful operator will be expected to operate service in accordance with this vessel listing.(depart)(arrive)(depart)(arrive)
6:00 AM6:30 AM6:50 AM7:20 AM
6:30 AM7:10 AM7:15 AM7:55 AM
6:50 AM7:30 AM7:35 AM8:15 AM
7:15 AM7:45 AM8:00 AM8:30 AM
7:45 AM8:15 AM8:30 AM9:00 AM
8:00 AM8:40 AM--
8:20 AM9:00 AM--
8:45 AM9:15 AM--
9:15 AM9:45 AM10:00 AM10:40 AM
Vessel Identification11:00 AM11:40 AM--
Vessel List Number:2--1:30 PM2:10 PM
Vessel Name:02:30 PM3:10 PM3:25 PM4:05 PM
Max. Vessel Speed:0 knots--4:00 PM4:40 PM
--4:30 PM5:00 PM
Passenger Capacity4:10 PM4:50 PM5:00 PM5:40 PM
Passenger Capacity:0--5:20 PM5:50 PM
Fixed Passenger Seats (Qty):04:45 PM5:25 PM5:40 PM6:20 PM
Upholstered Seats (Yes or No):05:15 PM5:45 PM6:00 PM6:30 PM
Passenger Seats At Tables (Qty):05:45 PM6:25 PM6:30 PM7:10 PM
6:10 PM6:40 PM7:00 PM7:30 PM
Average Vessel Fuel Use: (Gallons Per Hour)6:40 PM7:10 PM7:30 PM8:00 PM
Idling:07:40 PM8:10 PM8:30 PM9:00 PM
Operating:0
Vessel Trip Time
Hingham - Rowes Wharf:0 minutes
Fuel Consumption per Trip
Hingham - Rowes Wharf:0 gallons
Fuel Type:
0
The above listed vessel is able to operate the specified ferry service with no modifications to the schedule listed in the RFP: (select Yes or No)<-- Select Yes or No from the dropdown menu
If NO, list all modifications that would be required to the schedule of operated with this vessel:
<-- If applicable, enter any necessary schedule modifications -->
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)2Vessel Name:0
Is this vessel already constructed and ready for service (yes or no):<-- Select Yes or No
For: Existing Vessels<-- Complete this section unless you are proposing to use vessels that are currently under construction.
Vessel History(For vessels under construction, complete the "Vessels to be Constructed" section below)
Year Vessel Built:0
Vessel Age (years):2024 years
Estimated remaining vessel service life (years):<-- Enter estimate years
Type and quantity of power plant:<-- Enter type and quantity
Number of hours logged on each engine to date:<-- Enter hours on each engine
Date and nature of most recent routine maintenance or repair:
<-- Enter description
Date and nature of most recent major vessel maintenance or repair:
<-- Enter description
Date and nature of most recent external hull maintenance above the water line:
<-- Enter description
Date and nature of most recent internal or external hull maintenance below the waterline:
<-- Enter description
Date of most recent marine survey of this vessel:<-- Enter date
USCG Inspections
Offerer must attach the most recent Coast Guard Inspection, deficiencies found and date of repairs.<-- Attach USCG inspection documentation with proposal
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)2Vessel Name:0
For: Vessels To Be Constructed<-- Complete this section only if you are proposing to use vessels that are currently under construction.
Vessel Identification
Make:0Passenger Capacity:0
Model:0Power Plant
Type and Qty:<--Enter type and quantity of power plant
Vessel Construction
Vessel construction schedule including confirmation of proposed delivery date by shipbuilder:
(Offeror must include attachments verifying this information)
<--indicate the construction and delivery schedule, AND attach documentation.
PROPOSED VESSEL CERTIFICATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel List Number:2Vessel Top Speed:0 knots
Vessel Name:0
Name of Firm:<-- Enter the Offeror's Corporate Name

I, , hereby certify that: <-- Enter the Signer's Name

1. The dimensions and maneuvering capabilities of the above listed vessel will allow for safe and efficient docking at the designated terminal and intermediate stop locations for the designated route at all tide conditions.

2. I am familiar with the physical conditions and navigational constraints at the existing docking facilities for the above listed route.

3. The above listed vessel can operate safely and efficiently at these berthing facilities and meet all requirements of this specification for the above listed route.

4.The draft of the above listed vessel, when fully loaded, shall be shallow enough to operate where required to operate their assigned ferry services during all tide conditions.
Signature:<-- Sign this form

Name: <-- Enter the Signer's Name

Name of Firm: <-- Enter the Offeror's Corporate Name

NOTE: THIS INFORMATION TO BE INCLUDED IN THE CONTRACT

Vessel 3

VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)3Vessel Name:0
USCG Registration Number:0Current Owner:0
Make:0Passenger Capacity:0
Model:0Year Vessel Built:0
Fuel Type:0
Vessel Usage
Will this vessel be dedicated to this service?<-- Select Yes or No
If it will be used for other purposes please briefly describe:
<-- Enter N/A or description
Vessel Measurements
Length Overall (ft.):Draft (ft):<-- Enter dimensions
Beam (ft.):Gross Tonnage (GT):<-- Enter dimension/tonnage
Vessel Measurements - Passenger Loading Areas
Distance from bow to forwardmost passenger loading gate (ft):<-- Enter dimension, or N/A
Distance from forwardmost passenger loading gate to aft gate (ft.):<-- Enter dimension, or N/A
Freeboard at bow loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at forward loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at aft loading gate, if present (ft-in):<-- Enter dimension, or N/A
Description of Features
Description of hydraulic, sewage, sanitary, electrical, firefighting, and safety features aboard vessel:
<-- Enter description of this equipment and features
Other special features:
<-- Enter description of any other notable features
VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)3Vessel Name:0
USCG Registration Number:0Current Owner:0
Description of Accessibility Features
Bridgeplate:<-- Describe accessible features
Bathrooms:<-- Describe accessible features
Telephones:<-- Describe accessible features
Wheelchair Tie-Down Equipment:
Type of Securement:
(i.e. belts, clamps, etc.)<-- Describe type(s) of wheelchair tie down equipment
Manufacturer:No. of wheelchair positions:<-- Enter Manufacturer of wheelchair tie-down equipment and enter the number of wheelchair positions
Model:Date Installed:<--Enter model of wheelchair tie-down equipment and the date it was installed.
List other features which make vessel accessible to persons with disabilities:
<-- Describe accessible features
PROPOSED VESSEL UTILIZATION SHEETMake font BOLD for the trips that would be operated by this vessel:<--- follow these directions
Route F1: Hingham Ferry
Complete one sheet for each vesselHinghamLong WharfLong WharfHingham
The purpose of this sheet is to identify which of the proposed vessels will be used for each trip, in the full service schedule. Which vessels are designated for each trip will be a factor in determining whether the proposed vessels will meet the required passenger capacities in the evaluation of each proposal. The successful operator will be expected to operate service in accordance with this vessel listing.(depart)(arrive)(depart)(arrive)
6:00 AM6:30 AM6:50 AM7:20 AM
6:30 AM7:10 AM7:15 AM7:55 AM
6:50 AM7:30 AM7:35 AM8:15 AM
7:15 AM7:45 AM8:00 AM8:30 AM
7:45 AM8:15 AM8:30 AM9:00 AM
8:00 AM8:40 AM--
8:20 AM9:00 AM--
8:45 AM9:15 AM--
9:15 AM9:45 AM10:00 AM10:40 AM
Vessel Identification11:00 AM11:40 AM--
Vessel List Number:3--1:30 PM2:10 PM
Vessel Name:02:30 PM3:10 PM3:25 PM4:05 PM
Max. Vessel Speed:0 knots--4:00 PM4:40 PM
--4:30 PM5:00 PM
Passenger Capacity4:10 PM4:50 PM5:00 PM5:40 PM
Passenger Capacity:0--5:20 PM5:50 PM
Fixed Passenger Seats (Qty):04:45 PM5:25 PM5:40 PM6:20 PM
Upholstered Seats (Yes or No):05:15 PM5:45 PM6:00 PM6:30 PM
Passenger Seats At Tables (Qty):05:45 PM6:25 PM6:30 PM7:10 PM
6:10 PM6:40 PM7:00 PM7:30 PM
Average Vessel Fuel Use: (Gallons Per Hour)6:40 PM7:10 PM7:30 PM8:00 PM
Idling:07:40 PM8:10 PM8:30 PM9:00 PM
Operating:0
Vessel Trip Time
Hingham - Rowes Wharf:0 minutes
Fuel Consumption per Trip
Hingham - Rowes Wharf:0 gallons
Fuel Type:
0
The above listed vessel is able to operate the specified ferry service with no modifications to the schedule listed in the RFP: (select Yes or No)<-- Select Yes or No from the dropdown menu
If NO, list all modifications that would be required to the schedule of operated with this vessel:
<-- If applicable, enter any necessary schedule modifications -->
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)3Vessel Name:0
Is this vessel already constructed and ready for service (yes or no):<-- Select Yes or No
For: Existing Vessels<-- Complete this section unless you are proposing to use vessels that are currently under construction.
Vessel History(For vessels under construction, complete the "Vessels to be Constructed" section below)
Year Vessel Built:0
Vessel Age (years):2024 years
Estimated remaining vessel service life (years):<-- Enter estimate years
Type and quantity of power plant:<-- Enter type and quantity
Number of hours logged on each engine to date:<-- Enter hours on each engine
Date and nature of most recent routine maintenance or repair:
<-- Enter description
Date and nature of most recent major vessel maintenance or repair:
<-- Enter description
Date and nature of most recent external hull maintenance above the water line:
<-- Enter description
Date and nature of most recent internal or external hull maintenance below the waterline:
<-- Enter description
Date of most recent marine survey of this vessel:<-- Enter date
USCG Inspections
Offerer must attach the most recent Coast Guard Inspection, deficiencies found and date of repairs.<-- Attach USCG inspection documentation with proposal
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)3Vessel Name:0
For: Vessels To Be Constructed<-- Complete this section only if you are proposing to use vessels that are currently under construction.
Vessel Identification
Make:0Passenger Capacity:0
Model:0Power Plant
Type and Qty:<--Enter type and quantity of power plant
Vessel Construction
Vessel construction schedule including confirmation of proposed delivery date by shipbuilder:
(Offeror must include attachments verifying this information)
<--indicate the construction and delivery schedule, AND attach documentation.
PROPOSED VESSEL CERTIFICATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel List Number:3Vessel Top Speed:0 knots
Vessel Name:0
Name of Firm:<-- Enter the Offeror's Corporate Name

I, , hereby certify that: <-- Enter the Signer's Name

1. The dimensions and maneuvering capabilities of the above listed vessel will allow for safe and efficient docking at the designated terminal and intermediate stop locations for the designated route at all tide conditions.

2. I am familiar with the physical conditions and navigational constraints at the existing docking facilities for the above listed route.

3. The above listed vessel can operate safely and efficiently at these berthing facilities and meet all requirements of this specification for the above listed route.

4.The draft of the above listed vessel, when fully loaded, shall be shallow enough to operate where required to operate their assigned ferry services during all tide conditions.
Signature:<-- Sign this form

Name: <-- Enter the Signer's Name

Name of Firm: <-- Enter the Offeror's Corporate Name

NOTE: THIS INFORMATION TO BE INCLUDED IN THE CONTRACT

Vessel 4

VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)4Vessel Name:0
USCG Registration Number:0Current Owner:0
Make:0Passenger Capacity:0
Model:0Year Vessel Built:0
Fuel Type:0
Vessel Usage
Will this vessel be dedicated to this service?<-- Select Yes or No
If it will be used for other purposes please briefly describe:
<-- Enter N/A or description
Vessel Measurements
Length Overall (ft.):Draft (ft):<-- Enter dimensions
Beam (ft.):Gross Tonnage (GT):<-- Enter dimension/tonnage
Vessel Measurements - Passenger Loading Areas
Distance from bow to forwardmost passenger loading gate (ft):<-- Enter dimension, or N/A
Distance from forwardmost passenger loading gate to aft gate (ft.):<-- Enter dimension, or N/A
Freeboard at bow loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at forward loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at aft loading gate, if present (ft-in):<-- Enter dimension, or N/A
Description of Features
Description of hydraulic, sewage, sanitary, electrical, firefighting, and safety features aboard vessel:
<-- Enter description of this equipment and features
Other special features:
<-- Enter description of any other notable features
VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)4Vessel Name:0
USCG Registration Number:0Current Owner:0
Description of Accessibility Features
Bridgeplate:<-- Describe accessible features
Bathrooms:<-- Describe accessible features
Telephones:<-- Describe accessible features
Wheelchair Tie-Down Equipment:
Type of Securement:
(i.e. belts, clamps, etc.)<-- Describe type(s) of wheelchair tie down equipment
Manufacturer:No. of wheelchair positions:<-- Enter Manufacturer of wheelchair tie-down equipment and enter the number of wheelchair positions
Model:Date Installed:<--Enter model of wheelchair tie-down equipment and the date it was installed.
List other features which make vessel accessible to persons with disabilities:
<-- Describe accessible features
PROPOSED VESSEL UTILIZATION SHEETMake font BOLD for the trips that would be operated by this vessel:<--- follow these directions
Route F1: Hingham Ferry
Complete one sheet for each vesselHinghamLong WharfLong WharfHingham
The purpose of this sheet is to identify which of the proposed vessels will be used for each trip, in the full service schedule. Which vessels are designated for each trip will be a factor in determining whether the proposed vessels will meet the required passenger capacities in the evaluation of each proposal. The successful operator will be expected to operate service in accordance with this vessel listing.(depart)(arrive)(depart)(arrive)
6:00 AM6:30 AM6:50 AM7:20 AM
6:30 AM7:10 AM7:15 AM7:55 AM
6:50 AM7:30 AM7:35 AM8:15 AM
7:15 AM7:45 AM8:00 AM8:30 AM
7:45 AM8:15 AM8:30 AM9:00 AM
8:00 AM8:40 AM--
8:20 AM9:00 AM--
8:45 AM9:15 AM--
9:15 AM9:45 AM10:00 AM10:40 AM
Vessel Identification11:00 AM11:40 AM--
Vessel List Number:4--1:30 PM2:10 PM
Vessel Name:02:30 PM3:10 PM3:25 PM4:05 PM
Max. Vessel Speed:0 knots--4:00 PM4:40 PM
--4:30 PM5:00 PM
Passenger Capacity4:10 PM4:50 PM5:00 PM5:40 PM
Passenger Capacity:0--5:20 PM5:50 PM
Fixed Passenger Seats (Qty):04:45 PM5:25 PM5:40 PM6:20 PM
Upholstered Seats (Yes or No):05:15 PM5:45 PM6:00 PM6:30 PM
Passenger Seats At Tables (Qty):05:45 PM6:25 PM6:30 PM7:10 PM
6:10 PM6:40 PM7:00 PM7:30 PM
Average Vessel Fuel Use: (Gallons Per Hour)6:40 PM7:10 PM7:30 PM8:00 PM
Idling:07:40 PM8:10 PM8:30 PM9:00 PM
Operating:0
Vessel Trip Time
Hingham - Rowes Wharf:0 minutes
Fuel Consumption per Trip
Hingham - Rowes Wharf:0 gallons
Fuel Type:
0
The above listed vessel is able to operate the specified ferry service with no modifications to the schedule listed in the RFP: (select Yes or No)<-- Select Yes or No from the dropdown menu
If NO, list all modifications that would be required to the schedule of operated with this vessel:
<-- If applicable, enter any necessary schedule modifications -->
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)4Vessel Name:0
Is this vessel already constructed and ready for service (yes or no):<-- Select Yes or No
For: Existing Vessels<-- Complete this section unless you are proposing to use vessels that are currently under construction.
Vessel History(For vessels under construction, complete the "Vessels to be Constructed" section below)
Year Vessel Built:0
Vessel Age (years):2024 years
Estimated remaining vessel service life (years):<-- Enter estimate years
Type and quantity of power plant:<-- Enter type and quantity
Number of hours logged on each engine to date:<-- Enter hours on each engine
Date and nature of most recent routine maintenance or repair:
<-- Enter description
Date and nature of most recent major vessel maintenance or repair:
<-- Enter description
Date and nature of most recent external hull maintenance above the water line:
<-- Enter description
Date and nature of most recent internal or external hull maintenance below the waterline:
<-- Enter description
Date of most recent marine survey of this vessel:<-- Enter date
USCG Inspections
Offerer must attach the most recent Coast Guard Inspection, deficiencies found and date of repairs.<-- Attach USCG inspection documentation with proposal
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)4Vessel Name:0
For: Vessels To Be Constructed<-- Complete this section only if you are proposing to use vessels that are currently under construction.
Vessel Identification
Make:0Passenger Capacity:0
Model:0Power Plant
Type and Qty:<--Enter type and quantity of power plant
Vessel Construction
Vessel construction schedule including confirmation of proposed delivery date by shipbuilder:
(Offeror must include attachments verifying this information)
<--indicate the construction and delivery schedule, AND attach documentation.
PROPOSED VESSEL CERTIFICATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel List Number:4Vessel Top Speed:0 knots
Vessel Name:0
Name of Firm:<-- Enter the Offeror's Corporate Name

I, , hereby certify that: <-- Enter the Signer's Name

1. The dimensions and maneuvering capabilities of the above listed vessel will allow for safe and efficient docking at the designated terminal and intermediate stop locations for the designated route at all tide conditions.

2. I am familiar with the physical conditions and navigational constraints at the existing docking facilities for the above listed route.

3. The above listed vessel can operate safely and efficiently at these berthing facilities and meet all requirements of this specification for the above listed route.

4.The draft of the above listed vessel, when fully loaded, shall be shallow enough to operate where required to operate their assigned ferry services during all tide conditions.
Signature:<-- Sign this form

Name: <-- Enter the Signer's Name

Name of Firm: <-- Enter the Offeror's Corporate Name

NOTE: THIS INFORMATION TO BE INCLUDED IN THE CONTRACT

Vessel 5

VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)5Vessel Name:0
USCG Registration Number:0Current Owner:0
Make:0Passenger Capacity:0
Model:0Year Vessel Built:0
Fuel Type:0
Vessel Usage
Will this vessel be dedicated to this service?<-- Select Yes or No
If it will be used for other purposes please briefly describe:
<-- Enter N/A or description
Vessel Measurements
Length Overall (ft.):Draft (ft):<-- Enter dimensions
Beam (ft.):Gross Tonnage (GT):<-- Enter dimension/tonnage
Vessel Measurements - Passenger Loading Areas
Distance from bow to forwardmost passenger loading gate (ft):<-- Enter dimension, or N/A
Distance from forwardmost passenger loading gate to aft gate (ft.):<-- Enter dimension, or N/A
Freeboard at bow loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at forward loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at aft loading gate, if present (ft-in):<-- Enter dimension, or N/A
Description of Features
Description of hydraulic, sewage, sanitary, electrical, firefighting, and safety features aboard vessel:
<-- Enter description of this equipment and features
Other special features:
<-- Enter description of any other notable features
VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)5Vessel Name:0
USCG Registration Number:0Current Owner:0
Description of Accessibility Features
Bridgeplate:<-- Describe accessible features
Bathrooms:<-- Describe accessible features
Telephones:<-- Describe accessible features
Wheelchair Tie-Down Equipment:
Type of Securement:
(i.e. belts, clamps, etc.)<-- Describe type(s) of wheelchair tie down equipment
Manufacturer:No. of wheelchair positions:<-- Enter Manufacturer of wheelchair tie-down equipment and enter the number of wheelchair positions
Model:Date Installed:<--Enter model of wheelchair tie-down equipment and the date it was installed.
List other features which make vessel accessible to persons with disabilities:
<-- Describe accessible features
PROPOSED VESSEL UTILIZATION SHEETMake font BOLD for the trips that would be operated by this vessel:<--- follow these directions
Route F1: Hingham Ferry
Complete one sheet for each vesselHinghamLong WharfLong WharfHingham
The purpose of this sheet is to identify which of the proposed vessels will be used for each trip, in the full service schedule. Which vessels are designated for each trip will be a factor in determining whether the proposed vessels will meet the required passenger capacities in the evaluation of each proposal. The successful operator will be expected to operate service in accordance with this vessel listing.(depart)(arrive)(depart)(arrive)
6:00 AM6:30 AM6:50 AM7:20 AM
6:30 AM7:10 AM7:15 AM7:55 AM
6:50 AM7:30 AM7:35 AM8:15 AM
7:15 AM7:45 AM8:00 AM8:30 AM
7:45 AM8:15 AM8:30 AM9:00 AM
8:00 AM8:40 AM--
8:20 AM9:00 AM--
8:45 AM9:15 AM--
9:15 AM9:45 AM10:00 AM10:40 AM
Vessel Identification11:00 AM11:40 AM--
Vessel List Number:5--1:30 PM2:10 PM
Vessel Name:02:30 PM3:10 PM3:25 PM4:05 PM
Max. Vessel Speed:0 knots--4:00 PM4:40 PM
--4:30 PM5:00 PM
Passenger Capacity4:10 PM4:50 PM5:00 PM5:40 PM
Passenger Capacity:0--5:20 PM5:50 PM
Fixed Passenger Seats (Qty):04:45 PM5:25 PM5:40 PM6:20 PM
Upholstered Seats (Yes or No):05:15 PM5:45 PM6:00 PM6:30 PM
Passenger Seats At Tables (Qty):05:45 PM6:25 PM6:30 PM7:10 PM
6:10 PM6:40 PM7:00 PM7:30 PM
Average Vessel Fuel Use: (Gallons Per Hour)6:40 PM7:10 PM7:30 PM8:00 PM
Idling:07:40 PM8:10 PM8:30 PM9:00 PM
Operating:0
Vessel Trip Time
Hingham - Rowes Wharf:0 minutes
Fuel Consumption per Trip
Hingham - Rowes Wharf:0 gallons
Fuel Type:
0
The above listed vessel is able to operate the specified ferry service with no modifications to the schedule listed in the RFP: (select Yes or No)<-- Select Yes or No from the dropdown menu
If NO, list all modifications that would be required to the schedule of operated with this vessel:
<-- If applicable, enter any necessary schedule modifications -->
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)5Vessel Name:0
Is this vessel already constructed and ready for service (yes or no):<-- Select Yes or No
For: Existing Vessels<-- Complete this section unless you are proposing to use vessels that are currently under construction.
Vessel History(For vessels under construction, complete the "Vessels to be Constructed" section below)
Year Vessel Built:0
Vessel Age (years):2024 years
Estimated remaining vessel service life (years):<-- Enter estimate years
Type and quantity of power plant:<-- Enter type and quantity
Number of hours logged on each engine to date:<-- Enter hours on each engine
Date and nature of most recent routine maintenance or repair:
<-- Enter description
Date and nature of most recent major vessel maintenance or repair:
<-- Enter description
Date and nature of most recent external hull maintenance above the water line:
<-- Enter description
Date and nature of most recent internal or external hull maintenance below the waterline:
<-- Enter description
Date of most recent marine survey of this vessel:<-- Enter date
USCG Inspections
Offerer must attach the most recent Coast Guard Inspection, deficiencies found and date of repairs.<-- Attach USCG inspection documentation with proposal
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)5Vessel Name:0
For: Vessels To Be Constructed<-- Complete this section only if you are proposing to use vessels that are currently under construction.
Vessel Identification
Make:0Passenger Capacity:0
Model:0Power Plant
Type and Qty:<--Enter type and quantity of power plant
Vessel Construction
Vessel construction schedule including confirmation of proposed delivery date by shipbuilder:
(Offeror must include attachments verifying this information)
<--indicate the construction and delivery schedule, AND attach documentation.
PROPOSED VESSEL CERTIFICATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel List Number:5Vessel Top Speed:0 knots
Vessel Name:0
Name of Firm:<-- Enter the Offeror's Corporate Name

I, , hereby certify that: <-- Enter the Signer's Name

1. The dimensions and maneuvering capabilities of the above listed vessel will allow for safe and efficient docking at the designated terminal and intermediate stop locations for the designated route at all tide conditions.

2. I am familiar with the physical conditions and navigational constraints at the existing docking facilities for the above listed route.

3. The above listed vessel can operate safely and efficiently at these berthing facilities and meet all requirements of this specification for the above listed route.

4.The draft of the above listed vessel, when fully loaded, shall be shallow enough to operate where required to operate their assigned ferry services during all tide conditions.
Signature:<-- Sign this form

Name: <-- Enter the Signer's Name

Name of Firm: <-- Enter the Offeror's Corporate Name

NOTE: THIS INFORMATION TO BE INCLUDED IN THE CONTRACT

Vessel 6

VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)6Vessel Name:0
USCG Registration Number:0Current Owner:0
Make:0Passenger Capacity:0
Model:0Year Vessel Built:0
Fuel Type:0
Vessel Usage
Will this vessel be dedicated to this service?<-- Select Yes or No
If it will be used for other purposes please briefly describe:
<-- Enter N/A or description
Vessel Measurements
Length Overall (ft.):Draft (ft):<-- Enter dimensions
Beam (ft.):Gross Tonnage (GT):<-- Enter dimension/tonnage
Vessel Measurements - Passenger Loading Areas
Distance from bow to forwardmost passenger loading gate (ft):<-- Enter dimension, or N/A
Distance from forwardmost passenger loading gate to aft gate (ft.):<-- Enter dimension, or N/A
Freeboard at bow loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at forward loading gate, if present (ft-in):<-- Enter dimension, or N/A
Freeboard at aft loading gate, if present (ft-in):<-- Enter dimension, or N/A
Description of Features
Description of hydraulic, sewage, sanitary, electrical, firefighting, and safety features aboard vessel:
<-- Enter description of this equipment and features
Other special features:
<-- Enter description of any other notable features
VESSEL INFORMATION SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel
Vessel Identification
Vessel Number:
(from Vessel List)6Vessel Name:0
USCG Registration Number:0Current Owner:0
Description of Accessibility Features
Bridgeplate:<-- Describe accessible features
Bathrooms:<-- Describe accessible features
Telephones:<-- Describe accessible features
Wheelchair Tie-Down Equipment:
Type of Securement:
(i.e. belts, clamps, etc.)<-- Describe type(s) of wheelchair tie down equipment
Manufacturer:No. of wheelchair positions:<-- Enter Manufacturer of wheelchair tie-down equipment and enter the number of wheelchair positions
Model:Date Installed:<--Enter model of wheelchair tie-down equipment and the date it was installed.
List other features which make vessel accessible to persons with disabilities:
<-- Describe accessible features
PROPOSED VESSEL UTILIZATION SHEETMake font BOLD for the trips that would be operated by this vessel:<--- follow these directions
Route F1: Hingham Ferry
Complete one sheet for each vesselHinghamLong WharfLong WharfHingham
The purpose of this sheet is to identify which of the proposed vessels will be used for each trip, in the full service schedule. Which vessels are designated for each trip will be a factor in determining whether the proposed vessels will meet the required passenger capacities in the evaluation of each proposal. The successful operator will be expected to operate service in accordance with this vessel listing.(depart)(arrive)(depart)(arrive)
6:00 AM6:30 AM6:50 AM7:20 AM
6:30 AM7:10 AM7:15 AM7:55 AM
6:50 AM7:30 AM7:35 AM8:15 AM
7:15 AM7:45 AM8:00 AM8:30 AM
7:45 AM8:15 AM8:30 AM9:00 AM
8:00 AM8:40 AM--
8:20 AM9:00 AM--
8:45 AM9:15 AM--
9:15 AM9:45 AM10:00 AM10:40 AM
Vessel Identification11:00 AM11:40 AM--
Vessel List Number:6--1:30 PM2:10 PM
Vessel Name:02:30 PM3:10 PM3:25 PM4:05 PM
Max. Vessel Speed:0 knots--4:00 PM4:40 PM
--4:30 PM5:00 PM
Passenger Capacity4:10 PM4:50 PM5:00 PM5:40 PM
Passenger Capacity:0--5:20 PM5:50 PM
Fixed Passenger Seats (Qty):04:45 PM5:25 PM5:40 PM6:20 PM
Upholstered Seats (Yes or No):05:15 PM5:45 PM6:00 PM6:30 PM
Passenger Seats At Tables (Qty):05:45 PM6:25 PM6:30 PM7:10 PM
6:10 PM6:40 PM7:00 PM7:30 PM
Average Vessel Fuel Use: (Gallons Per Hour)6:40 PM7:10 PM7:30 PM8:00 PM
Idling:07:40 PM8:10 PM8:30 PM9:00 PM
Operating:0
Vessel Trip Time
Hingham - Rowes Wharf:0 minutes
Fuel Consumption per Trip
Hingham - Rowes Wharf:0 gallons
Fuel Type:
0
The above listed vessel is able to operate the specified ferry service with no modifications to the schedule listed in the RFP: (select Yes or No)<-- Select Yes or No from the dropdown menu
If NO, list all modifications that would be required to the schedule of operated with this vessel:
<-- If applicable, enter any necessary schedule modifications -->
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)6Vessel Name:0
Is this vessel already constructed and ready for service (yes or no):<-- Select Yes or No
For: Existing Vessels<-- Complete this section unless you are proposing to use vessels that are currently under construction.
Vessel History(For vessels under construction, complete the "Vessels to be Constructed" section below)
Year Vessel Built:0
Vessel Age (years):2024 years
Estimated remaining vessel service life (years):<-- Enter estimate years
Type and quantity of power plant:<-- Enter type and quantity
Number of hours logged on each engine to date:<-- Enter hours on each engine
Date and nature of most recent routine maintenance or repair:
<-- Enter description
Date and nature of most recent major vessel maintenance or repair:
<-- Enter description
Date and nature of most recent external hull maintenance above the water line:
<-- Enter description
Date and nature of most recent internal or external hull maintenance below the waterline:
<-- Enter description
Date of most recent marine survey of this vessel:<-- Enter date
USCG Inspections
Offerer must attach the most recent Coast Guard Inspection, deficiencies found and date of repairs.<-- Attach USCG inspection documentation with proposal
VESSEL HISTORY DATA SHEET
Route F1: Hingham Ferry
Complete one sheet for each vessel

Complete the top portion only for existing vessels.

Complete the bottom portion only for vessels to be constructed prior to the Contract start.

Vessel Identification
Vessel Number:
(from Vessel List)6Vessel Name:0
For: Vessels To Be Constructed<-- Complete this section only if you are proposing to use vessels that are currently under construction.
Vessel Identification
Make:0Passenger Capacity:0
Model:0Power Plant
Type and Qty:<--Enter type and quantity of power plant
Vessel Construction
Vessel construction schedule including confirmation of proposed delivery date by shipbuilder: