This document provides details for a Multiple Award Task Order Contract (MATOC) opportunity with the Department of Veterans Affairs. The MATOC seeks approximately six contractors to provide construction services for two years at medical centers in Wilmington, Delaware and Coatesville, Pennsylvania. Services include interior and exterior renovations, electrical, plumbing, HVAC, fire suppression, communications and construction of new facilities. Projects will range from $2,000 to $5.5 million individually under the $100 million total ceiling for all contracts. The solicitation is set aside for Service Disabled Veteran Owned Small Businesses. The anticipated release date for the solicitation is January 3, 2018 with responses due approximately two weeks after issuance. Awards will be made based on technical, past performance and price factors.

VA244-17-R-1057 00006 VA244-17-R-1057 00006.docx

View the file

Other files

File Type Posted
VA244-17-R-1057-008.docx DOCX document
VA244-17-R-1057-00009000.docx DOCX document
VA244-17-R-1057-00008000.docx DOCX document
VA244-17-R-1057-00008001.xls XLS spreadsheet
VA244-17-R-1057-00007000.docx DOCX document
VA244-17-R-1057-00005002.pdf PDF
VA244-17-R-1057-00005000.docx DOCX document
VA244-17-R-1057-00005001.pdf PDF
VA244-17-R-1057-00004000.docx DOCX document
VA244-17-R-1057-00003000.docx DOCX document
VA244-17-R-1057-00002000.docx DOCX document
VA244-17-R-1057-00001000.docx DOCX document
VA244-17-R-1057-00001003.pdf PDF
VA244-17-R-1057-00001001.docx DOCX document
VA244-17-R-1057-00001002.pdf PDF
VA244-17-R-1057-007.pdf PDF
VA244-17-R-1057-003.docx DOCX document
VA244-17-R-1057-005.pdf PDF
VA244-17-R-1057-006.pdf PDF
VA244-17-R-1057-004.xls XLS spreadsheet
VA244-17-R-1057-002.docx DOCX document
VA244-17-R-1057-001.docx DOCX document
VA244-17-R-1057-000.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 00006 03-09-2018 none 00244 Department of Veterans Affairs Network Contracting Office 4

00244 Department of Veterans Affairs Network Contracting Office 4

To all Offerors/Bidders

VA244-17-R-1057

03-09-2018

X X x The purpose of this amendment is to provide answers to submitted questions.

MICHAEL F. WHITE

Contract Officer michael.white9@va.gov Amendment 6

1. Is this project sales tax exempt? If the project is sales tax exempt can the government provide sales tax exemption certificate?

A. No, this is not a tax exempt project. We do not anticipate any Task Orders under the MATOC will be tax exempt.

2. Will the VA consider using Vendor Portal for the Task orders under this MATOC?

A. The Vendor Portal will not be used for issuing Task Orders under the MATOC, as indicated in SCR 9, TO will be electronically sent directly to the MATOC holders.

3. Is the pricing form in the solicitation required in total for this requirement?

A. The Price Schedule is required for the Seed Project, and will also be used to determine price fair and reasonable for the overall MATOC awards.

4. Will the pricing form in the solicitation be used for all task orders under the contract?

A. Not necessarily, as each MATOC task order will stand on its own.

5. Can the VA award part of the project based on the provided pricing form?

A. The VA intends to award the entire seed project under one Task Order to one MATOC holder

6. Based on the pricing form in the solicitation for the seed project, will the contractor be required to maintain the same overhead and profit percentages throughout the MATOC?

A. Not necessarily, as vendor’s OH & Profit may be adjusted over time. MATOC holders are not proposing a set OH & Profit percentage on the base MATOC.

7. . If a company is awarded the MATOC as an SDVOSB but at some point, during the contract becomes “other than small”, will that contractor still be allowed to bid task orders since they were “small” at the time of MATOC award?

A. Yes

8. Will the contractor be able to spot a dumpster at each building and near the area of work?

A. Yes, per the COR’s discretion

9. The flooring in Building 3 looks fairly new yet it is severely buckled in many areas and some depressions were observed. Can you provide information regarding the previous installation including subfloor prep, underlayment material, and warranty determinations?

A. The leveling material has decomposed turning to dust. No moisture tests have occurred. There is no temperature difference in the other sections of the floor in the vicinity.

10. Will the VCT under the existing carpet in Building 1 need to be removed prior to vinyl plank flooring installation A. Yes

11. Has standing water been observed in the Building 3 basement hallways?

A. Never

12. We understand that projects under this MATOC will be under $5.5 million per the solicitation. What is the reasoning for this?

A. See the Federal Acquisition Regulation Part 16.505(b)(1)(i)(ii) and (iii)

13. How many days are you giving the General Contractor to complete the Seed Project?

A. Answer is located in the statement of work.

14. Regarding the Seed Project, Building 38 Second Floor Hallways cove base, what gets painted, the portion of the existing that does not get covered by the new 4”? Why can’t a 6” cove base be used to cover the existing 5.5” high masonry faux type?

A. Above the new 4” cove base will be painted black. The reason that 6” wasn’t selected is because of the concern of how the new cove base would adhere above the rounded portion of the masonry cove base at the top.

15. Regarding the Seed Project, the required work per Building, can this be done all at once or will it have to be phased?

A. Must be done in phases to accommodate VA employees dislocated for construction and VA furniture movers to accommodate this. Hallways can be done simultaneously.