This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Higgins (DDG-76), specifically focused on a Tightness & Operational Test for the Potable Water System. The TGI is dated 03-MAY-2025 with the identification number 53311-3-300KTR, and is associated with Project KB2 and System 53311. Key personnel involved include Morita Matsuki as the preparer and Jason Y. Ohta as the approver, both from Code 246.2. The zone manager is identified as Yaginuma Takehide. The document references a technical procedure (TP 53311-3-300KTR) for the Potable Water System Test and Operational (T & OP) process, with the job summary ID 645A1111, though specific man-hours, duration, and total job cost are not populated on this form.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6264925RA051-0002.pdf | ||
| N6264925RA051-0003.pdf | ||
| TGI_38KB264511A03_c0v0 FY26.pdf | ||
| N6264925RA051-0001.pdf | ||
| TGI_38KB212317A01_c2v2 FY26.pdf | ||
| TGI_38KB264512A01_c0v0 FY26.pdf | ||
| TGI_38KB264511T01_c0v0 FY26.pdf | ||
| TGI_38KB264505A02_c0v0 FY26.pdf | ||
| TGI_38KB212317A01_c2v2.pdf | ||
| TGI_38KB264505T01_c0v0 FY26.pdf | ||
| TGI_38KB244101A01_c0v0 FY26.pdf | ||
| TGI_38KB264510A01_c0v0 FY26.pdf | ||
| N6264925RA051.pdf | ||
| Att III RFI 25RA051.docx | DOCX document | |
| TGI_38KB264512A01_c0v0.pdf | ||
| TGI_38KB264510A01_c0v0.pdf | ||
| N6264925RA051.pdf | ||
| Att II Price Proposal Form N6264925RA051.xlsx | XLSX spreadsheet | |
| TGI_38KB264511A03_c0v0.pdf | ||
| Att III RIF 25RA051.docx | DOCX document | |
| TGI_38KB264505A02_c0v0.pdf | ||
| TGI_38KB244101A01_c0v0.pdf | ||
| TGI_38KB264505T01_c0v0.pdf | ||
| Att IV GFP_GFM listings.xlsx | XLSX spreadsheet |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
03-MAY-2025 1017
20.14.15.2.9020 (September 2024) ICN: 38KB264511 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 53311-3-300KTR TT T 1 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-76 USS HIGGINS KB2 53311
CU PHASE TITLE: POTABLE WATER SYS (T & OP) - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
NN010978
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
MORITA, MATSUKI 246.2 3152432332 01-MAY-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 01-MAY-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
NN01-0978
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
645A1111
Tightness & Operational Test for Potable Water System - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
03-MAY-2025 1017
20.14.15.2.9020 (September 2024) (Continued) ICN: 38KB264511 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 53311-3-300KTR TT T 1 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-76 USS HIGGINS KB2 53311
CU PHASE TITLE: POTABLE WATER SYS (T & OP) - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 53311-3-300KTR POTABLE WATER SYS (T &
OP) - KTR
LAT Y
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38KB264511 KEY OP: T01