Technical Exhibit 3 Scheduled Services.docx

DOCX document 21 KB Posted

Attached to
Preventive Maintenance (PM), Repair, and Cleaning Service at Army Family Housing, Camp Walker
Solicitation number
W90VN924R0024
Issued by

About this file

This document is a Technical Exhibit that details the Schedule of Services for an Army contract for Preventive Maintenance, Repair, and Cleaning Services at Army Family Housing at Camp Walker.

The exhibit outlines the required response times and completion timelines for various service orders, including emergency (30 minutes), urgent (24 hours), and routine (2 workdays). It also specifies the work completion timelines for change of occupancy tasks such as interior painting, plumbing repairs, flooring replacement, and unit cleaning based on unit size. Additional details are provided on concurrent work activities and factors that may affect the average completion times. The related federal contract opportunity is a solicitation (W90VN924R0024) for these preventive maintenance, repair, and cleaning services at the Army Family Housing at Camp Walker, with a closing date of June 28, 2024.

View the file

Other files

File Type Posted
Amendment 0001 to 24R0024.pdf PDF
Technical Exhibit 18 Tower1 Custodial Drawing.pdf PDF
Technical Exhibit 21 Tower1 Elec Drawing 1.pdf PDF
Technical Exhibit 26 Tower2 Exterior Window Cleaning Drawing.pdf PDF
Technical Exhibit 5 Vacant Qtrs Montly Report.docx DOCX document
Technical Exhibit 27 Tower2 Ground Maintenance Map.pdf PDF
Attachment-ELIN List for CLIN X022.pdf PDF
Technical Exhibit 53 Tower4 Mech and Plumbing Drawing 3.pdf PDF
Technical Exhibit 14 Contract Descepancy Report (CDR).pdf PDF
Technical Exhibit 33 Tower2 Bed Type Drawing.pdf PDF
Technical Exhibit 25 Tower2 Custodial Drawing.pdf PDF
Technical Exhibit 30 Tower2 Elec Drawing-3.pdf PDF
AFH-Maintenance_Exhibit-list.docx DOCX document
Technical Exhibit 4 Monthly Service Order Report.docx DOCX document
Technical Exhibit 8 COP Check List.docx DOCX document
Technical Exhibit 17 Check Lists.docx DOCX document
RFP-W90VN924R0024.pdf PDF
Technical Exhibit 40 Tower3 Mech and Plumbing Drawing 1.pdf PDF
Technical Exhibit 6 Quality and Standards of Work.docx DOCX document
Technical Exhibit 46 Tower4 Exterior Window Cleaning Drawing.pdf PDF
Technical Exhibit 50 Tower4 Elec Drawing 2.pdf PDF
Technical Exhibit 31 Tower2 Elec Drawing 4.pdf PDF
Technical Exhibit 11 Daily Contract Inspection Report.docx DOCX document
Technical Exhibit 51 Tower4 Mech and Plumbing Drawing 1.pdf PDF
Technical Exhibit 47 Tower4 Exterior Window Cleaning Drawing.pdf PDF
Technical Exhibit 22 Tower1 Elec Drawing-2.pdf PDF
Technical Exhibit 16 COM Monthly Report.xlsx XLSX spreadsheet
Technical Exhibit 20 Tower1 Ground Maintenance Map.pdf PDF
Technical Exhibit 48 Tower4 Ground Maintenance Map.pdf PDF
Technical Exhibit 28 Tower2 Elec Drawing-1.pdf PDF
Technical Exhibit 43 Tower3 Bed Type Drawing.pdf PDF
Technical Exhibit 1 PRS.docx DOCX document
Technical Exhibit 13 Contract Reminder.docx DOCX document
Technical Exhibit 45 Tower4 Custodial Drawing.pdf PDF
Technical Exhibit 52 Tower4 Mech and Plumbing Drawing 2.pdf PDF
Technical Exhibit 2 Deliverables.docx DOCX document
Technical Exhibit 37 Tower3 Ground Maintenance Map.pdf PDF
Technical Exhibit 54 Tower4 Bed Type Drawing.pdf PDF
Technical Exhibit 12 Sample NCIR.docx DOCX document
Technical Exhibit 29 Tower2 Elec Drawing-2.pdf PDF
Technical Exhibit 38 Tower3 Elec Drawing 1.pdf PDF
Technical Exhibit 36 Tower3 Exterior Window Cleaning Drawing 2.pdf PDF
Technical Exhibit 41 Tower3 Mech and Plumbing Drawing 2.pdf PDF
Technical Exhibit 35 Tower3 Exterior Window Cleaning Drawing 1.pdf PDF
Technical Exhibit 44 Custodial Working Schedule.docx DOCX document
Technical Exhibit 23 Tower1 Mech and Plumbing Drawing.pdf PDF
Technical Exhibit 7 COC Check List.xlsx XLSX spreadsheet
Technical Exhibit 49 Tower4 Elec Drawing 1.pdf PDF
Technical Exhibit 34 Tower3 Custodial Drawing.Revised.pdf PDF
Technical Exhibit 42 Tower3 Mech and Plumbing Drawing 3.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 3

SCHEDULE OF SERVICES

Description Response Time Completion Time

Service Orders:

Emergency30 minutes during theContinuous until safe
(Priority 1)contractor's normaland secure, and complete work hours, 45 minuteswithin two working days
other than the contractor’s
normal work hours, except
gas leaks shall be 30
minutes at all times.

Urgent 24 hours Two workdays (Priority 2)

Routine Two workdays Four Workdays (Priority 3)

Change of Occupancy Work :

Item Work Description Work Completion Day

1COP Interior painting to include repair, prepare,
Prime, and paint walls, ceilings, cabinets,
Doors, windows and trim, including
Replacement of wall coverings including balcony

Painting if needed.

(a) DU less than 1,500 NSF (139.4 NSM)2 days
(b) DU 1,500 to 3,000 NSF (139.4 to 278.7 NSM)3 day
(c) DU greater than 3,000 NSF (278.7 NSM)4 days
2Replace a sink, lavatory, faucet, flush valve,
or water closet.0.5 days

3 Replace kitchen countertop. 1 day

4 COM Miscellaneous repair and replacement work. 1 day

5Replace resilient flooring (tile and sheet vinyl).
(a) DU less than 200 SF/18.6 SM to be retiled.1 day
(b) DU more than 200 SF/18.6 SM to be retiled.2 days

6 Replace carpet and pad or steam clean carpet. 1 day

7Replace a bathtub or shower receptor
including ceramic tile.3 days
8COC Complete DU cleaning.
(a) DU with less than 1,500 NSF/139.4 NSM1 day
(b) DU 1,500 and 3,000 NSF/139.4 to 278.7 NSM2 days
(c) DU greater than 3,000 NSF/ 278.7 NSM3 days
9Repair, prepare, and refinish wood floors, stair treads,
risers, landings, banisters, and railings.4 days
10.RepairWorkday after receipt7 days
Smoke and Fireor as ordered

Damaged Quarters

* Net Square Feet (NSF), Net Square Meter (NSM), Dwelling Unit (DU) Note:

a. The amount of time shown for each item above is an average and may vary at any installation. Factors which may affect the average times are climatic (more humid areas may require more time for paint and floor finish to dry); higher than normal turnover of DUs which would overextend the contractor’s ability to meet the scheduled times (this shall not be reflected in contractor’s schedule of times but shall be negotiated separately if and when it occurs).

b. Items 1 through 4 will be done concurrently. The time allowed for the combination of items will be the longest time for that item which has the largest time.

c. Items 5 through 8 may be done concurrently with any one or combination of items 1 through 8 providing there are no physical conflicts in performing the work. (For example: items 2, 3, and 6 could be done concurrently. The time allowed for all three would be 1 day.) Where there is a conflict, times for items in conflict will be added together to give the total time allowed. (For example, the combination of items 1(b) and 6 will give a total time of 4 days.)

d. Item 9 shall not be done concurrently with other work items.

** Tower #1 3 bedroom : 1636 sf , 4 bedroom : 1890 sf , 3 bedroom : 2164 sf ,