Specifications and Submittals Procedures.pdf

PDF 200 KB Posted

Attached to
Demolition of Building 5022 & 1906 Federal contract opportunity
Solicitation number
FA301022R0004
Issued by
Department of the Air Force Air Education and Training Command

About this file

This solicitation requests proposals for the demolition of two buildings at a military base. The solicitation seeks demolition of Building 5022 with a project magnitude between $500,000 and $1,000,000. This acquisition is set aside as a 100% Service Disabled Veteran Owned Small Business. Offerors must acknowledge any amendments and attend an organized site visit on December 20, 2021 at 2:30 PM CST to gain base access. No award will be made until funds are available, and the Government reserves the right to cancel the solicitation before or after the closing date. Proposals are due by the instructions in 52.212-1 and will be evaluated based on the factors in 52.212-2. The solicitation was issued by the Department of the Air Force Air Education and Training Command for the demolition of buildings located at a military base.

View the file

Other files for this federal contract opportunity

Other files attached to Demolition of Building 5022 & 1906, newest first.
File Type Posted
Questions and Answers - Demolition 11 Jan 2022.pdf PDF
FA301022R00040004.pdf PDF
Tree Protection Guidance.pdf PDF
Integra CT30 Locks.pdf PDF
1906 ACM Survey Notes.pdf PDF
1906 HA Sheet.pdf PDF
Demo. Heritage and VQ Buildings- Addendum #1.docx DOCX document
B1906 Asbestos Report.pdf PDF
B5022 Asbestos Report.pdf PDF
Demo B5022 and B1906 Site Visit Sign In 6 January 2022.pdf PDF
Q and A - Demolition_3 Jan 2022.pdf PDF
Amendment 003--SF 30.pdf PDF
Site Visit Information_3 Jan 2022.pdf PDF
Environmental Management Contractor Packet_Sep 2021.pdf PDF
Q and A - Demo_30 Dec 2021.pdf PDF
Amendment 002--SF 30.pdf PDF
Site Visit Information_30 Dec 2021.pdf PDF
MAHG211035 - Demolition Hertiage Bldg B1906 SOW.pdf PDF
MAHG211035 Demolition Heritage Bldg B1906 MSS.xls XLS spreadsheet
FA301022R00040001.pdf PDF
MAHG211035 - Drawings.pdf PDF
MAHG211035 - Specifications.pdf PDF
Demo B5022 and B1906 Site Visit sign in.pdf PDF
SF 1444.pdf PDF
Solicitation - FA301022R0004.pdf PDF
WD 15-5147_Rev 15_dated 20 OCT 2021.pdf PDF
Notice of Compliance.pdf PDF
3 Line Reference - Past Performance Reference List.pdf PDF
MAHG211036_Demo B5022_SOW.docx DOCX document
Past Performance Questionnaire.pdf PDF
MAHG211036_Demo B5022_Drawings.pdf PDF
MAHG211036_Demo B5022_MSS.xls XLS spreadsheet
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT A: DEMOLITION MAHG 21-1036

EXISTING CONDITIONS

Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inches will be acceptable as a record of existing conditions. Include in the record possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.

Demolish structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed. Demolish concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing. Building, or the remaining portions thereof, not exceeding 80 feet in height may be demolished by the mechanical method of demolition.

Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.

Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the

Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made. Shut off and cap utilities for future use, as indicated.

Disconnecting Existing Utilities

Remove existing utilities still connected to structure or uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to Vectrus in accordance with instructions of the Contracting Officer.

Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, utilities serving each area of alteration or removal will

ATTACHMENT A: DEMOLITION MAHG 21-1036

be shut off by the Government and disconnected and sealed by the Contractor.

Dust and Debris Control

Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, flooding, or pollution. Vacuum and dust the work area daily or as needed.

Sweep pavements as often as necessary to control the spread of debris. Keep site wet in a manner to prevent ponding but prevent the spreading of dust.

ATTACHMENT B: EXCAVATION MAHG 21-1036

Excavation

The unit of measurement for excavation and borrow will be the cubic yard, computed by the average end area method from cross sections taken before and after the excavation and borrow operations, including the excavation for ditches, gutters, and channel changes, when the material is acceptably utilized or disposed of as herein specified. The measurements will include authorized excavation of unsatisfactory subgrade soil; allowance will be made on the same basis for selected backfill ordered as replacement. The measurement will not include the volume of subgrade material or other material that is scarified or plowed and reused in-place, and will not include the volume excavated without authorization or the volume of any material used for purposes other than directed. The volume of overburden stripped from borrow pits and the volume of excavation for ditches to drain borrow pits, unless used as borrow material, and will not be measured for payment. The measurement will not include the volume of any excavation performed prior to the taking of elevations and measurements of the undisturbed grade.

General Excavation

Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified.

Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Dispose unsatisfactory excavated material in designated waste or spoil areas.

During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times. Excavate material required for fill or embankment in excess of that produced by excavation within the grading limits from the borrow areas indicated or from other approved areas selected by the Contractor as specified.

Grading

Where indicated, divide work into grading areas within which satisfactory excavated material will be placed in embankments, fills, and required backfills. Do not haul satisfactory material excavated in one grading area to another grading area except when so directed in writing. Place and grade stockpiles of satisfactory, unsatisfactory, and wasted materials as specified. Keep stockpiles in a neat and well drained condition, giving due consideration to drainage at all times. Clear, grub, and seal by rubber-tired equipment, the ground surface at stockpile locations; separately stockpile excavated satisfactory and unsatisfactory materials. Protect stockpiles of satisfactory materials from contamination which may destroy the quality and fitness of the stockpiled material. If the Contractor fails to protect the stockpiles, and any material becomes unsatisfactory, remove and replace such material with satisfactory material from approved sources.

Do not excavate to final grade until just before concrete is to be placed.

General Requirements

ATTACHMENT B: EXCAVATION MAHG 21-1036

Remove and replace unsatisfactory material with satisfactory materials, as directed by the Contracting Officer, in surfaces to receive fill or in excavated areas. Scarify the surface to a depth of 6 inches before the fill is started. Plow, step, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material. When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inches, pulverizing, and compacting to the specified density. When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inches and compact it as specified for the adjacent fill.

Compaction

Place backfill adjacent to any and all types of structures, in successive horizontal layers of loose materia not more than 8 inches in depth.

Compact to at least 95 percent laboratory maximum density. Backfill material must be within the range of -2 to +2 percent of optimum moisture content at the time of compaction.

Prepare ground surface on which backfill is to be placed and provide compaction requirements for backfill materials. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas Deposit backfill in layers of a maximum of 12 inches loose thickness, and compact it to 85 percent maximum density.

Topsoil

Material suitable for topsoils obtained from offsite areas is defined as:

Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth.

Amend topsoil pH range to obtain a pH of 5.5 to 7.

SECTION 01 30 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.0 SUMMARY (Not Applicable)

1.1 REFERENCES (Not Applicable)

1.2 SUBMITTAL CLASSIFICATION

1.2.1 Submittals are classified as follows:

1.2.1.1 Contracting Officer Approval: The Contracting Officer (CO) approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the CO. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction", they are considered to be "shop drawings."

1.2.1.2 Information Only: All submittals not requiring the Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.3 APPROVED SUBMITTALS:

The approval of submittals by the CO shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.

Approval will not relieve the Contractor of the responsibility for any error, which may exist, as the Contractor is responsible for the dimensions and design of adequate connections, details and satisfactory construction of all work. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be given consideration unless accompanied by an explanation as to why a substitution is necessary.

1.4 DISAPPROVED SUBMITTALS:

The Contractor shall make all corrections required by the CO and promptly furnish a corrected submittal in the form and number of copies as specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, notice as required under the Contract Clause entitled "Changes" shall be given promptly to the CO.

PART 2 EXECUTION

2.0 GENERAL:

The Contractor shall submit all items listed on the Submittal Register (Material Submittal Schedule (MSS), or equivalent) or specified in the other sections of these specifications. The CO may request submittals in addition to those listed when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same used in the contract drawings. Submittals shall be made in three (3) copies unless otherwise noted on the Submittal Register to the CO. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Prior to submittal, all items shall be checked and approved and each respective transmittal form or material approval submittal (AF 3000, Material Approval Submittal) shall be stamped, signed and dated by the Contractor certifying that the accompanying submittal complies with the contract requirements. Submittals shall include line number of item from Government-prepared Submittal Register. Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals including parts list;

certifications; warranties and other such required submittals. Submittals requiring CO approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby.

2.1 SUBMITTAL REGISTER: Material Submittal Schedule (MSS):

A Submittal Register on the MSS shall be provided to the Contractor as an attachment to the awarded contract. During the pre-construction meeting, the Contractor shall meet with the CO to jointly review the CO prepared Submittal Register. The Contractor shall be responsible for providing all items listed on the Submittal Register in accordance with the scheduled submittal dates.

2.2 SCHEDULING:

Submittals covering component items forming a system or items that are interrelated, shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. The Contractor shall take special care to timely schedule the submittal date required for long lead-time items and shall allow 30 days for CO review action on all submittals except as noted below. No delays, damages, or time extensions will be allowed for time lost in late submittals.

All submittals will be made on AF 3000, Material Approval Submittal as specified below.

2.2.1 The number of days for CO action on the following submittals will be as indicated:

2.2.1.1 Submittals required on the MSS – 10 calendar days.

2.2.1.2 Any submittal that requests or requires deviation from contract drawings or specifications – 14 calendar days.

2.3 TRANSMITTAL FORM (AF 3000, Material Approval Submittal):

AF 3000, Material Approval Submittal shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor by the CO. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted.

Special care will be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.

2.4 CONTROL OF SUBMITTALS:

The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the provided Submittal Register.

2.5 CO APPROVED SUBMITTALS:

Upon completion of review of submittals requiring CO approval, the submittals will be identified as having received approval by being so noted on AF 3000, Material Approval Submittal. Such submittals shall be made in accordance with the Construction Contract Clause entitled "Specifications and Drawings for Construction" and the following: unless otherwise noted on the Submittal Register and when submitting physical documents, three (3) prints of all drawings; or, if catalog cuts, printed specifications or similar publications are used as submittals, three (3) original copies shall be submitted. One corrected copy shall be returned to the Contractor. When submitting documents for review and approval via email, only one copy is required. In cases where "trade names or equal" specifications are used, any equal substitution by the Contractor will be considered a deviation and will require approval. Any submittal requesting a deviation shall be considered as one requiring "approval" action. Payment for materials incorporated into the work will not be allowed if required approvals have not been obtained. Upon completion of review of submittals requiring CO approval, the submittals will be identified as having received approval by being so noted on AF 3000, Material Approval Submittal.

2.6 INFORMATION ONLY SUBMITTALS:

All other submittals are considered to be "Information Only" submittals and may be subject to review action by the CO or may be simply receipt acknowledged. Any submittal “For Information Only” shall be clearly marked “FIO”. Normally, submittals for information only will not be returned. Approval of the Construction Manager (CM) is not required on information only submittals. These submittals will be used for information purposes. The CO reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications and will not prevent the CO from requiring removal and replacement if nonconforming material is incorporated in the work. This also does not relieve the Contractor of the requirement to furnish samples for testing by the CO laboratory or check testing by the CO, in those instances where the technical specifications so prescribe. It shall be the Contractor's responsibility of assuring that the materials and/or equipment covered by that submittal meets the contract requirements. Any such "For Information Only" submittal found to contain errors or omissions shall be resubmitted as one requiring "approval" action. All "For Information Only" submittals shall be made in triplicate unless otherwise specified.

END OF SECTION

Specifications
Attachment A - Demolition Spec
Attachment B - Earthwork Specs

Submittal Procedures

File details come from the government source that posted it. Updated .