This pre-solicitation announcement describes an upcoming invitation for bid for construction services. The Department of Veterans Affairs VA Medical Center in Battle Creek, Michigan will solicit bids to reconfigure space in Operating Room 6 for new high-cost medical equipment at the Ann Arbor VA Medical Center. Work includes floor, wall, ceiling preparation and utility support for sole source equipment installation by the vendor. The contractor will prepare the site and coordinate with the vendor. The fixed-price contract value is between $1 million and $2 million. The solicitation will be available on March 9, 2021 at sam.gov for 180 days of work. The NAICS code is 236220 and size standard is $39.5 million. Bids are due as specified in the solicitation. Offerors must register in SAM, VetBiz, and submit VETS-4212 reports if applicable.

View the file

Other files

File Type Posted
36C25021B0022 0003.docx DOCX document
Q-52148 VA Ann Arbor Hybrid OR 6 Skytron Surgical Lights Booms and Integration Quote with Tax.pdf PDF
041621VA VA Ann Arbor Hybrid OR 6 SLD AirFRAME Modular Ceiling System Quote with Tax.pdf PDF
36C25021B0022 0002.docx DOCX document
041621VA VA Ann Arbor Hybrid OR 6 SLD AirFRAME Modular Ceiling System Quote.pdf PDF
Q-52148 VA Ann Arbor Hybrid OR 6 Skytron Surgical Lights Booms and Integration Quote.pdf PDF
Wage determination MI20210100 2-26-2021.pdf PDF
190103 VA Ann Arbor SLD AirFRAME Submittal Layout.pdf PDF
19-354 VA Ann Arbor Hybrid OR 6 Subs Rev1 2-23-2021 (1).pdf PDF
SLD Indigo Clean Light Fixture Cut Sheets.pdf PDF
36C25021B0022 0001.docx DOCX document
5th floor ICRA plan.pdf PDF
Skytron Freedom Boom Pre-Install Guide.pdf PDF
VHA Directive 1192.01, Seasonal Influenza Prevention Program for VHA Health Care Personnel.pdf PDF
Skytron and SLD Additional Critical Scope of Work Details.pdf PDF
2021 SLD Installation Guide.pdf PDF
Skytron LINX 300 Integration Pre-Installation Manual.pdf PDF
36C25021B0022_1.docx DOCX document
J-A Attachment Skytron Booms 506-CSI-113 (3-11-21).pdf PDF
Contractor EMR Certification Form 2021 - 506-CSI-113.pdf PDF
Wage Determination MI20210100 2-8-2021.pdf PDF
J-A Attachments SLD Air Frame 506-CSI-113 (3-11-21).pdf PDF
Drawings 506-CSI-113.pdf PDF
J-A Attachment Skytron Lights 506-CSI-113 (3-11-21).pdf PDF
REQUEST FOR INFORMATION (RFI) Form 506-CSI-113.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual 100% Bid Documents

VA Ann Arbor Healthcare System Site Prep Angio OR-6 VA Project No. 506-CSI-113

June 1, 2020

6/1/2020

6/1/2020

6/1/2020

6/1/2020

100% Bid Documents Site Prep Angio OR-6 VA Ann Arbor Healthcare System Ann Arbor, Michigan

506-CSI-113

00 01 10 - 1/3

TABLE OF CONTENTS

VA Master Specification 11-18

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

Section 00 01 10 - TABLE OF CONTENTS

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 12-18AA 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 04-13 01 33 23 Shop Drawings, Product Data, and Samples 05-17AA 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 00 Quality Control 01-18 01 45 00 Quality Control Report Form 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 02-15

DIVISION 03 – CONCRETE – NOT USED

DIVISION 04 – MASONRY – NOT USED

DIVISION 05 – METALS – NOT USED

05 12 00 Structural Steel Framing 11-18 05 50 00 Metal Fabrications 07-14

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES – NOT USED

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping

00 01 10 - 2/3

VA Master Specification 11-18

07 92 00 Joint Sealants 10-15

DIVISION 08 – OPENINGS

08 31 13 Access Doors and Frames 02-16

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 22 16 Non-Structural Metal Framing 05-16 09 29 00 Gypsum Board 11-14 09 65 16 Resilient Sheet Flooring 07-13 09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES – NOT USED

DIVISION 11 – EQUIPMENT

11 76 00 Hospital Operating Room, Fully Integrated, Modular Diffuser System 06-18

DIVISION 12 – FURNISHINGS

12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION – NOT USED

DIVISION 14– CONVEYING EQUIPMENT – NOT USED

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17 23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 08 00 Commissioning of HVAC Systems 23 31 00 HVAC Ducts and Casings 03-13

00 01 10 - 3/3

VA Master Specification 11-18

23 36 00 Air Terminal Units 23 37 00 Air Outlets and Inlets 02-15

DIVISION 25 – INTEGRATED AUTOMATION – NOT USED

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 51 00 Interior Lighting 01-18 26 55 71 Medical and Surgical Lighting Fixtures 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 27 05 33 Raceways and Boxes for Communications Systems 27 08 00 Commissioning of Communications Systems 27 15 00 Communications Structured Cabling

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

DIVISION 31 – EARTHWORK – NOT USED

DIVISION 32 – EXTERIOR IMPROVEMENTS – NOT USED

DIVISION 33 – UTILITIES – NOT USED

DIVISION 34 – TRANSPORTATION – NOT USED

DIVISION 48 – ELECTRICAL POWER GENERATION – NOT USED

00 01 15 - 1/1

LIST OF DRAWINGS

VA Master Specifications 07-15

SECTION 00 01 15 - LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

G-001 COVER SHEET

S-106 PARTIAL SIXTH FLOOR FRAMING PLAN AND DETAILS

A-001 ARCHITECTURAL LEGENDS AND SYMBOLS

A-105 PARTIAL DEMOLITION AND FLOOR PLANS

A-115 PARTIAL REFLECTED CEILING PLANS

A-125 PARTIAL EQUIPMENT PLAN

EQ-1 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-2 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-3 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-4 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-5 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-6 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-7 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-8 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

EQ-9 EQUIPMENT DRAWINGS - FOR REFERENCE ONLY

FP-105 PARTIAL FIFTH FLOOR FIRE PROTECTION PLAN

P-001 PLUMBING LEGENDS

P-105 PARTIAL FIFTH FLOOR PLUMBING PLANS

M-001 MECHANICAL LEGENDS

MD-105 PARTIAL MECANICAL DEMOLITION PLANS

M-105 PARTIAL MECHANICAL FLOOR PLANS

M-501 MECHANICAL SCHEDULES AND DETAILS

E-001 ELECTRICAL GENERAL INFORMATION

ED-105 PARTIAL FIFTH FLOOR ELECTRICAL DEMOLTION PLAN

EP-105 PARTIAL FIFTH FLOOR NEW WORK PLAN

END OF SECTION 00 01 15

01 00 00 - 1/16

GENERAL REQUIREMENTS

VISN 10: 11-15

SECTION 01 00 00 - GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to Section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall furnish all labor, materials, equipment, management, supervision, tools, and all other necessary resources to complete project CSI-113 Site Prep Angio OR-6 #506-CSI-113 as required by drawings and specifications.

B. Visits to the site by offerors shall be as specified in solicitation provision 52.236-27 Site Visit (Construction).

C. Offices of Walter Mechanical Services, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer.

D. Prior to commencing work, general Contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) shall maintain a presence at the work site at any time work is being performed.

E. Training:

1. All on-site workers of the prime and sub-Contractors shall have completed and received a certificate of completion of the 10-hour OSHA certified Construction Safety course or other equivalent competency training. The Construction Superintendent shall have completed and received certification of completing the 30-hour OSHA Construction Safety course.

2. Submit OSHA certifications for all on-site workers to the COR prior to any worker beginning on-site work.

1.3 STATEMENT OF BID ITEM(S)

A. The Statement of Bid Item(s) is located within the solicitation Information and Instructions to Bidder section.

B. ALL PRICING IS TO BE ENTERED IN BLOCK 17 OF THE SF1442 SOLICITATION

OFFER PAGE (BLOCK 17) OR THE BID SCHEDULE IF SO INCLUDED WITH THE

SOLICITATION.

01 00 00 - 2/16

VISN 10: 11-15

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security:

1. The General Contractor is responsible for assuring that all sub-Contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They shall also be subject to inspection of their personal effects when entering or leaving the project site.

2. No photography of VA premises is allowed without permission of the COR.

3. VA reserves the right to close down or shut down the project site and order General

Contractor’s employees off the premises in the event of a national emergency.

The General Contractor may return to the site only with the written approval of the Contracting Officer.

4. For working outside the “regular hours” as defined in the contract, the Contractor shall give 5 working days prior notice to the COR so that security and any necessary escort arrangements can be provided for the workers. This notice is separate from any notices required for utility shutdown described later in this section.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the

Contracting officers representative (COR) for any locked storage area, office or storage trailer, and any other locks installed by permission of the COR at the project site.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. The General Contractor is responsible for safekeeping of all drawings, project manuals and other project information. This information shall be shared only with those with a specific need to accomplish the project.

2. Should any documents, drawings, specifications, photographs, or other project documents are marked “Law Enforcement Sensitive” or “Sensitive Unclassified”, secure such information in separate containers and limit the access to only those who will need it for the project. Any such marked security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer. All shall be returned to the Contracting Officer upon project completion.

01 00 00 - 3/16

VISN 10: 11-15

a. Notify the Contracting Officer immediately when there is a loss or compromise of “sensitive information”.

b. AT THE PRE-CONSTRUCTION CONFERENCE ALL PROCEDURES

INVOLVING THE STORAGE, ENCRYPTION, SECURITY, VA

STANDARDS, ETC. OF SENSITIVE DOCUMENTS AS WELL AS THE

SAFEKEEPING OF ALL CONSTRUCTION DOCUMENTS NOT

CLASSIFIED AS SENSITIVE, WILL BE DISCUSSED IN DETAIL AND

APPROPRIATE DOCUMENTATION PROVIDED FOR CONTRACTOR’S

USE AND COMPLIANCE.

1.6 OPERATIONS AND STORAGE AREAS

A. Working space and space available for storing materials shall be as determined by the

COR.

B. Workmen are subject to the rules of the Medical Center applicable to their conduct.

C. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

D. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

E. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR.

F. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

01 00 00 - 4/16

VISN 10: 11-15

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

G. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the COR’s prior knowledge and written approval of the Contracting Officer. Refer to specification Division 26 ELECTRICAL, Division 27 COMMUNICATIONS, and Division 28 ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 calendar days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the

COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

H. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

I. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

01 00 00 - 5/16

VISN 10: 11-15

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

J. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article 1.15 USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Prior to the furnishing of any new items and any related work thereof, a mutual agreement between the Contractor and Contracting Officer on the total cost shall first be negotiated and a contract modification executed incorporating the changed work. Contractor is cautioned only the Contracting Officer has the authority to make changes to the contract related to this section. Any changed work performed or new items provided prior to Contracting Officer authorization shall result in no adjustment to the contract price.

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.

They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

01 00 00 - 6/16

VISN 10: 11-15

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.

When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the Department of Transportation (DOT) as outlined in Code of Federal Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic Substance Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform Hazardous Waste Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the COR.

a. Copies of the following listed CFR titles may be obtained from the

Government Printing Office:

40 CFR 261 Identification and Listing of Hazardous Waste 40 CFR 262 Standards Applicable to Generators of Hazardous Waste 40 CFR 263 Standards Applicable to Transporters of Hazardous Waste 40 CFR 761 PCB Manufacturing, Processing, Distribution in

Commerce, and use Prohibitions

01 00 00 - 7/16

VISN 10: 11-15

49 CFR 172 Hazardous Material tables and Hazardous Material Communications Regulations

49 CFR 173 Shippers - General Requirements for Shipments and Packaging

49 CRR 173 Subpart A General 49 CFR 173 Subpart B Preparation of Hazardous Material for

Transportation 49 CFR 173 Subpart J Other Regulated Material; Definitions and

Preparation TSCA Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

A. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

01 00 00 - 8/16

VISN 10: 11-15

1.11 PHYSICAL DATA – NOT USED

1.12 PROFESSIONAL SURVEYING SERVICES – NOT USED

1.13 LAYOUT OF WORK – NOT USED

1.14 AS-BUILT DRAWINGS

A. The Contractor shall maintain two full size sets of as-built drawings which shall be kept current during construction of the project, to include all contract changes, modifications and clarifications. In accordance with Contract Documents, Specifications and Drawings for Construction, Contractor is responsible to maintain and keep on site an as-built ‘red line’ set of drawings and specifications. These drawings and specifications shall contain up to date addendums, approved changes & modifications, approved Request for Information responses, and Architect’s Supplemental Instructions (ASI) for the project.

The COR shall have ready access to inspect the as-built drawings and specifications, as well as field copies in use, to ensure current drawings and specifications are being deployed for use on project.

B. All variations shall be shown in the same general detail as used in the contract drawings.

To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the Contracting Officer.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

Contractor is responsible to ensure all roads clean and free of debris, mud, spoils, etc.

that may have been left on road as the direct or indirect result of Contractor’s work.

1.16 RESERVED

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

01 00 00 - 9/16

VISN 10: 11-15

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR shall withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded.

The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces. Contractor is responsible to provide lock out-tag out of electrical, air, medical gases, water and steam work performed by Contractor.

All work shall be approved by COR in accordance with provision set forth herein.

3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government. Boilers, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel.

Boiler water must be given complete and continuous chemical treatment.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the Contractor at the Contractor’s expense.

1.18 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:

01 00 00 - 10/16

VISN 10: 11-15

1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a. Entrance jambs, heads soffits and threshold plates.

b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c. Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the Contractor’s expense.

4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the Contractor’s expense.

5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the Contractor’s expense, if recommended by elevator inspector after elevator is released by Contractor.

6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

1.19 TEMPORARY USE OF NEW ELEVATORS – NOT USED

1.20 TEMPORARY TOILETS

A. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by the COR. Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

01 00 00 - 11/16

VISN 10: 11-15

C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted.

Maintain minimum temperatures as specified for various materials.

1. Obtain heat by connecting to Medical Center heating distribution system.

a. Steam is available at no cost to Contractor.

D. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system.

The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

E. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system.

Provide reduced pressure backflow preventer at each connection as per code.

Water is available at no cost to the Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

1.22 RESERVED

1.23 TESTS

A. As per specification Section 23 05 93 TESTING, ADJUSTING AND BALANCEING FOR HVAC the Contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns.

The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The Contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, 01 00 00 - 12/16

VISN 10: 11-15

steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feed-water, condensate and other related components.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.24 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained.

All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. All training shall be videotaped by Contractor on HD medium and copy shall be furnished on DVD with each O&M manual. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of

01 00 00 - 13/16

VISN 10: 11-15

inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Contracting Officer reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the Contracting Officer, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.25 GOVERNMENT-FURNISHED PROPERTY

A. The Government shall deliver to the Contractor, the Government-furnished property shown on the drawings.

B. Equipment furnished by Government to be installed by Contractor will be furnished to Contractor at the Medical Center.

C. Storage space for equipment will be provided by the Government and the Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Medical Center.

D. Notify Contracting Officer in writing, 60 days in advance, of date on which Contractor will be prepared to receive equipment furnished by Government. Arrangements will then be made by the Government for delivery of equipment.

1. Immediately upon delivery of equipment, Contractor shall arrange for a joint inspection thereof with a representative of the Government. At such time the Contractor shall acknowledge receipt of equipment described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.

2. Contractor thereafter is responsible for such equipment until such time as acceptance of contract work is made by the Government.

E. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices, complete with all fittings, fastenings, and appliances necessary for connections to respective services installed under contract. All fittings and appliances (i.e., couplings, ells, tees, nipples, piping, conduits, cables, and the like) necessary to make the connection between the Government furnished equipment item and the utility stub-up shall be furnished and installed by the Contractor at no additional cost to the Government.

F. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.

G. Furnish supervision of installation of equipment at construction site by qualified factory trained technicians regularly employed by the equipment manufacturer.

01 00 00 - 14/16

VISN 10: 11-15

1.26 RELOCATED EQUIPMENT AND ITEMS

A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated by symbol "R" or otherwise shown to be relocated by the Contractor.

B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.

C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".

D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.

E. Contractor shall employ services of an installation engineer, who is an authorized representative of the manufacturer of this equipment to supervise assembly and installation of existing equipment, required to be relocated.

F. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.

1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT –

NOT USED

1.28 CONSTRUCTION SIGN – NOT USED

1.29 SAFETY SIGN – NOT USED

1.30 RESERVED

1.31 RESERVED

1.32 HISTORIC PRESERVATION

A. Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.

01 00 00 - 15/16

VISN 10: 11-15

1.33 RESERVED

1.34 INDUSTRY STANDARDS

A. Applicability of Standards: Except where the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with the standards in effect as of the date of the Contract Documents unless a specific date is indicated in the Contract Documents or the governing regulations cited herein.

C. Conflicting Requirements: Where compliance with two (2) or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent and highest quality requirement. In the event of conflicting requirements within the Contract Documents, comply with the most stringent and highest quality requirement. Request a decision from the COR before proceeding on requirements that are different but apparently equal, and where it is uncertain which requirement is the most stringent.

D. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum acceptable. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Request a clarification from the COR regarding uncertainties before proceeding.

E. Copies of Standards: Each entity engaged in construction on the Project is required to be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents. Where copies of standards are needed to perform a required construction activity, the Contractor shall obtain copies directly from the publication source.

F. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where such acronyms or abbreviations are used in the Specifications or other Contract Documents, they mean the recognized name of the trade association, standards-generating organization, authorities having jurisdiction, or other entity applicable to the context of the text provision. Refer to Thompson Gale's "Encyclopedia of Associations," available in most libraries.

1.35 GOVERNING REGULATIONS AND AUTHORITIES

A. Copies of Regulations: Obtain copies of the following regulations and retain at the Project Site to be available for reference by parties who have a reasonable need during submittals, planning, and progress of the work, until final completion.

01 00 00 - 16/16

VISN 10: 11-15

1. International Building Code – 2018 edition.

2. International Existing Building Code – 2018 edition.

3. International Mechanical Code – 2018 edition.

4. International Plumbing Code – 2018 edition.

5. International Energy Conservation Code – 2018 edition.

6. International Fire Code – 2018 edition.

7. National Electric Code / NFPA 70 Code – 2020 edition.

8. Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier Free Design Guide (PG-18-13)

9. NFPA 101 – 2018 edition.

10. OSHA 29 CFR Part 1910 Occupational Safety and Health Regulations/2010.

11. OSHA 29 CFR Part 1926 Occupational Safety and Health Regulations for

Construction/2010.

PART 2 - PRODUCTS – NOT APPLICABLE

PART 3 - EXECUTION – NOT APPLICABLE

END OF SECTION 01 00 00

01 32 16.15 - 1/8

PROJECT SCHEDULES (SMALL PROJECTS – DESIGN/BID/BUILD)

VA Master Specifications 02-15

SECTION 01 32 16.15 - PROJECT SCHEDULES (SMALL PROJECTS – DESIGN/BID/BUILD)

PART 1 - GENERAL

1.1 DESCRIPTION

A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements (Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.

1.2 CONTRACTOR'S REPRESENTATIVE

A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COR).

B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.

C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.

1.3 CONTRACTOR'S CONSULTANT

A. The Contractor shall submit a qualification proposal to the COR, within 10 days of bid acceptance. The qualification proposal shall include:

1. The name and address of the proposed consultant.

2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.

3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.

B. The Contracting Officer has the right to approve or disapprove the proposed consultant, and will notify the Contractor of the VA decision within seven calendar days from receipt of the qualification proposal. In case of disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration. The Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.

01 32 16.15 - 2/8

VA Master Specifications 02-15

1.4 COMPUTER PRODUCED SCHEDULES

A. The contractor shall provide monthly, to the Department of Veterans Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COR shall identify the five different report formats that the contractor shall provide.

B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.

C. The VA will report errors in computer-produced reports to the Contractor’s representative within ten calendar days from receipt of…