Amendment__0011.pdf
PDF 2 MB Posted
- Attached to
- Shipboard Multipurpose Copier Program Federal contract opportunity
- Solicitation number
- SP700013R1026
- Issued by
- Defense Logistics Agency
About this file
Change in PWS Specifications and solicitation extension to May 31 2013 4 00pm EST
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment__0013.pdf | ||
| Amendment__0012.pdf | ||
| Amendment__10.pdf | ||
| Amendment__09.pdf | ||
| Amendment__08.pdf | ||
| Amendment__07.pdf | ||
| Amendment__06.pdf | ||
| Amendment__05.pdf | ||
| Amendment__04.pdf | ||
| Amendment__03.pdf | ||
| Amendment__02.pdf | ||
| Amendment__01.pdf | ||
| SMCP_Solicitation_SP7000-13-R-1026_Revision.pdf | ||
| SMCP_Solicitation_SP7000-13-R-1026.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
APS1596
Cross-Out
This amendment is to:
- Incorporate changes to Color and Black & White Production Equipment requirements.
Summary of Changes
Color Production Equipment change (See Page 3 of 4 of this amendment for revised specification):
Item 2: Print Engine Color impressions changed from 200,000 impressions to 180,000 impressions.
Paper weight changed from 16 to 110 lbs. to 18 to 110lbs.
Item 3: Scanner/Document Handler Throughput weights changed from 16 to 110 lbs. to 18 to 110lbs.
Black & White Production Equipment change (See Page 4 of 4 of this amendment for revised specification):
Item 2: Print Engine Minimum pages per month changed from 300,000 impressions to 180,000 impressions.
Paper weight changed from 16 to 140 lbs. to 18 to 110lbs.
Item 3: Scanner/Document Handler Throughput weights changed from 16 to 110 lbs. to 18 to 110lbs.
********************************************** END OF CHANGES******************************************
NAME OF OFFEROR OR CONTRACTOR:
Item NO. QUANTITY UNIT UNIT PRICE AMOUNT
SUPPLIES/SERVICES
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED:
SP700013R1026-0011
APS1596
Typewritten Text
1. Ensure that supporting documents are accurately verifying that you comply with the PWS. For example: If you state devices are WIN 7 capable, the tech sheet verifies this.
APS1596
Typewritten Text
2. Ensure "Instruction to Offerors" are properly addressed and submitted
APS1596
Typewritten Text
APS1596
Typewritten Text
APS1596
Typewritten Text
3. Each Factor and Sub-Factor MUST be answered either individually or as a whole.
APS1596
Typewritten Text
4. If you have already submitted a proposal you must resubmit your entire package.
APS1596
Typewritten Text
5. Solicitation is hereby extended to May 31, 2013 4:00pm EST.
SPECIFIC MINIMUM COLOR PRODUCTION REQUIREMENTS FOR PRINT SHOP PERFORMANCE
Please refer to the Spec changes made in RED.
COLOR PRODUCTION PRINTER-Note: objective is to maintain or exceed industry standard
1. Digital laser full color copier with Print Server/Digital Front End capable of simultaneous work flow.
Networkable Server/Digital Front End able to receive and send files/data from multiple sources simultaneously.
2. Print Engine Minimum 25,000 impressions per month B&W and 180,000 impressions per month Color (production rated) Minimum 50 full color ppm (8.5” x 11”) Must be capable to print sizes up to of 12” x 18” with ability to produce 11” x 17” full bleed Minimum Printing resolution of 1200 x 1200 dpi 256 Color – continuous tone Paper weights from 18 to 110 lbs. paper stock (glossy and matte finish) PDLs and Data Formats: Adobe PostScript Level 3, PDF, TIFF
3. Scanner/Document Handler Minimum of 50 ipm color simplex and duplex scanning Minimum scanning resolution up to 600 x 600 dpi Scan formats: TIFF, multi-page TIFF, and PDF Throughput weights from 18 to 110 lbs.
Throughput sizes from 5” x 8” to 11” x 17” 100 sheet capacity Automatic document feeder Anti-counterfeit device Reduction and enlargement from 25% to 400% Automatic color exposure Accepts originals up to 11” x 17” Paper Handling: No Less Than, 5,000 sheet capacity
4. Data Security:
Secure Print /Image overwrite up to 3 times (minimum)
5. Electrical Requirements:
20A, 110-120 VAC
6. Finishing Capabilities Collating Minimum 50 sheet stapling Hole punching, Booklet making, Bi-Folding
7. Delivery Dimension Capability of disassembly to a maximum dimension of 26” hatch access for shipboard use.
8. Maximum dimension of Working Environment The maximum available work space is 112" Width x 72" Depth x 60" Height. When assembled, the installed device must have sufficient space around the device for performing operator and maintenance duties.
SUPPLIES/SERVICES
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED:
SP700013R1026-0011
SPECIFIC MINIMUM B&W PRODUCTION REQUIREMENT FOR PRINT SHOP PERFORMANCE
Please refer to the Spec changes made in RED.
BLACK AND WHITE PRODUCTION PRINTER NOTE: Objective is to maintain or exceed industry standard
1. Digital laser black and white copier with Print Server/Digital Front End capable of simultaneous work flow.
Networkable
Server/Digital Front End able to receive and send files/data from multiple sources simultaneously.
2. Print Engine
Minimum 180,000 pages per month (production rated)
Minimum 110 ppm (8.5” x 11”)
Must be capable to print sizes up to of 12” x 18” with ability to produce 11” x 17” full bleed
Minimum Printing resolution of 1200 x 1200 dpi
Paper weights from 18 to 110 lbs. paper stock
Multiple media types with a minimum capability to print on bond. cover, index, recycled, tabs and pre-printed forms
PDLs and Data Formats: Adobe PostScript Level 3, PDF, TIFF
3. Scanner/Document Handler
Minimum of 80 ipm B & W simplex and duplex scanning
Minimum Scanning resolution up to 600 x 600 dpi / 8 bit gray (256 shades)
Scan formats: TIFF, multi-page TIFF, and PDF
Throughput weights from 18 to 110 lbs.
Throughput sizes 5” x 8” to 11” x 17”
100 Sheet Automatic document feeder
Anti-counterfeit device
Paper Handling: No Less Than, 7,000 sheet capacity
4. Electrical Requirements:
220VAC
5. Finishing Capabilities
Collating
Minimum 100 sheet stapling
Hole punching
Booklet making
Bi-Folding
Post process inserter
6. Delivery Dimensions:
Capability of disassembly to a maximum dimension of 26” hatch access for shipboard use.
7. Maximum dimension:
The maximum available work space is 140" Width x 80" Depth x 60" Height. When assembled, the installed device must have sufficient space around the device for performing operator and maintenance duties.
SUPPLIES/SERVICES
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED:
SP700013R1026-0011
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE 17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
RFQ IFB RFP
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF.
DATED . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 3/2005)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITON IS
UNRESTRICTED OR
NAICS:
SIZE STANDARD:
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
OFFER
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS
EMERGING SMALL
BUSINESS
8(A)
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
APS0899
Typewritten Text
APS0899
STANDARD FORM 1449 (REV. 3/2005) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
APS1596
Typewritten Text
SP7000-13-R-1026
APS1596
Typewritten Text
APS1596
SP7000-13-R-1026 Page 3 of 48
Shipboard Multipurpose Copier Program
SECTION B: SUPPLIES AND SERVICES
Estimated POP: 01 OCT 13 - 30 SEP 18
CLIN Volume Band Estimated
Units for Evaluation Purposes
Unit Unit Price Total Cost
1 Class 1 Copier/Printer/Fax 730 Each 2 Class 1 - Installation Charge - CONUS 700 Each 3 Class 1 - Installation Charge - OCONUS 30 Each 4 Class 1 - Vibration Mount - Surface Vessels 700 Each 5 Class 1 - Low Profile Hard Mount- Submarine 30 Each 6 Class I - Removal and Disposal Charge 730 Each 7 Class 1 - Prev. Maintenance CONUS - per machine 30 Each 8 Class 1 - Prev. Maintenance OCONUS - per machine 2 Each 9 Class 1 - Toner Kits - 3 month ship pack
Calculate Total Cost for 15,000 Impressions of print 850 Each
10 Class 1 - Toner Kits - 6 month ship pack Calculate Total Cost for 30,000 Impressions of print
330 Each
11 Class 1 - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
50 Each
12 Class 1 - Repair Parts Kits (for 2 copiers) List by Item Name, QTY
25 Each
13 Class 1 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
120 Each
14 Class 1 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
30 Each
15 Class 1 - Additional Unique Tool Kits 10 Each 16 Class 1 - Additional Technical Manuals - Class I 8 Each 17 Class 1 - Contractor's Facility - CONUS-Per Trainee 585 Each 18 Class 1 - Government's Facility - OCONUS-Per Trainee 6 Each 19 Class 1 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
20 Class 1 - Full Services Maintenance. Agreement Per Month 1 Month 21 Class 1C Copier/Printer 62 Each 22 Class 1C - Installation Charge - CONUS 54 Each 23 Class 1C- Installation Charge - OCONUS 8 Each 24 Class 1C - Vibration Mount - Surface Vessels 60 Each 25 Class 1C - Low Profile Hard Mount - Submarine 2 Each 26 Class 1C - Removal and Disposal Charge 62 Each 27 Class 1C - Prev. Maintenance CONUS - per machine 20 Each 28 Class 1C- Prev. Maintenance OCONUS - per machine 2 Each 29 Class 1C- Toner Color Kits- 3 month ship pack
Calculate Total Cost for 15,000 Impressions BW/3,000 Impressions Color 65 Each
30 Class 1C - Toner Color Kits- 6 month ship pack Calculate Total Cost for 30,000 Impressions BW/6,000 Impressions Color
144 Each
31 Class 1C - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
3 Each
32 Class 1C - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
9 Each
33 Class 1C - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
5 Each
34 Class 1C- Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
2 Each
35 Class 1C - Additional Unique Tool Kits 2 Each 36 Class 1C- Additional Technical Manuals 1 Each
SP7000-13-R-1026 Page 4 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
37 Class 1C- Contractor's Facility - CONUS Training 13 Each 38 Class 1C - Government's Facility - OCONUS Training 1 Each 39 Class 1C - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
40 Class 1C - Full Services Maintenance. Agreement Per Month 1 Month 41 Class 2 - Copier/Printer 152 Each 42 Class 2 - Installation Charge - CONUS 152 Each 43 Class 2 - Installation Charge - OCONUS 1 Each 44 Class 2 - Vibration Mount - Surface Vessels 152 Each 45 Class 2 - Removal and Disposal Charge 152 Each 46 Class 2 - Prev. Maintenance CONUS - per machine 12 Each 47 Class 2 - Prev. Maintenance OCONUS - per machine 1 Each 48 Class 2 - Toner Kits - 3 month ship pack
Calculate Total Cost for 60,000 Impressions BW 182 Each
49 Class 2 - Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions BW
188 Each
50 Class 2 - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
11 Each
51 Class 2 - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
13 Each
52 Class 2 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
4 Each
53 Class 2 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
1 Each
54 Class 2 - Additional Unique Tool Kits 9 Each 55 Class 2 - Additional Technical Manuals 1 Each 56 Class 2 - Contractor's Facility - CONUS Training 51 Each 57 Class 2 - Government's Facility - OCONUS Training 1 Each 58 Class 2 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
59 Class 2 - Full Services Maintenance. Agreement Per Month 1 Month 60 Class 3 Copier/Printer 706 Each 61 Class 3 - Installation Charge - CONUS 706 Each 62 Class 3 - Installation Charge - OCONUS 1 Each 63 Class 3 - Vibration Mount - Surface Vessels 706 Each 64 Class 3 - Removal and Disposal Charge 706 Each 65 Class 3 - Prev. Maintenance CONUS - per machine 19 Each 66 Class 3 - Prev. Maintenance OCONUS - per machine 1 Each 67 Class 3 - Toner Kits - 3 month ship pack
Calculate Total Cost for 120,000 Impressions BW 418 Each
68 Class 3 - Toner Kits - 6 month ship pack Calculate Total Cost for 240,000 Impressions BW
253 Each
69 Class 3 - Staples - 3 month ship pack 90 Each 70 Class 3 - Staples - 6 month ship pack 67 Each 71 Class 3 - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 11 Each
72 Class 3 - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
34 Each
SP7000-13-R-1026 Page 5 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
73 Class 3 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
106 Each
74 Class 3 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
7 Each
75 Class 3 - Additional Unique Tool Kits 5 Each 76 Class 3 - Additional Technical Manuals - Class I 1 Each 77 Class 3 - Contractor's Facility - CONUS Training 248 Each 78 Class 3 - Government's Facility - OCONUS Training 1 Each 79 Class 3 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
80 Class 3 - Full Services Maintenance. Agreement Per Month 1 Month 81 Class 3C - Color Copier/Printer 279 Each 82 Class 3C - Installation Charge - CONUS 279 Each 83 Class 3C - Installation Charge - OCONUS 1 Each 84 Class 3C - Vibration Mount - Surface Vessels 279 Each 85 Class 3C - Removal and Disposal Charge 279 Each 86 Class 3C - Prev. Maintenance CONUS - per machine 1 Each 87 Class 3C - Prev. Maintenance OCONUS - per machine 3 Each 88 Class 3C - Black Toner Kits - 3 month ship pack
Calculate Total Cost for 120,000 Impressions BW 492 Each
89 Class 3C - Black Toner Kits - 6 month ship pack Calculate Total Cost for 240,000 Impressions BW
20 Each
90 Class 3C - Cyan Toner Kits - 3 month ship pack Calculate Total Cost for 60,000 Impressions Color
206 Each
91 Class 3C - Cyan Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions Color
50 Each
92 Class 3C - Magenta Toner Kits - 3 month ship pack Calculate Total Cost for 60,000 Impressions Color
200 Each
93 Class 3C - Magenta Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions Color
46 Each
94 Class 3C - Yellow Toner Kits - 3 month ship pack Calculate Total Cost for 60,000 Impressions Color
203 Each
95 Class 3C - Yellow Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions Color
48 Each
96 Class 3C - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
11 Each
97 Class 3C - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
72 Each
98 Class 3C - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
3 Each
99 Class 3C - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
1 Each
100 Class 3C - Additional Unique Tool Kits 2 Each 101 Class 3C - Additional Technical Manuals - Class IV 1 Each 102 Class 3C - Contractor's Facility - CONUS-Per Trainee 101 Each 103 Class 3C - Government's Facility - OCONUS-Per Trainee 1 Each 104 Class 3C - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
SP7000-13-R-1026 Page 6 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
105 Class 3C - Full Services Maintenance. Agreement Per Month 1 Month 106 Class 4 - Copier/Printer 155 Each 107 Class 4 - Installation Charge - CONUS 154 Each 108 Class 4 - Installation Charge - OCONUS 1 Each 109 Class 4 - Vibration Mount - Surface Vessels 155 Each 110 Class 4 - Removal and Disposal Charge 155 Each 111 Class 4 - Prev. Maintenance CONUS - per machine 1 Each 112 Class 4 - Prev. Maintenance OCONUS - per machine 1 Each 113 Class 4 - Toner Kits - 3 month ship pack
Calculate Total Cost for 270,000 Impressions Color 122 Each
114 Class 4 - Toner Kits - 6 month ship pack Calculate Total Cost for 540,000 Impressions Color
45 Each
115 Class 4 - Staples - 3 month ship pack 86 Each 116 Class 4 - Staples - 6 month ship pack 16 Each 117 Class 4 - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 8 Each
118 Class 4 - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
27 Each
119 Class 4 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
13 Each
120 Class 4 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
3 Each
121 Class 4 - Additional Unique Tool Kits 3 Each 122 Class 4 - Additional Technical Manuals - Class 4 1 Each 123 Class 4 - Contractor's Facility - CONUS-Per Trainee 56 Each 124 Class 4 - Government's Facility - OCONUS-Per Trainee 1 Each 125 Class 4 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
126 Class 4 - Full Services Maintenance. Agreement Per Month 1 Month 127 Class Production Color (PC) Copier/Printer 72 Each 128 Class PC - Installation Charge - CONUS 71 Each 129 Class PC - Installation Charge - OCONUS 1 Each 130 Class PC - Vibration Mount - Surface Vessels 72 Each 131 Class PC - Removal and Disposal Charge 72 Each 132 Class PC - Preventative Maintenance. CONUS - per machine 1 Each 133 Class PC - Preventative Maintenance. OCONUS - per machine 1 Each 134 Class PC - Toner Kits, Black - 3 month ship pack
Calculate Total Cost for 75,000 Impressions Color 16 Each
135 Class PC - Toner Kits, Black - 6 month ship pack Calculate Total Cost for 150,000 Impressions Color
4 Each
136 Class PC - Toner Kits, Cyan - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color
12 Each
137 Class PC - Toner Kits, Cyan - 6 month ship pack Calculate Total Cost for 1,200,000 Impressions Color
4 Each
138 Class PC - Toner Kits, Magenta - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color
11 Each
139 Class PC - Toner Kits, Magenta - 6 month ship pack Calculate Total Cost for 1,200,000 Impressions Color
4 Each
140 Class PC - Toner Kits, Yellow - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color
11 Each
SP7000-13-R-1026 Page 7 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
141 Class PC - Toner Kits, Yellow - 3 month ship pack Calculate Total Cost for 1,200,000 Impressions Color
4 Each
142 Class PC - Toner Waste Bottle - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color and 75,000 B&W
9 Each
143 Class PC - Toner Waste Bottle - 6 month ship pack Calculate Total Cost for 1,200,000 Impressions Color and 150,000 B&W
4 Each
144 Class PC - Staples - 3 month ship pack 8 Each 145 Class PC - Staples - 6 month ship pack 7 Each 146 Class PC - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 3 Each
147 Class PC - Repair Parts Kits (for 3 copier) Provide Parts List and Quantity/Kit
5 Each
148 Class PC - Additional Unique Tool Kits 1 Each 149 Class PC - Additional Technical Manuals - Print Shop CPC 1 Each 150 Class PC - Contractor's Facility - CONUS-Per Trainee 21 Each 151 Class PC - Government's Facility - OCONUS-Per Trainee 2 Each 152 Class PC -Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
153 Class PC - Full Services Maintenance. Agreement Per Month 1 Month 154 Class Production B/W (PWB) Copier/Printer 30 Each 155 Class PBW - Installation Charge - CONUS 29 Each 156 Class PBW - Installation Charge - OCONUS 1 Each 157 Class PBW - Vibration Mount - Surface Vessels 30 Each 158 Class PBW - Removal and Disposal Charge 30 Each 159 Class PBW - Preventative Maintenance. CONUS - per machine 1 Each 160 Class PBW - Preventative Maintenance. OCONUS - per machine 1 Each 161 Class PBW - Toner Kits, Black - 3 month ship pack
Calculate Total Cost for 900,000 impressions 52 Each
162 Class PBW - Toner Kits, Black - 6 month ship pack Calculate Total Cost for 1,800,000 impressions
12 Each
163 Class PBW - Toner Waste Bottle - 3 month ship pack Calculate Total Cost for 900,000 impressions
44 Each
164 Class PBW - Toner Waste Bottle - 6 month ship pack Calculate Total Cost for 1,800,000 impressions
5 Each
165 Class PBW - Staples - 3 month ship pack 45 Each 166 Class PBW - Staples - 6 month ship pack 16 Each 167 Class PBW - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 3 Each
168 Class PBW - Repair Parts Kits (for 2 copier) Provide Parts List and Quantity/Kit
4 Each
169 Class PBW - Additional Unique Tool Kits 1 Each 170 Class PBW - Additional Technical Manuals - Print Shop BW 1 Each 171 Class PBW - Contractor's Facility - CONUS-Per Trainee 20 Each 172 Class PBW - Government's Facility - OCONUS-Per Trainee 1 Each 173 Class PBW - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
174 Class PBW - Full Services Maintenance. Agreement Per Month 1 Month 175 Service Call - CONUS - Regular (up to 1 Hr.) 2134 Each 176 Service Call - CONUS - After Hours (up to 1 Hr.) 22 Each
SP7000-13-R-1026 Page 8 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
177 Service Call - CONUS -Weekends & Holidays (up to 1 Hr.) 20 Each 178 Service Call - OCONUS - Regular (up to 1 Hr.) 592 Each 179 Service Call - OCONUS - After Hours (up to 1 Hr.) 28 Each 180 Service Call - OCONUS -Weekends & Holidays (up to 1 Hr.) 20 Each 181 West Coast Rider Monthly Services for Carriers/Amphibs 159 Month 182 East Coast Rider Monthly Services for Carriers/Amphibs 366 Month
OPTION: 5 YEAR MAINTENANCE, SUPPORT, AND SUPPLIES
ESTIMATED POP: 01 OCT 2018 - 30 SEP 2023
183 Class I - Removal and Disposal Charge 730 Each 184 Class 1 - Prev. Maintenance CONUS - per machine 30 Each 185 Class 1 - Prev. Maintenance OCONUS - per machine 2 Each 186 Class 1 - Toner Kits - 3 month ship pack
Calculate Total Cost for 15,000 Impressions of print 850 Each
187 Class 1 - Toner Kits - 6 month ship pack Calculate Total Cost for 30,000 Impressions of print
330 Each
188 Class 1 - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
50 Each
189 Class 1 - Repair Parts Kits (for 2 copiers) List by Item Name and Quantity/Kit
25 Each
190 Class 1 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
120 Each
191 Class 1 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
30 Each
192 Class 1 - Additional Unique Tool Kits 10 Each 193 Class 1 - Additional Technical Manuals - Class I 8 Each 194 Class 1 - Contractor's Facility - CONUS-Per Trainee 585 Each 195 Class 1 - Government's Facility - OCONUS-Per Trainee 6 Each 196 Class 1 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
197 Class 1 - Full Services Maintenance. Agreement Per Month 1 Month 198 Class 1C - Removal and Disposal Charge 62 Each 199 Class 1C - Prev. Maintenance CONUS - per machine 20 Each 200 Class 1C- Prev. Maintenance OCONUS - per machine 2 Each 201 Class 1C- Toner Color Kits- 3 month ship pack
Calculate Total Cost for 15,000 Impressions BW/3,000 Impressions Color 65 Each
202 Class 1C - Toner Color Kits- 6 month ship pack Calculate Total Cost for 30,000 Impressions BW/6,000 Impressions Color
144 Each
203 Class 1C - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
3 Each
204 Class 1C - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
9 Each
205 Class 1C - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
5 Each
206 Class 1C- Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
2 Each
207 Class 1C - Additional Unique Tool Kits 2 Each 208 Class 1C- Additional Technical Manuals 1 Each 209 Class 1C- Contractor's Facility - CONUS Training 13 Each 210 Class 1C - Government's Facility - OCONUS Training 1 Each
SP7000-13-R-1026 Page 9 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
211 Class 1C - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
212 Class 1C - Full Services Maintenance. Agreement Per Month 1 Month 213 Class 2 - Removal and Disposal Charge 152 Each 214 Class 2 - Prev. Maintenance CONUS - per machine 12 Each 215 Class 2 - Prev. Maintenance OCONUS - per machine 1 Each 216 Class 2 - Toner Kits- 3 month ship pack
Calculate Total Cost for 60,000 Impressions BW 182 Each
217 Class 2 - Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions BW
188 Each
218 Class 2 - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
11 Each
219 Class 2 - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
13 Each
220 Class 2 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
4 Each
221 Class 2 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
1 Each
222 Class 2 - Additional Unique Tool Kits 9 Each 223 Class 2 - Additional Technical Manuals 1 Each 224 Class 2 - Contractor's Facility - CONUS Training 51 Each 225 Class 2 - Government's Facility - OCONUS Training 1 Each 226 Class 2 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
227 Class 2 - Full Services Maintenance. Agreement Per Month 1 Month 228 Class 3 - Removal and Disposal Charge 706 Each 229 Class 3 - Prev. Maintenance CONUS - per machine 19 Each 230 Class 3 - Prev. Maintenance OCONUS - per machine 1 Each 231 Class 3 - Toner Kits - 3 month ship pack
Calculate Total Cost for 120,000 Impressions BW 418 Each
232 Class 3 - Toner Kits - 6 month ship pack Calculate Total Cost for 240,000 Impressions BW
253 Each
233 Class 3 - Staples - 3 month ship pack 90 Each 234 Class 3 - Staples - 6 month ship pack 67 Each 235 Class 3 - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 11 Each
236 Class 3 - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
34 Each
237 Class 3 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
106 Each
238 Class 3 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
7 Each
239 Class 3 - Additional Unique Tool Kits 5 Each 240 Class 3 - Additional Technical Manuals - Class I 1 Each 241 Class 3 - Contractor's Facility - CONUS Training 248 Each 242 Class 3 - Government's Facility - OCONUS Training 1 Each
SP7000-13-R-1026 Page 10 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
243 Class 3 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
244 Class 3 - Full Services Maintenance. Agreement Per Month 1 Month 245 Class 3C - Removal and Disposal Charge 279 Each 246 Class 3C - Prev. Maintenance CONUS - per machine 1 Each 247 Class 3C - Prev. Maintenance OCONUS - per machine 3 Each 248 Class 3C - Black Toner Kits - 3 month ship pack
Calculate Total Cost for 120,000 Impressions B&W 492 Each
249 Class 3C - Black Toner Kits - 6 month ship pack Calculate Total Cost for 240,000 Impressions B&W
20 Each
250 Class 3C - Cyan Toner Kits - 3 month ship pack Calculate Total Cost for 60,000 Impressions Color
206 Each
251 Class 3C - Cyan Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions Color
50 Each
252 Class 3C - Magenta Toner Kits - 3 month ship pack Calculate Total Cost for 60,000 Impressions Color
200 Each
253 Class 3C - Magenta Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions Color
46 Each
254 Class 3C - Yellow Toner Kits - 3 month ship pack Calculate Total Cost for 60,000 Impressions Color
203 Each
255 Class 3C - Yellow Toner Kits - 6 month ship pack Calculate Total Cost for 120,000 Impressions Color
48 Each
256 Class 3C - Repair Parts Kits (for 1 copier) Provide Parts List and Quantity/Kit
11 Each
257 Class 3C - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
72 Each
258 Class 3C - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
3 Each
259 Class 3C - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
1 Each
260 Class 3C - Additional Unique Tool Kits 2 Each 261 Class 3C - Additional Technical Manuals - Class IV 1 Each 262 Class 3C - Contractor's Facility - CONUS-Per Trainee 101 Each 263 Class 3C - Government's Facility - OCONUS-Per Trainee 1 Each 264 Class 3C - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
265 Class 3C - Full Services Maintenance. Agreement Per Month 1 Month 266 Class 4 - Removal and Disposal Charge 155 Each 267 Class 4 - Prev. Maintenance CONUS - per machine 1 Each 268 Class 4 - Prev. Maintenance OCONUS - per machine 1 Each 269 Class 4 - Toner Kits - 3 month ship pack
Calculate Total Cost for 270,000 Impressions 122 Each
270 Class 4 - Toner Kits - 6 month ship pack Calculate Total Cost for 540,000 Impressions
45 Each
271 Class 4 - Staples - 3 month ship pack 86 Each 272 Class 4 - Staples - 6 month ship pack 16 Each 273 Class 4 - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 8 Each
SP7000-13-R-1026 Page 11 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
274 Class 4 - Repair Parts Kits (for 2 copiers) Provide Parts List and Quantity/Kit
27 Each
275 Class 4 - Repair Parts Kits (for 5 copiers) Provide Parts List and Quantity/Kit
13 Each
276 Class 4 - Repair Parts Kits (for 10 copiers) Provide Parts List and Quantity/Kit
3 Each
277 Class 4 - Additional Unique Tool Kits 3 Each 278 Class 4 - Additional Technical Manuals - Class 4 1 Each 279 Class 4 - Contractor's Facility - CONUS-Per Trainee 56 Each 280 Class 4 - Government's Facility - OCONUS-Per Trainee 1 Each 281 Class 4 - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
282 Class 4 - Full Services Maintenance. Agreement Per Month 1 Month 283 Class PC - Removal and Disposal Charge 72 Each 284 Class PC - Preventative Maintenance. CONUS - per machine 1 Each 285 Class PC - Preventative Maintenance. OCONUS - per machine 1 Each 286 Class PC - Toner Kits, Black - 3 month ship pack
Calculate Total Cost for 75,000 Impressions B&W 16 Each
287 Class PC - Toner Kits, Black - 6 month ship pack Calculate Total Cost for 150,000 Impressions B&W
4 Each
288 Class PC - Toner Kits, Cyan - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color
12 Each
289 Class PC - Toner Kits, Cyan - 6 month ship pack Calculate Total Cost for 1,200,000 Impressions Color
4 Each
290 Class PC - Toner Kits, Magenta - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color
11 Each
291 Class PC - Toner Kits, Magenta - 6 month ship pack Calculate Total Cost for 1,200,000 Impressions Color
4 Each
292 Class PC - Toner Kits, Yellow - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color
11 Each
293 Class PC - Toner Kits, Yellow - 6 month ship pack Calculate Total Cost for 1,200,000 Impressions Color
4 Each
294 Class PC - Toner Waste Bottle - 3 month ship pack Calculate Total Cost for 600,000 Impressions Color and 75,000 B&W
9 Each
295 Class PC - Toner Waste Bottle - 6 month ship pack Calculate Total Cost for 600,000 Impressions Color and 150,000 B&W
4 Each
296 Class PC - Staples - 3 month ship pack 8 Each 297 Class PC - Staples - 6 month ship pack 7 Each 298 Class PC - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 3 Each
299 Class PC - Repair Parts Kits (for 3 copier) Provide Parts List and Quantity/Kit
5 Each
300 Class PC - Additional Unique Tool Kits 1 Each 301 Class PC - Additional Technical Manuals - Print Shop CPC 1 Each 302 Class PC - Contractor's Facility - CONUS-Per Trainee 21 Each 303 Class PC - Government's Facility - OCONUS-Per Trainee 2 Each 304 Class PC -Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
305 Class PC - Full Services Maintenance. Agreement Per Month 1 Month
SP7000-13-R-1026 Page 12 of 48
CLIN Volume Band Estimated Units for Evaluation Purposes
Unit Unit Price Total Cost
306 Class PBW - Removal and Disposal Charge 30 Each 307 Class PBW - Preventative Maintenance. CONUS - per machine 1 Each 308 Class PBW - Preventative Maintenance. OCONUS - per machine 1 Each 309 Class PBW - Toner Kits, Black - 3 month ship pack
Calculate Total Cost for 900,000 impressions 52 Each
310 Class PBW - Toner Kits, Black - 6 month ship pack Calculate Total Cost for 1,800,000 impressions
12 Each
311 Class PBW - Toner Waste Bottle - 3 month ship pack Calculate Total Cost for 900,000 impressions
44 Each
312 Class PBW - Toner Waste Bottle - 6 month ship pack Calculate Total Cost for 1,800,000 impressions
5 Each
313 Class PBW - Staples - 3 month ship pack 45 Each 314 Class PBW - Staples - 6 month ship pack 16 Each 315 Class PBW - Repair Parts Kits (for 1 copier)
Provide Parts List and Quantity/Kit 3 Each
316 Class PBW - Repair Parts Kits (for 2 copier) Provide Parts List and Quantity/Kit
4 Each
317 Class PBW - Additional Unique Tool Kits 1 Each 318 Class PBW - Additional Technical Manuals - Print Shop BW 1 Each 319 Class PBW - Contractor's Facility - CONUS-Per Trainee 20 Each 320 Class PBW - Government's Facility - OCONUS-Per Trainee 1 Each 321 Class PBW - Individual Parts Will NOT be evaluated.
Provide Parts List with prices for all non wearable items. Provide a parts list with prices for all wearable parts and their yield or expected lifecycle. Pricing will not exceed Manufactured Retail Price.
N/A N/A N/A N/A
322 Class PBW - Full Services Maintenance. Agreement Per Month 1 Month 323 Service Call - CONUS - Regular (up to 1 Hr.) 2134 Each 324 Service Call - CONUS - After Hours (up to 1 Hr.) 22 Each 325 Service Call - CONUS -Weekends & Holidays (up to 1 Hr.) 20 Each 326 Service Call - OCONUS - Regular (up to 1 Hr.) 592 Each 327 Service Call - OCONUS - After Hours (up to 1 Hr.) 28 Each 328 Service Call - OCONUS -Weekends & Holidays (up to 1 Hr.) 20 Each 329 West Coast Rider Monthly Services for Carriers/Amphibs 159 Month 330 East Coast Rider Monthly Services for Carriers/Amphibs 366 Month
TOTAL:
SP7000-13-R-1026 Page 13 of 48
SECTION C: CONTRACT CLAUSES
FAR CLAUSES BY REFERENCE
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Oct 2010) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (May 2011) 52.204-7 Central Contractor Registrations (Dec 2012) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Dec 2010) 52.237-3 Continuity of Services (Jan 1991) 52.246-2 Inspection of Supplies -- Fixed-Price (Aug. 1996) 52.246-25 Limitation of Liability--Services (Feb 1997) 52.247-34 F.o.b. – Destination (Nov 1991)
FAR CLAUSES BY FULL TEXT
52.204-2 -- Security Requirements (Aug. 1996)
(a) This clause applies to the extent that this contract involves access to information classified “Confidential,” “Secret,” or “Top Secret.”
(b) The Contractor shall comply with --
(1) The Security Agreement (DD Form 441), including the National Industrial Security Program Operating Manual (DoD 5220.22-M); and
(2) Any revisions to that manual, notice of which has been furnished to the Contractor.
(c) If, subsequent to the date of this contract, the security classification or security requirements under this contract are changed by the Government and if the changes cause an increase or decrease in security costs or otherwise affect any other term or condition of this contract, the contract shall be subject to an equitable adjustment as if the changes were directed under the Changes clause of this contract.
(d) The Contractor agrees to insert terms that conform substantially to the language of this clause, including this paragraph (d) but excluding any reference to the Changes clause of this contract, in all subcontracts under this contract that involve access to classified information.
52.204-9 -- Personal Identity Verification of Contractor Personnel (Jan 2011)
(a) The Contractor shall comply with agency personal identity verification procedures identified in the contract that implement Homeland Security Presidential Directive-12 (HSPD-12), Office of Management and Budget (OMB) guidance M-05-24, and Federal Information Processing Standards Publication (FIPS PUB) Number 201.
(b) The Contractor shall account for all forms of Government-provided identification issued to the Contractor employees in connection with performance under this contract. The Contractor shall return such identification to the issuing agency at the earliest of any of the following, unless otherwise determined by the Government;
(1) When no longer needed for contract performance.
(2) Upon completion of the Contractor employee’s employment.
(3) Upon contract completion or termination.
SP7000-13-R-1026 Page 14 of 48
(c) The Contracting Officer may delay final payment under a contract if the Contractor fails to comply with these requirements.
(d) The Contractor shall insert the substance of clause, including this paragraph (d), in all subcontracts when the subcontractor’s employees are required to have routine physical access to a Federally-controlled facility and/or routine access to a Federally-controlled information system. It shall be the responsibility of the prime Contractor to return such identification to the issuing agency in accordance with the terms set forth in paragraph (b) of this section, unless otherwise approved in writing by the Contracting Officer.
52.212-5 -- Contract Terms and Conditions Required to Implement Statutes or Executive Orders -- Commercial Items (Nov 2012)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.222-50, Combating Trafficking in Persons (FEB 2009) (22 U.S.C. 7104(g)).
_X_ Alternate I (AUG 2007) of 52.222-50 (22 U.S.C. 7104(g)).
(2) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(3) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the contracting officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.]
X (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 253g and 10 U.S.C. 2402).
___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Apr 2010) (Pub. L.
110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub L. 111-5) (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009).
___ (4) 52.204-10, Reporting Executive compensation and First-Tier Subcontract Awards (Aug 2012) (Pub. L. 109-282) (31 U.S.C. 6101 note).
___ (5) 52.204-11, American Recovery and Reinvestment Act—Reporting Requirements (Jul 2010) (Pub. L. 111-5).
_X_ (6) 52.209-6, Protecting the Government’ Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Dec 2010) (31 U.S.C.
6101 note).
___ (7) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Feb 2012) (41 U.S.C. 2313).
SP7000-13-R-1026 Page 15 of 48
___ (8) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (May 2012) (section 738 of Division C of Public Law 112-74, section 740 of Division C of Pub. L. 111-117, section 743 of Division D of Pub. L. 111-8, and section 745 of Division D of Pub. L. 110-161).
___ (9) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).
___ (10) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Jan 2011) (if the offeror elects to waive the preference, it shall so indicate in its offer)(15 U.S.C. 657a).
___ (11) [Reserved]
___ (12) (i) 52.219-6, Notice of Total Small Business Aside (Nov 2011) (15 U.S.C. 644).
___ (ii) Alternate I (Nov 2011).
___ (iii) Alternate II (Nov 2011).
___ (13) (i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C.
644).
___ (ii) Alternate I (Oct 1995) of 52.219-7.
___ (iii) Alternate II (Mar 2004) of 52.219-7.
_X_ (14) 52.219-8, Utilization of Small Business Concerns (Jan 2011) (15 U.S.C.
637(d)(2) and (3)).
_X_ (15) (i) 52.219-9, Small Business Subcontracting Plan (Jan 2011) (15 U.S.C. 637 (d)(4).)
___ (ii) Alternate I (Oct 2001) of 52.219-9.
___ (iii) Alternate II (Oct 2001) of 52.219-9.
___ (iv) Alternate III (July 2010) of 52.219-9.
___ (16) 52.219-13, Notice of Set-Aside of Orders (Nov 2011) (15 U.S.C. 644(r)).
___ (17) 52.219-14, Limitations on Subcontracting (Nov 2011) (15 U.S.C. 637(a)(14)).
___ (18) 52.219-16, Liquidated Damages—Subcontracting Plan (Jan 1999) (15 U.S.C.
637(d)(4)(F)(i)).
___ (19) (i) 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns (Oct 2008) (10 U.S.C. 2323) (if the offeror elects to waive the adjustment, it shall so indicate in its offer).
___ (ii) Alternate I (June 2003) of 52.219-23.
SP7000-13-R-1026 Page 16 of 48
___ (20) 52.219-25, Small Disadvantaged Business Participation Program— Disadvantaged Status and Reporting (Dec 2010) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
___ (21) 52.219-26, Small Disadvantaged Business Participation Program—Incentive Subcontracting (Oct 2000) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
___ (22) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set- Aside (Nov 2011) (15 U.S.C. 657f).
_X_ (23) 52.219-28, Post Award Small Business Program Rerepresentation (Apr 2012) (15 U.S.C. 632(a)(2)).
___ (24) 52.219-29, Notice of Set-Aside for Economically Disadvantaged Women- Owned Small Business (EDWOSB) Concerns (Apr 2012) (15 U.S.C. 637(m)).
___ (25) 52.219-30, Notice of Set-Aside for Women-Owned Small Business (WOSB) Concerns Eligible Under the WOSB Program (Apr 2012) (15 U.S.C. 637(m)).
_X_ (26) 52.222-3, Convict Labor (June 2003) (E.O. 11755).
_X_ (27) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Mar 2012) (E.O. 13126).
_X_ (28) 52.222-21, Prohibition of Segregated Facilities (Feb 1999).
_X_ (29) 52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).
_X_ (30) 52.222-35, Equal Opportunity for Veterans (Sep 2010) (38 U.S.C. 4212).
_X_ (31) 52.222-36, Affirmative Action for Workers with Disabilities (Oct 2010) (29 U.S.C. 793).
_X_ (32) 52.222-37, Employment Reports on Veterans (Sep 2010) (38 U.S.C. 4212).
___ (33) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).
___ (34) 52.222-54, Employment Eligibility Verification (Jul 2012). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)
___ (35) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA- Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)).
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .