0008 Att 1 Schedule.pdf

PDF 147 KB Posted

Attached to
Distribution and Warehousing Services at DLA Distribution Cherry Point, NC Federal contract opportunity
Solicitation number
SP3300-24-R-5003
Issued by
Defense Logistics Agency Distribution

About this file

This document is a Schedule B from a federal contract opportunity for Distribution and Warehousing Services at DLA Distribution Cherry Point, NC. The contract has a 5-year period of performance from February 2025 to January 2030.

The contract includes the following key requirements: Services to perform warehousing and distribution operations, non-capital equipment new or replacement costs, material support costs, scheduled and unscheduled equipment maintenance, contractor-owned contractor-operated (COCO) facilities in Greenville and Newport, travel for training and conferences, and special projects/surge and sustainment support. Pricing is structured as firm-fixed-price, cost-reimbursement, and cost-plus-fixed-fee CLINs. The estimated total contract cost across the 5-year period is not-to-exceed the total indicated in the document. The solicitation number is SP3300-24-R-5003.

View the file

Other files for this federal contract opportunity

Other files attached to Distribution and Warehousing Services at DLA Distribution Cherry Point, NC, newest first.
File Type Posted
Att 2 - Solicitation Conformed 8-21-24.pdf PDF
Att 1 - Solicitation Tracked 0010 8-21-24.docx DOCX document
Amendment 0008 SF30 SP330024R5003.pdf PDF
Att 3 0007 Applicable DSS Roles.pptx PPTX presentation
Att 2 0007 TE 2.1.1 WMS to DSS Crosswalk.pdf PDF
Amendment 0007 SF30 SP330024R5003.pdf PDF
Att 2 - Solicitation tracked 0005.docx DOCX document
Att 8 TE 5.0 APLs Conformed 0005.docx DOCX document
Att 7 TE 5.0 APLs Tracked 0005.docx DOCX document
Att 4 - J.1 PWS Tracked 0005.docx DOCX document
Att 1 - Questions and Answers 0005.docx DOCX document
Att 6 TE 5.2 Projected Workload 0005.xlsx XLSX spreadsheet
Att 5 - J.1 PWS Conformed 0005.docx DOCX document
Att 3 - Solicitation Conformed 0005.pdf PDF
Amendment 0005 SF30 SP330024R5003.pdf PDF
Att 10 - Solicitation conformed.pdf PDF
Att 5 - TE 5.0 APLs conformed.docx DOCX document
Att 3 - J.1 PWS conformed.docx DOCX document
Att 11 - DDCN SSMR Dec 2023.xlsx XLSX spreadsheet
Att 9 - Solicitation tracked changes.docx DOCX document
Att 8 - DLA DD254 Cont Page.docx DOCX document
Att 2 - J.1 PWS tracked change.docx DOCX document
Att 7 - TE 5.2 Projected Workload.xlsx XLSX spreadsheet
Att 6 - TE 5.1 Historical Workload.docx DOCX document
Att 4 - TE 5.0 APLs tracked changes.docx DOCX document
Amendment 0004 SF30 SP330024R5003.pdf PDF
Att 1 - Questions and Answers.docx DOCX document
Amendment 0003 SF30 SP330024R5003.pdf PDF
Amendment 0002 SF30 SP330024R5003.pdf PDF
DDCN PPC Attendance 23 Aug 2024 (Day 1).pdf PDF
DDCN PPC Slide Deck_Final 4-23-2024 JCD Rev 1.pptx PPTX presentation
Att 1 Conformed Solicitation 0002.pdf PDF
Att 2 Conformed Solicitation 0001.pdf PDF
Att 1 Section M - Tracked Changes 0001.pdf PDF
Att 3 J.13 DDCN Preproposal Conference Instructions.pdf PDF
Amendment 0001 SF30 SP330024R5003.pdf PDF
J.12 Contractor Equipment List 24R5003.xlsx XLSX spreadsheet
J.10 Accounting System Self-Certification.pdf PDF
J.6 CLIN X006 Labor Rate Table.xlsx XLSX spreadsheet
J.3 WD 2015-5781 Rev 22.pdf PDF
J.2 DDCN 24R5003.docx DOCX document
J.5 DD254 DDCN SP330024R5003.pdf PDF
J.4 DDCN CBA.pdf PDF
J.11 Limitation on Subcontracting.xlsx XLSX spreadsheet
J.8 PPQ.docx DOCX document
J.7 Tech Exhibits.zip ZIP file
J.5 DLA DD254 Continuation Page Template_SP3300-24-R-5003.docx DOCX document
J.1 DDCN PWS 24R5003.docx DOCX document
J.9 CDRLs.zip ZIP file
SP3300-24-R-5003 DDCN RFP.pdf PDF
Show all 50

Distribution and Warehousing Services at DLA Distribution Cherry Point, NC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM

NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

PERFORMANCE YEAR ONE

1 February 2025 - 31 January 2026

Firm-Fixed Price (Applicable to CLIN 0001)

? EA $1.00 ?

PoP: 9 Months (1 May 2025 - 31 January 2026)

Cost Reimbursement (Applicable to CLINs 0002, 0003, 0004 & 0005)

Estimated Cost $63,451.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $63,451.00

Estimated Cost $228,107.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $228,107.00

Estimated Cost $1,283,208.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $1,283,208.00

Estimated Cost $3,413.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $3,413.00

Cost-Plus Fixed Fee (Applicable to CLIN 0006)

Estimated Cost $101,330.00 Fixed Fee ___% $0.00

Not-to-Exceed (NTE) 1 LOT $101,330.00

Firm-Fixed Price (Applicable to CLIN 0007)

9 MO ? #VALUE!

PoP: 9 Months (1 May 2025 - 31 January 2026)

Travel for Training and Conferences (PWS Sections C-3.3, C-4.6, and C-5.9)

Special Projects/Surge & Sustainment (PWS Section C-5.8) (See Attachment J.6, CLIN X006 Labor Rate Table, for applicable labor categories and labor rates)

PART 1 - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

Services to Perform Warehousing and Distribution Operations (Unless specifically identified separately in another CLIN, this CLIN encompasses PWS Sections C-1 through C-6)

Non-Capital Equipment New or Replacement Costs (PWS Section C-4.2 paragraphs C&D)

Material Support Costs ( inclusive of CLINs 0001, 0006, 0007, 0009, and 0010)

Scheduled and Unscheduled Equipment Maintenance (Parts Only) (PWS Section C-4.4 and its sub-paragraphs)

Contractor Owned Contractor Operated (COCO) Facilities (Greenville) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

0008 1 LOT NSP NSP

Firm-Fixed Price (Applicable to CLIN 0009)

0009 3 MO ? #VALUE!

PoP: 3 Months (1 February 2025 - 30 April 2025)

Firm-Fixed Price (Applicable to CLIN 0010)

9 MO ? #VALUE!

PoP: 9 Months (1 May 2025 - 31 January 2026)

TOTAL ESTIMATED COST – PERFORMANCE YEAR ONE #VALUE!

PERFORMANCE YEAR TWO

1 February 2026 - 31 January 2027

Firm-Fixed Price (Applicable to CLIN 1001)

? EA $1.00 ?

PoP: 12 Months (1 February 2026 - 31 January 2027)

Cost Reimbursement (Applicable to CLINs 1002, 1003, 1004 & 1005)

Estimated Cost $87,834.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $87,834.00

Estimated Cost $315,760.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $315,760.00

Estimated Cost $1,776,302.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $1,776,302.00

Contractor Owned Contractor Operated (COCO) Facilities (Newport) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

Services to Perform Warehousing and Distribution Operations (Unless specifically identified separately in another CLIN, this CLIN encompasses PWS Sections C-1 through C-6)

Scheduled and Unscheduled Equipment Maintenance (Parts Only) (PWS Section C-4.4 and its sub-paragraphs)

Non-Capital Equipment New or Replacement Costs (PWS Section C-4.2 paragraphs C&D)

Material Support Costs ( inclusive of CLINs 1001, 1006, 1007, 1009, and 1010)

Contract Data Requirements List (CDRL) in accordance with DD Form 1423 - Attachment J.9 CDRLs. (Note: Contractor shall not price these items separately)

Services to Perform Transition per C-1.8 (Unless specifically identified separately in another CLIN, this CLIN encompasses PWS Sections C-1 through C-6)

Travel for Training and Conferences (PWS Sections C-3.3, C-4.6, and C-5.9)

Estimated Cost $4,725.00

Not-to-Exceed (NTE) G&A Rate ___% $0.00 Not-to-Exceed (NTE) 1 LOT $4,725.00

Cost-Plus Fixed Fee (Applicable to CLIN 1006)

Estimated Cost $105,201.00 Fixed Fee ___% $0.00

Not-to-Exceed (NTE) 1 LOT $105,201.00

Firm-Fixed Price (Applicable to CLIN 1007)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2026 - 31 January 2027)

1008 1 LOT NSP NSP

Firm-Fixed Price (Applicable to CLIN 1010)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2026 - 31 January 2027)

TOTAL ESTIMATED COST – PERFORMANCE YEAR TWO #VALUE!

PERFORMANCE YEAR THREE

1 February 2027 - 31 January 2028

Firm-Fixed Price (Applicable to CLIN 2001)

? EA $1.00 ?

PoP: 12 Months (1 February 2027 - 31 January 2028)

Cost Reimbursement (Applicable to CLINs 2002, 2003, 2004 & 2005)

Estimated Cost $91,189.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $91,189.00

Estimated Cost $327,822.00

Special Projects/Surge & Sustainment (PWS Section C-5.8) (See Attachment J.6, CLIN X006 Labor Rate Table, for applicable labor categories and labor rates)

Contractor Owned Contractor Operated (COCO) Facilities (Greenville) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

Contract Data Requirements List (CDRL) in accordance with DD Form 1423 - Attachment J.9 CDRLs. (Note: Contractor shall not price these items separately)

Contractor Owned Contractor Operated (COCO) Facilities (Newport) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

Non-Capital Equipment New or Replacement Costs (PWS Section C-4.2 paragraphs C&D)

Services to Perform Warehousing and Distribution Operations (Unless specifically identified separately in another CLIN, this CLIN encompasses PWS Sections C-1 through C-6)

Scheduled and Unscheduled Equipment Maintenance (Parts Only) (PWS Section C-4.4 and its sub-paragraphs)

Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $327,822.00

Estimated Cost $1,844,157.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $1,844,157.00

Estimated Cost $4,905.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $4,905.00

Cost-Plus Fixed Fee (Applicable to CLIN 2006)

Estimated Cost $109,219.00 Fixed Fee ___% $0.00

Not-to-Exceed (NTE) 1 LOT $109,219.00

Firm-Fixed Price (Applicable to CLIN 2007)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2027 - 31 January 2028)

2008 1 LOT NSP NSP

Firm-Fixed Price (Applicable to CLIN 2010)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2027 - 31 January 2028)

TOTAL ESTIMATED COST – PERFORMANCE YEAR THREE #VALUE!

PERFORMANCE YEAR FOUR

1 February 2028 - 31 January 2029

Firm-Fixed Price (Applicable to CLIN 3001)

? EA $1.00 ?

PoP: 12 Months (1 February 2028 - 31 January 2029)

Contractor Owned Contractor Operated (COCO) Facilities (Greenville) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

Material Support Costs ( inclusive of CLINs 2001, 2006, 2007, 2009, and 2010)

Travel for Training and Conferences (PWS Sections C-3.3, C-4.6, and C-5.9)

Special Projects/Surge & Sustainment (PWS Section C-5.8) (See Attachment J.6, CLIN X006 Labor Rate Table, for applicable labor categories and labor rates)

Contract Data Requirements List (CDRL) in accordance with DD Form 1423 - Attachment J.9 CDRLs. (Note: Contractor shall not price these items separately)

Contractor Owned Contractor Operated (COCO) Facilities (Newport) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

Services to Perform Warehousing and Distribution Operations (Unless specifically identified separately in another CLIN, this CLIN encompasses PWS Sections C-1 through C-6)

Cost Reimbursement (Applicable to CLINs 3002, 3003, 3004 & 3005)

Estimated Cost $94,672.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $94,672.00

Estimated Cost $340,345.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $340,345.00

Estimated Cost $1,914,603.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $1,914,603.00

Estimated Cost $5,093.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $5,093.00

Cost-Plus Fixed Fee (Applicable to CLIN 3006)

Estimated Cost $113,391.00 Fixed Fee ___% $0.00

Not-to-Exceed (NTE) 1 LOT $113,391.00

Firm-Fixed Price (Applicable to CLIN 3007)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2028 - 31 January 2029)

3008 1 LOT NSP NSP

Firm-Fixed Price (Applicable to CLIN 3010)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2028 - 31 January 2029)

Special Projects/Surge & Sustainment (PWS Section C-5.8) (See Attachment J.6, CLIN X006 Labor Rate Table, for applicable labor categories and labor rates)

Contractor Owned Contractor Operated (COCO) Facilities (Greenville) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

Contract Data Requirements List (CDRL) in accordance with DD Form 1423 - Attachment J.9 CDRLs. (Note: Contractor shall not price these items separately)

Contractor Owned Contractor Operated (COCO) Facilities (Newport) (Unless specifically identified separately in another CLIN, this CLIN encompasses Attachment J.2 PWS Section C-4M)

Scheduled and Unscheduled Equipment Maintenance (Parts Only) (PWS Section C-4.4 and its sub-paragraphs)

Non-Capital Equipment New or Replacement Costs (PWS Section C-4.2 paragraphs C&D)

Material Support Costs ( inclusive of CLINs 3001, 3006, 3007, 3009, and 3010)

Travel for Training and Conferences (PWS Sections C-3.3, C-4.6, and C-5.9)

TOTAL ESTIMATED COST – PERFORMANCE YEAR FOUR #VALUE!

PERFORMANCE YEAR FIVE

1 February 2029 - 31 January 2030

Firm-Fixed Price (Applicable to CLIN 4001)

? EA $1.00 ?

PoP: 12 Months (1 February 2029 - 31 January 2030)

Cost Reimbursement (Applicable to CLINs 4002, 4003, 4004 & 4005)

Estimated Cost $98,289.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $98,289.00

Estimated Cost $353,347.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $353,347.00

Estimated Cost $1,987,741.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $1,987,741.00

Estimated Cost $5,287.00 Not-to-Exceed (NTE) G&A Rate ___% $0.00

Not-to-Exceed (NTE) 1 LOT $5,287.00

Cost-Plus Fixed Fee (Applicable to CLIN 4006)

Estimated Cost $117,723.00 Fixed Fee ___% $0.00

Not-to-Exceed (NTE) 1 LOT $117,723.00

Firm-Fixed Price (Applicable to CLIN 4007)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2029 - 31 January 2030)

Services to Perform Warehousing and Distribution Operations (Unless specifically identified separately in another CLIN, this CLIN encompasses PWS Sections C-1 through C-6)

Travel for Training and Conferences (PWS Sections C-3.3, C-4.6, and C-5.9)

Special Projects/Surge & Sustainment (PWS Section C-5.8) (See Attachment J.6, CLIN X006 Labor Rate Table, for applicable labor categories and labor rates)

Contractor Owned Contractor Operated (COCO) Facilities (Greenville) (Unless specifically identified separately in another

Contract Data Requirements List (CDRL) in accordance with DD

Scheduled and Unscheduled Equipment Maintenance (Parts Only) (PWS Section C-4.4 and its sub-paragraphs)

Non-Capital Equipment New or Replacement Costs (PWS Section C-4.2 paragraphs C&D)

Material Support Costs ( inclusive of CLINs 4001, 4006, 4007, 4009, and 4010)

4008 1 LOT NSP NSP

Firm-Fixed Price (Applicable to CLIN 4010)

12 MO ? #VALUE!

PoP: 12 Months (1 February 2029 - 31 January 2030)

TOTAL ESTIMATED COST – PERFORMANCE YEAR FIVE #VALUE!

TOTAL ESTIMATED CONTRACT COST #VALUE!

Contractor Owned Contractor Operated (COCO) Facilities (Newport) (Unless specifically identified separately in another

Form 1423 - Attachment J.9 CDRLs. (Note: Contractor shall not price these items separately)

24R5003 Schedule B

File details come from the government source that posted it. Updated .