Solicitation N3220521R4225.docx

DOCX document 134 KB Posted

Attached to
USNS COMFORT (T-AH 20) ROH/DD Solicitation
Solicitation number
N3220521R4225
Issued by

About this file

This solicitation is for the Regular Overhaul and Dry Docking (ROH/DD) of the USNS COMFORT (T-AH 20). The contractor will be required to prepare for and accomplish the ROH/DD at their shipyard according to the Work Item package provided as an attachment. The contractor must have the facilities and capabilities to perform all aspects of the work. The period of performance is 150 calendar days from vessel arrival, which is anticipated on or around March 1, 2022. The solicitation includes pricing tables for firm fixed price line items for Category A required work items and optional Category B work items. Additional general services and requirements are outlined such as project planning, quality assurance, and hazardous waste disposal.

View the file

Other files

File Type Posted
USNS COMFORT ROH Amendment 0005.docx DOCX document
0712_B_MTF ENLISTED BERTHING DECKING RENEWAL (VR21-0062).doc DOC document
USNS COMFORT ROH Amendment 0004.pdf PDF
0031_B_(REV A) MTF SPONSOR OFFICE.docx DOCX document
J-2 Category A Rev 0004.xlsx XLSX spreadsheet
J-3 Category B Rev 0004.xlsx XLSX spreadsheet
709_A_(REV A) MTF T-AH COMFORT NAVY CASH EFT SYSTEM INSTALLATION.doc DOC document
502_A_(REV C) SLEP- TLI SENSOR INSTALLATION PHASE 2 (T-ALT 14009).doc DOC document
510_A_(REV B) SLEP-ADG LUBE OIL PURIFER INSTALLATION (T-ALT 17011).doc DOC document
USNS COMFORT ROH Amendment 0003.docx DOCX document
Responces to RFC 064-067.docx DOCX document
492_A_(REV B)TAH_CSI_CALIBRATE ELECTRONIC TEST EQUIPMENT (GPETE) (Annual).doc DOC document
USNS COMFORT ROH Amendment 0002.docx DOCX document
Revised Work Items 0002.zip ZIP file
J2 Category A.xlsx XLSX spreadsheet
Responces to Bidders Questions (09-02-21).docx DOCX document
0492_A_TAH CSI CALIBRATE ELECTRONIC TEST EQUIPMENT (GPETE) (Annual).doc DOC document
Responces to Bidders Questions (08-25-21).docx DOCX document
Revised Work Items.zip ZIP file
USNS COMFORT ROH Amendment 0001.docx DOCX document
J-14 Technical Data Non-Disclosure.docx DOCX document
J-3 Category B.xlsx XLSX spreadsheet
Exhibit A - CDRLs.zip ZIP file
J-7 MSC Ship Repair Facility Survey.docx DOCX document
J-10 Interport Differential.docx DOCX document
J-2 Category A.xlsx XLSX spreadsheet
J-4 GFP.pdf PDF
J-11 Dry Dock Eval Form.docx DOCX document
J-8 Request for Spec Clarification.docx DOCX document
J-9 Disclosure of Lobbying Activities SF-LLL.docx DOCX document
J-12 Past Performance Data.docx DOCX document
J-13 Past Performance Questionnaire.docx DOCX document
JA COMFORT ROH 21R4225 - Redacted.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220521R4225

Section B - Supplies or Services and Prices

CLAUSES INCORPORATED BY FULL TEXT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "A" WIs

FFP

Prepare for and accomplish the ROH/DD of the USNS COMFORT (T-AH 20) Total Category "A" WIs $_____________

Proposed unit price per KWh of electrical shore power $_____ IAW WI 0011, 7.1.1 Proposed unit price per gallon of potable water $______ IAW WI 0011, 7.1.4 Proposed unit price per gallon of distilled water $______ IAW WI 0011, 7.1.5 Proposed unit price per gallon of bilge water removal $______ IAW WI 0011, 7.1.19 Proposed unit price per crane usage $______ IAW WI 0011, 7.1.27 Proposed Hazardous Waste handling fee rate IAW WI 0023, 7.4.3. ______%

CDRLs FOR CLINs INCLUDING OPTION CLINs, IF EXERCISED:

The data to be furnished hereunder shall be prepared and submitted IAW the CDRL, DD Form 1423, Exhibit A, attached hereto. The CDRLs form a part of the schedule of this solicitation.

SEE PARAGRAPH 1.

FOB: Destination

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

AGR and ODC

AGR

21,760 man-hours @ $________ per man-hour = $_____________

ODC

Base $1,088,000.00

Proposed G&A Rate _______________% Subtotal: $_____________

Proposed Profit Rate _______________% Subtotal: $_____________

SEE PARAGRAPH 2, 3, AND 4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0025

WI 0025 - Physical Security at Private Contractor's Facility in FPCON Charlie - Delta

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

SEE PARAGRAPH 5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0026

WI 0026 – Final Vessel Cleaning

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0030

WI 0030 – Continuation of Services

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0031

WI 0031 – MTF Sponsor Office

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0090

WI 0090 – Daily COVID-19 Prevention and Control Services

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0197

WI 0197 – Lead Paint Testing and Abatement

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0198

WI 0198 – Directed Hull Gauging

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0199

WI 0199 – Miscellaneous Steel Repairs

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0599

WI 0599 – Miscellaneous Piping Renewal

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0899

WI 0899 – Insulation and Lagging Repair

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0982

WI 0982 – T-AH CSI Tail Shaft Removal and Inspection (5 YR)

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0997

WI 0997 – Additional Freeboard Preservation

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0998

WI 0998 – Additional Underwater Hull Preservation

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0999

WI 0999 – Extension on Dry Dock

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0016 $______________

The contractor shall enter the total proposed price of all CLINs.

Section B, Price Schedule, detailed information

1. Attachment J-2, Category “A” WIs, provides a WI breakdown of CLIN 0001 pricing.

2. AGR and ODC

a. This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated during the contract. Changes are inherent to vessel repair contracts and should be expected by Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:

Abrasive cleaning/blastingTank cleaning
WeldingMachinists (inside and outside)
BurningBrazing
CarpentryElectrical work
Electronic workShipfitting
LaggingPainting
BoilermakingPipefitting
Sheetmetal workEngineering
RiggingStaging/scaffolding
General laborFire Watch

b. Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:

TestingQuality Assurance
PlanningCleaning (except tank cleaning)
Material handling & warehousingSecurity
SurveyingAdministration
TransportationPurchasing staff
LoftingOther indirect support
Supervision

c. Consumable materials are goods used in the ordinary course of work performance that do not become an integral part of the repaired vessel (e.g., office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing). Consumable material shall be included in the contractor's FBLR and not separately priced.

d. The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The ACO will apply these rates to the ODCs for each CCO when it is negotiated and settled.

e. The base cost stated in this CLIN does not include profit or G&A rates.

f. This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.

3. AGR details.

a. The Government may utilize CLIN 0002 for, and not limited to, man-hours generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. AGR does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 AGR man-hours, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with ODC, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders AGR pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time as may be granted, may be considered a failure of the parties to negotiate a fair and reasonable price for the AGR and will permit the ACO to take any of the three (3) options set forth in subparagraph “d” below. AGR proposals shall be priced using the FBLR set forth in Section B, CLIN 0002. The rate established in CLIN 0002 will be used in evaluating the contractor's proposal and for negotiating changes. As part of the contractor’s proposal submission for AGR, the following shall be included:

- FBLR
- Proposed Labor Mix/Categories
- Proposed Man Hours
- Total Proposed AGR

c. Considering FBLRs have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of labor categories and associated man-hours to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) as a result of the mix of labor categories and man-hours, the subsequent AGR price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “d”, below.

d. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

e. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the AGR at the contractor's facility. Furthermore, in cases described in subparagraphs “d.1” and “d.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

f. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for AGR (CLIN 0002). Settlement of AGR (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The Contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0016 at contract completion shall be de-obligated.

4. ODC details.

a. The Government may utilize CLIN 0002 for and not limited to, material and equipment generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. ODC does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 ODC, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with AGR, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders ODC pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the ODC and will permit the ACO to take any of the three options set forth in subparagraph “e” below. As part of the contractor’s proposal submission for ODCs, the following shall be included:

MaterialEquipment
-Part number- Part number
-Order quantity- Order quantity
-Unit price- Unit price
-Total price- Total price

Other Direct Costs not captured above

- Travel

- Per diem (lodging, M&IE daily rates)

- Subcontractor Proposal Breakdown shall include but not be limited to, Material (Part number, Order Quantity, Unit Price, and Total Price), equipment (Part Number, Order Quantity, Unit Price, and Total Price), labor (FBLR, Proposed Labor Mix/Categories, and Proposed Manhours), and ODC (Travel and Per Diem)

The G&A and profit rates proposed shall be the same as the rates provided under CLIN 0002.

c. The contractor shall demonstrate due diligence in the assessment, evaluation, and determination resulting in the proposed utilization of other than local specialized labor resources. Only with ACO approval to proceed will a contractor, technical representative, or subcontractor be reimbursed for reasonable per diem costs (transportation, travel expenses, lodging, meals, and incidental expenses) required in connection with the associated change order. Per diem costs are considered reasonable, allowable, and reimbursable only to the extent that they do not exceed the allowed per diem rate in effect at the time of travel as set forth in the JTR.

d. Considering G&A and profit rates have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of ODCs proposed to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) the price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “e”, below.

e. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

f. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing this work at the contractor's facility. Furthermore, in cases described in subparagraphs “e.1” and “e.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

g. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for the ODC (CLIN 0002). Settlement of ODC (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0016 at contract completion shall be de-obligated.

5. Attachment J-3, Category “B” WIs, provides a WI breakdown of CLIN 0003 through 0016 pricing.

Section C - Descriptions and Specifications

ACRONYM TABLE

ABIH
American Board of Industrial Hygiene
ABR
Agreement for Boat Repair
ABS
American Bureau of Shipping
ACO
Administrative Contracting Officer
AGR
Additional Government Requirements
AIHA
American Industrial Hygiene Association
ALT
Alternate
AMT
Amount
BLDG
Building
CCO
Contract Change Order
CD
Compact Disc
CDRL
Contract Data Requirements List
CD-ROM
Compact Disc Read-Only Memory
CFM
Contractor Furnished Material
CFP
Contractor Furnished Property
CFR
Condition Found Report
CHENG
Chief Engineer
CFR
Code of Federal Regulations
CIH
Certified Industrial Hygienist
CLIN
Contract Line Item Number

CONUS

CPARS

Contiguous United States Contractor Performance Assessment Reporting System

DBIDS
Defense Biometric Identification Systems
DFARS
Defense Federal Acquisition Regulation Supplement
DOD
Department of Defense
DOD SAFE
Department of Defense Secure Access File Exchange
DON
Department of the Navy
EMAIL
Electronic Mail
ESRS
Electronic Subcontract Report System
FAPIIS
Federal Awardee Performance and Integrity Information System
FAR
Federal Acquisition Regulation
FBLR
Fully-Burdened Labor Rate
F/CC
Fibers Per Cubic Centimeter
FPCON
Force Protection Condition
FTR
Federal Travel Regulations
G&A
General and Administrative
GFI-TD
Government Furnished Information – Technical Data
GFM
Government Furnished Material
GFP
Government Furnished Property
GPE
Governmentwide Point of Entry
IAW
In Accordance With
ID
Identification
ISO
International Organization for Standardization
JTR
Joint Travel Regulations
KO
Contracting Officer
KWh
Kilowatt Hour
LLTM
Long Lead Time Material
LPTA
Lowest Price Technically Acceptable
M&IE
Meals and Incidental Expenses
MSC
Military Sealift Command
MSCREP
Military Sealift Command Representative
MM
Millimeter
MSRA
Master Ship Repair Agreement
MTA
Mid-Term Availability
N/A
Not Applicable
NCACS
Navy Commercial Access Control System
NDA
Non-Disclosure Agreement
NO
Number
NSP
Not Separately Priced
ODC
Other Direct Costs
PAT
Proficiency in Analytical Testing

PDF

PII

Portable Document Format Personally Identifiable Information

PM
Program Manager
PPE
Principle Port Engineer
PRIME
Prime Contractor
QA
Quality Assurance
QC
Quality Control
REV
Revision
RFC
Request for Specification Clarification
RFP
Request for Proposal
ROH/DD
Regular Overhaul/Dry-Docking
SECNAV
Secretary of the Navy
SF
Standard Form
SUB
Subcontractor
TPSN
Time Phased Sequencing Network
TWA
Time-Weighted Average
USC
United States Code
USCG
United States Coast Guard
USNS
United States Naval Ship
VR
Voyage Repair
WAWF
Wide Area Workflow
WI
Work Item

SCOPE OF WORK

1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS COMFORT (T-AH 20) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.

2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):

a. Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.

b. Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR 52.245-1 and DFARS 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.

c. Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.

d. Using management procedures and systems to identify behind-schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.

e. Developing a performance milestone schedule/critical path chart to measure scheduled performance. Deviations from the milestone schedule/critical path chart dates in WI 0013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted IAW the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths. The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 0013.

f. Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.

g. Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.

h. Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.

i. Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.

j. Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.

k. Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.

3. Contract work shall be performed by an eligible contractor as defined below.

a. The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.

b. The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:

1) Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority. Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.

2) Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.

3) Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.

4) Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.

5) Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.

6) Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.

7) Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.

8) Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training. First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.

9) Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records which indicate type of material, date, and place of disposal.

10) Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:

· Pier, with services in place, accessible to the CLASS size ship for berthing

· Structural Shop

· Machine Shop

· Pipe Shop

· Electrical/Electronic Shop

· Carpentry Shop

· Rigging Equipment

· Dry-dock – when required for docking of vessel in performance of the specification

11) Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.

c. The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.

4. Asbestos removal requirements.

a. During the performance of this contract the contractor and subcontractors may be required to perform work which involves the removal or disturbance of asbestos or asbestos-containing products. This requirement applies to each instance of asbestos removal or disturbance.

b. The contractor shall comply with the precautions required in 29 CFR 1910.1001, 29 CFR 1926.58 and 40 CFR Part 61 and all other applicable Federal, state, and local restrictions. The contractor shall forward a copy of all required notices, licenses and permits to the KO immediately upon issuance or receipt.

c. The latest change to the Federal, state, and local regulations in effect at the time of issuance of the contract shall govern. Compliance with these regulations is mandatory and is necessary to protect the employees of the contractor and Naval personnel from exposure to asbestos fibers in excess of the OSHA Action level airborne concentration (currently 0.1 f/cc of air).

d. During removal or disturbance, the contractor shall control airborne asbestos concentrations outside the removal boundary to less than 0.1 f/cc at all times.

e. After removal or disturbance is complete, the areas within the removal boundary shall not be released for re-occupancy until clearance air sampling demonstrates these spaces have concentrations of asbestos less than 0.1 f/cc.

f. In all respects, the performance of air sampling and analysis shall be performed IAW the OSHA Reference Method (Appendix A of 29 CFR 1910.1001), with the following additional specifications:

1) Aggressive clearance sampling shall be performed on 25 mm cassettes at 2.0 liters per minute for a minimum of four (4) hours.

2) In performing the clearance sampling, the pump shall be placed within the compartment where the removal or disturbance occurred. When this operation is conducted in a multilevel space, at least one pump shall be placed on each level.

3) Air sampling shall be performed by a person competent in sampling procedures and overseen by a CIH by the ABIH.

4) Laboratory analysis of samples shall be performed by a participant in the AIHA PAT Program rated proficient for asbestos and air.

g. Personal sampling shall be conducted using breathing zone air samples which are representative of the 8-hour TWA exposure of each individual. Samples shall be collected and analyzed using the OSHA Reference Method contained in either 29 CFR 1910.1001 (as amended) or 29 CFR 1926.58 (as amended).

h. The contractor agrees to indemnify MSC for any fines assessed by Federal, state, or local agencies, for the contractor's failure to properly follow applicable regulations.

i. The contractor shall insert this instruction in all subcontracts entered into under this contract.

5. Post-award substitution of any major subcontractor should not be effected unless the proposed substitution is submitted to the KO and official approval is obtained. The post-award substitution or insertion of a second-tier subcontractor will be treated in the same manner as the substitution of a major subcontractor and requires specific approval by the KO.

6. Substitution of key personnel.

a. The contractor agrees to assign to this contract those persons identified as key personnel who are necessary to fulfill the requirements of this contract and whose resumes were submitted with the proposal. No substitution of key personnel shall be made except IAW these instructions.

b. All proposed substitutions must be submitted, in writing, at least seven (7) days in advance of the proposed substitutions to the KO and must provide the information required by paragraph “c” below.

c. All requests for substitution must provide a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information as requested by the KO. All proposed substitutes must have qualifications equal to or higher than the qualifications of the person to be replaced. The KO or his authorized representative will evaluate such requests and promptly notify the contractor of the approval or disapproval thereof.

7. It is anticipated the ship will arrive at the contractor’s yard on or about March 1, 2022. All work shall be completed in no more than 150 calendar days from the actual start date designated by the Government at the time of contract award.

8. The place of performance for this contract shall be the contractor’s facility. Due to operational commitments, the location shall be on the East or Gulf Coast.

Table 1: List of WIs:

Item Number
Title
Category
SECTION 0000
GENERAL SERVICES AND REQUIREMENTS
0001
SCOPE GENERAL REQUIREMENTS AND DEFINITIONS REV 2021-2-20
NSP
0002
TECHNICAL AND MANUFACTURERS REPRESENTATIVES REV 2021-2-20
NSP
0003
APPROACH BERTH AND MOORING REQUIREMENTS REV 2021-2-20 TAH20
NSP
0004
TESTING AND QUALITY ASSURANCE REV 2021-2-20
NSP
0005
ELECTRICAL SAFETY PROCEDURE REQUIREMENTS, REV 2021-2-20
NSP
0006
HEAVY WEATHER PLAN, REV 2021-2-20 TAH20
NSP
0007
COLD WEATHER PLAN, REV 2021-2-20 TAH20
NSP
0010
FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM (OMT) Rev 2021-3-11 TAH
A
0011
FURNISH GENERAL SERVICES FOR THE SHIP-TAH REV 2021-2-20
A
0012
INFORMATION TECHNOLOGY SERVICES REV 2019-8-03
A
0013
PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS REV 2021-2-20
A
0014
WEIGHT AND MOMENT REPORT REV 2021-2-20
A
0015
ILS GFM REV 2021-2-20
A
0016
FIRE PROTECTION AND SHIPS SAFETY PROGRAM REV 2021-2-20
A
0018
DELIVERY AND REDELIVERY OF THE VESSEL REV 2021-2-20
A
0019
SHIPBOARD ACCESS AND SECURITY REV 2021-2-20
A
0020
GAS FREE CERTIFICATES REV 2021-2-20
A
0021
CLEAN AND GAS FREE TANKS, VOIDS AND COFFERDAMS AND SPACE, REV 2021-2-20 TAH
A
0022
MACHINERY SPACE TURN-OVER, DOCK TRIALS AND SEA TRIALS REV 2021-2-20
A
0023
HAZARDOUS WASTE DISPOSAL AT A CONTRACTORS FACILITY, REV 2021-2-20
A
0024
PHYSICAL SECURITY AT PRIVATE CONTRACTOR FACILITY REV 2021-2-20
NSP
0025
ENHANCED PHYSICAL SECURITY AT PRIVATE CONTRACTOR FACILITY REV 2021-2-20
B
0026
FINAL VESSEL CLEANING REV 21-2-20
B
0030
CONTINUATION OF SERVICES, REV 2021-2-20
B
0031
MTF SPONSOR OFFICE
B
0090
DAILY COVID-19 PREVENTION AND CONTROL SERVICES
B
SECTION 0100
HULL AND STRUCTURAL
0101
PUMP ROOM TANK TOP REPAIRS
A
0104
SERVICE AREA BILGE WELL REFURBISHMENT
A
0105
SERVICE AREA 2 STEEL REPAIR (ABS) Rev 6-30-21
A
0107
SERVICE AREA 4 STEEL REPAIR
A
0108
SERVICE AREA 5 STEEL REPAIR Rev 6-30-21
A
0151
TAH_CCSI_ULTRASONIC THICKNESS GAUGINGS (5 YR)
A
0154
TAH_CCSI_ABS SPECIAL TANK INSPECTION (1 X 5 yEARS)
A
0156
TAH_CCSI_FLIGHT DECK PRESERVATION (1 x 3 Years)
A
0162
TAH_CCSI_ WATERTIGHT CLOSURE INSPECTION (1 X 5 Years)
A
0163
TAH_CCSI_FLIGHT DECK SAFETY NET INSPECTION & TEST (1 x 3 Years)
A
0183
TAH_CSI_TANK VENTS OPEN & INSPECT (1 x 5 Years)
A
0197
LEAD PAINT-TESTING AND ABATEMENT
B
0198
DIRECTED HULL GAUGING
B
0199
MISC STEEL REPAIRS
B
SECTION 0200
PROPULSION MACHINERY
0201
SLEP-MAIN CIRC PUMPS AND MOTORS OVERHAUL
A
0202
SLEP-BOILER SAFETY VALVE REPLACEMENT (T-ALT 17041)
A
0204
SLEP-BOILER TUBE INSPECTIONS
A
0206
BOILER STEAM VALVE RENEWAL(VR 21-021)
A
0207
BOILER SUPERHEATER HEADER ORIFICE PLATE REPAIR
A
0251
TAH_CCSI_WOODWARD GOVERNOR SERVICING (20K HR)
A
0252
TAH_CCSI_REDUCTION GEAR INSPECTION (5 YR)
A
0254
TAH_CCSI_THRUST & LINESHAFT BEARING INSPECTION (1 x 5 Years)
A
0281
TAH_CSI_BOILER INSPECTION & HYDRO (1 X 30 MONTHS)
A
0282
BOILER MOUNTS OPEN INSPECT AND TEST (30M)
A
0284
TAH_CSI_STEAM PIPING- INSPECT & HYRO (1 X 5 Years)
A
0285
TAH_CSI_BOILER SLIDING FEET MAINTENANCE (1 X 5 Years)
A
0286
TAH_CSI_HP & LP STEAM TURBINE- OPEN & INSPECT (1 X 5 Years)
A
0287
AUTOMATION AND PROPULSION CONTROL INSPECT AND TEST (1YR)
A
0288
TAH_CSI_MAIN CONDENSER INSPECTION (1 x 5 Years)
A
0290
LUBE OIL FLUSH OF MAIN ENGINE AND REDUCTION GEAR-TAH
A
SECTION 0300
ELECTRICAL
0301
SLEP - SHORE POWER METER INSTALLATION (T-ALT 13007)
A
0302
SLEP-AUX SOLID STATE FREQUENCY CONVERTER INSTALL(T-ALT 14016)
A
0304
BLOOD BANK UPS INSTALLATION (T-ALT 17052)
A
0351
TAH_CCSI_ SWITCHBOARD CLEANING(1 X 30 Months)
A
0352
TAH_CCSI_MOTOR CONTROLLER CENTER CLEANING (30MON)
A
0353
TAH_CCSI_THERMOGRAPHIC SURVEY (1 YR)
A
SECTION 0400
COMMUNICATION AND NAVIGATION
0401
SLEP-H2S ALARM SYSTEM SA2 AND SA5 (T-ALT 11021)
A
0403
SLEP-LOSS OF STEERING ALARM (T-ALT 14029)
A
0456
TAH_CSI_MAGNETIC COMPASS SERVICE (2 YR)
A
0459
TAH_CCSI_ECHO SOUNDER SERVICE (5 YR)
A
0482
TAH_CSI_WINDBIRD CALIBRATION (1 X 3 Years)
A
0490
TAH_CSI_SPEED LOG SERVICING (1 X 5 Years)
A
SECTION 0500
AUXILIARY MACHINERY
0501
SLEP- PLUMBING SYSTEM PHASE 1
A
0502
SLEP- TLI SENSOR INSTALLATION PHASE 2 (T-ALT 14009)
A
0503
SLEP- TLI SENSOR INSTALLATION PHASE 3 (T-ALT 14009)
A
0504
SLEP-CO2 TIME DELAY REPLACEMENT (T-ALT 14012)
A
0505
SLEP- MSD CONTROLLER RENEWAL (T-ALT 17057)
A
0509
SLEP-AC SW PUMP FLUX DRIVE INSTALLATION (T-ALT 17009)
A
0510
SLEP-ADG LUBE OIL PURIFER INSTALLATION (T-ALT 17011)
A
0514
SLEP-WATERTIGHT DOOR INDICATOR TALT (T-ALT 16014)
A
0515
SLEP-SEAWATER PUMP REPLACEMENT (T-ALT 18008)
A
0516
SLEP SW REDUCING STATION-1 OVERHAUL
A
0517
SLEP SW REDUCING STATION-2 OVERHAUL
A
0518
SLEP SW REDUCING STATION-3 OVERHAUL
A
0519
SLEP SW REDUCING STATION-4 OVERHAUL
A
0520
SLEP SW REDUCING STATION-5 OVERHAUL
A
0521
SLEP SW REDUCING STATION-6 OVERHAUL
A
0522
SLEP SW REDUCING STATION-7 OVERHAUL
A
0523
MOORING WINCH OVERHAULS (VR19-0001)
A
0524
MISCELLANEOUS PIPING REPAIRS -Rev 5-28-21
A
0526
FIRE PUMP AND MOTOR OVERHAULS
A
0527
FIRE MAIN ISOLATION VALVE REPAIRS
A
0528
FIRE MAIN RELIEF VALVE REPAIRS
A
0529
ADG JACKET WATER PUMP REPAIR (VR16-0035)
A
0530
ADG AND EDG INJECTOR REFURBISHMENT (VR18-32 AND 33)
A
0531
ADG SEAWATER STRAINER NO1 RENEWAL (VR 18-077)
A
0532
MSD SYSTEM REPAIRS
A
0533
AC CHILLER SW ISOLATION VALVE REPAIR
A
0534
SLEP-INSTALLATION OF FORWARD FIRE PUMP NO. 2
A
0535
CHILLER SEAWATER REGULATING VALVE REPAIRS
A
0536
SLEP-INSTALL SCBA COMPRESSOR & FILL STATION (T-ALT T-AH 19044R)
A
0553
TAH_CSI_PRESSURE VESSEL INSPECTION (5YR)
A
0554
TAH_CCSI_INSPECT, TEST AND CERTIFY MACHINERY SPACE CRANES AND HOISTS (1 YR)
A
0560
TAH_CCSI_PERSONNEL ELEVATOR INSPECTION AND TEST (5 YR)
A
0561
TAH_CCSI_GAUGE CALIBRATION (1 YR)
A
0599
MISCELLANEOIUS PIPING RENEWAL
B
SECTION 0600
HABITABILITY OUTFITTING AND FURNISHINGS
0603
03 LEVEL PASSAGEWAY DECK TILE RENEWAL (VR17-028)
A
0604
TAH_CSI_TENDER BOAT SERVICE- 4YR TAH
A
0605
TAH_CSI_TENDER BOAT DAVIT SERVICE- 4YR TAH
A
0606
TAH_CSI_DECK CRANE INSPECTION-5YR (NON-ABS)
A
0612
MSC CREW 01 LEVEL DECK TILE REPLACEMENT
A
0652
TAH_CSI_LIFEBOAT & DAVIT SERVICE & INSPECTION- 4 YR TAH
A
0654
TAH_CCSI_RESCUE BOAT & DAVIT SERVICE (1 X 5 Years)
A
0655
TAH_CCSI_IMMERSION SUIT SERVICE (3YR)
A
0656
TAH_CCSI_ANNUAL LIFE RAFT CERTIFICATION (ABS)
A
0658
TAH_CCSI_ACCOMMODATION LADDER MAINTENANCE AND TESTING (5YR)
A
0682
TAH_CSI_LIFE RAFT DAVIT SERVICING (1 X 4 Years)
A
0689
TAH_CSI_TENDER BOAT ENGINE & DRIVE SERVICING (1 X 4 YEARS)
A
0690
TAH_CSI_STEAM KETTLE RELIEF VALVE AND HYDROSTATIC TEST (5 YR)
A
0695
TAH_CSI_UTILITY BOAT INSPECTION (1 X 5 Years)
A
SECTION 0700
SPONSOR RELATED
0701
TAH_CSI_SHIPS LAUNDRY EQUIPMENT GROOM AND INSPECT
A
0702
TAH_CSI_PATIENT LITTER HOIST INSPECTION- 30 MONTH
A
0703
MTF OR PRC DECK RENEWAL (VR21-0026)
A
0704
MTF SCULLERY DECK REPLACEMENT (T-ALT 19043R)
A
0705
MTF GALLEY DECK SAND AND RESEAL
A
0706
MTF STOREROOMS DECK GRATING RENEWAL (VR21-0066)
A
0708
MTF OR AREA PRC DECK RENEWAL (VR21-0026)
A
0709
MTF T-AH COMFORT NAVY CASH EFT SYSTEM INSTALLATION
A
0710
MTF FWD WARD PRC DECK RENEWAL (VR21-0075)
A
0711
MTF OFFICER BERTHING (VR21-0076)
A
0712
MTF ENLISTED BERTHING DECKING RENEWAL (VR21-0062)
A
0713
MTF LAUNDRY RECEIVING DECK RENEWAL (VR 21-0071)
A
0714
MTF ELEVATOR VESTIBULE DECK RENEWAL (VR 21-0077)
A
0781
MTF TAH_CSI_O2N2 PRODUCER INSPECTION AND SERVICING (1 YR)
A
0782
MTF TAH_CSI_O2N2 LPAC COMPRESSOR INSPECTION AND SERVICING (1 YR)
A
0783
TAH_CSI_OXYGEN BOTTLE INSPECTION AND HYDRO (5 YR)
A
SECTION 0800
HVAC
0851
TAH_CCSI_ANNUAL GALLEY VENTILATION AND GAYLORD HOOD CLEANING (1 YR)
A
0852
TAH_CCSI_ANNUAL LAUNDRY VENT CLEANING
A
0882
TAH_CSI_AC CHILLER PLANT SERVICING (5 YR)
A
0899
INSULATION AND LAGGING REPAIR
B
SECTION 0900
DRYDOCKING
0901
TAH_CCSI_DRYDOCKING AND UNDOCKING THE VESSEL (1 x 5 Years)
A
0902
BOILER BLOWDOWN PIPING OVERBOARD REPAIR
A
0904
CHAIN LOCKER AND FOREPEAK EDUCTOR VALVE SERVICE
A
0953
TAH_CCSI_ANCHORS, CHAINS & LOCKERS (5YR)
A
0954
TAH_CCSI_RUDDER AND STERN FRAME EXAMINATION (1 x 5 Years)
A
0956
TAH_CCSI_OVERHAULING SEA VALVES (1 X 5 Years)
A
0957
TAH_CCSI_PROPELLER INSPECTION AND POLISHING- ON DOCK (1 X 5 Years) Rev
A
0960
TAH_CCSI_UNDERWATER HULL CLEANING & PAINTING - SPOT BLAST (1 x 5 Years)
A
0962
TAH_CCSI_CATHODIC PROTECTION SYSTEM (1 X 5 Years)
A
0963
TAH_CCSI_SEA CHEST MARINE GROWTH PREVENTION SYSTEM (1 X 5 Years)
A
0964
TAH_CCSI_SW EXPANSION JOINTS (1 x 5 Years)
A
0966
TAH_CCSI_SHAFT ALIGNMENT & BEARING REACTION CHECKS (1 x 5 Years)
A
0980
TAH_CSI_TAILSHAFT INSPECTION - IN PLACE (1 x 5 Years)
A
0982
TAH_CSI_TAILSHAFT REMOVAL AND INSPECTION (5 YR)
B
0984
TAH_CSI_HULL ZINC REPLACEMENT (1 x 5 Years)
A
0985
TAH_CSI_SHAFT SEAL INSPECTION & REPLACEMENT (1 x 5 Years)
A
0997
ADDITIONAL FREEBOARD PRESERVATION
B
0998
ADDITIONAL UNDERWATER HULL PRESERVATION
B
0999
EXTENSION ON DRY DOCK
B

Section D - Packaging and Marking

WOOD PACKAGING MATERIAL (WPM) - ADDITIONAL DELIVERY INSTRUCTIONS

In accordance with the requirements of International Standards for Phytosanitary Measures (ISPM) 15, the following commercial heat treatment process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging Material (WPM). WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames, and cleats. Packaging materials exempt from the requirements are materials that have undergone a manufacturing process such as corrugated fiberboard, plywood, particleboard, veneer and oriented strand board. All WPM shall be constructed from Heat Treated (HT to 56 degrees Centigrade for 30 minutes) lumber and certified by an accredited agency recognized by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). All materials must include certification markings in accordance with ALSC standards and be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved "DUNNAGE" stamp. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment of materials at the point of entry.

(end of instructions)

Section E - Inspection and Acceptance

CLAUSES INCORPORATED BY REFERENCE

252.217-7005
Inspection and Manner of Doing Work
JUL 2009
252.217-7006
Title
DEC 1991
252.217-7013
Guarantees
DEC 1991

Section F - Delivery and Performance

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE
52.242-15
Stop-Work Order
AUG 1989
52.242-17
Government Delay Of Work
APR 1984
52.247-55
F.O.B. Point For Delivery Of Government-Furnished Property
JUN 2003

Section G - Contract Administration data

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer. Invoice and Receiving Report (Combo)

The following information, at a minimum, must be attached into Wide Area Work Flow (WAWF) and submitted with each and every invoice showing certification with the Onsite Management Team prior to submission:

CLIN #
Contract Price Through Mod P0000x
% Complete
Contract Completed ($)
Less Retainage ($)
Less Prev Payments ($)
Amount due this Invoice ($)
Total Invoiced to Date ($)
0003
Option
0004
Option
0005
Option
0006
Option
0007
Option
0008
Option
0009
Option
0010
Option
0011
Option
0012
Option
0013
Option
0014
Option
0015
Option
0016
Option

Military Sealift Command

Administrative Contracting Officer

Military Sealift Command

Ship Yard Representative

Port Engineer

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer. NOT APPLICABLE

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v…

This is the start of the file's text. The full file is on GovTribe.