About this file

This is a Fair Opportunity Proposal Request (FOPR) for repair work at Joint Base Charleston - Air Base, issued by the 628th Contracting Squadron located in Joint Base Charleston, South Carolina.

The solicitation seeks repair services with an estimated project magnitude of $20 million to $25 million. The project number is DKGV 1100820, and proposals are due by March 5, 2025. The period of performance is 180 calendar days from Notice to Proceed. Evaluation will be conducted on a lowest-price, responsive basis, with proposals ranked by price and award made to the lowest priced responsive offeror. Proposals must remain valid for 180 calendar days after the proposal due date. Offerors must submit a Proposal Bond (Standard Form 24) equal to 20 percent of the proposal price. Within 15 days of award, the contractor must submit a Performance Bond (Standard Form 25) and Payment Bond (Standard Form 25-A), each with a penal sum equal to 100 percent of the contract price.

A mandatory pre-proposal site visit will be conducted at Joint Base Charleston - Weapons Station at 9:00 a.m. EST, with contractors meeting at the Visitor Control Center (1650 Redbank Road, Goose Creek, SC 29445) at 8:30 a.m. EST. Attendance is required for proposal responsiveness. All questions must be submitted in writing using the JB Charleston Question and Answer Form (Attachment 4) by the deadline specified in the solicitation. The contracting officer is Rob Melton (843-963-5173). Liquidated damages provisions are referenced in the full solicitation. The notice to offerors states that funds are not presently available and the government reserves the right to cancel the solicitation at any time without obligation to reimburse offerors for costs.

View the file

Other files

File Type Posted
Solicitation Amendment FA441826R00090003.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings_20260918.pdf PDF
Solicitation Amendment - FA441826R00090002.pdf PDF
Attachment YU - Seed Project Schedule B.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings.pdf PDF
Solicitation Attachment - Salvage Storage List.docx DOCX document
Solicitation Attachment - Site Visit Sign-In Sheet.pdf PDF
Attachment XT - JB Charleston Question and Answer Form (Completed).xlsx XLSX spreadsheet
B466 Photos.pdf PDF
Solicitation Attachment - Wage Determination NC20260012 - Wayne County.pdf PDF
Solicitation Attachment - Wage Determination SC20260022 - Berkeley County.pdf PDF
Solicitation Attachment - Hydrant Flow Test Data.pdf PDF
B464 Photos.pdf PDF
Solicitation Attachment - Wage Determination SC20260030 - Sumter County.pdf PDF
Solicitation Attachment - Wage Determination SC20260023 - Charleston County.pdf PDF
Solicitation Attachment - B466 Mechanical RFIs.pdf PDF
Solicitation Attachment - Geotechnical Report 14 April 2025.pdf PDF
Solicitation Attachment - Pre-Proposal Conference Slides 2026.pptx PPTX presentation
Solicitation Attachment YS Seed Project Specifications_Mark Up.pdf PDF
Solicitation Amendment FA441826R00090001.pdf PDF
Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx XLSX spreadsheet
Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx DOCX document
Statement of Work - Attachment 14 - 01 35 26 - Attachment A Accident Investigation (CIRS).pdf PDF
Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf PDF
Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx DOCX document
Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx DOCX document
Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx DOCX document
Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf PDF
Statement of Work - JB CHS MACC.pdf PDF
Solicitation Attachment YT Seed Project Drawings.pdf PDF
Solicitation Attachment YS Seed Project Specifications.pdf PDF
Solicitation Attachment XY - On and Off-Ramp Procedures (1).pdf PDF
Solicitation Attachment XV - Past Performance Survey.pdf PDF
Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf PDF
Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx DOCX document
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf PDF
Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx DOCX document
Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A_E).pdf PDF
Solicitation - FA441826R0009.pdf PDF
Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 9 - 01 33 00 - Attachment A - JB CHS Transmittal Form 4025.pdf PDF
Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule-Pay Calendar Example 2.xlsx XLSX spreadsheet
Statement of Work - Attachment 6 - 01 32 00 - Attachment A - Schedule- Pay Calendar Example 1.pdf PDF
Solicitation Attachment XZ - Past Performance Project List.xlsx XLSX spreadsheet
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.xlsx XLSX spreadsheet
Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DKGV

6 - Liquidated Damages

SEE SOLICITATION

Summary of Work:

5 - Submittal Register

1 - Specifications

2 - Drawings

3 - Schedule B - (CLIN 0001, 0002, 0003)

4 - JB Charleston Question and Answer Form

Solicitation Attachments:

The proposal shall be prepared in accordance with the Schedule B.

Proposal Requirements:

Notice to Offeror: Funds are not presently available for this effort. No award will be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.

Contracting Officer

Key Government Personnel

Contracting OfficerRob Melton

PhoneOrganization

843-963-5173628 CONS

843-963-5172

843-794-4142

843-794-4297628 CES

628 CES

Requirement Special Conditions:

a. In accordance with FAR Clause 52.236-27, Site Visit (Construction), a site visit will be conducted on Joint Base Charleston - Weapons Station on ______ at 9:00 a.m. EST. Contractors will meet the government at the (Visitor Control Center) 1650 Redbank Rd., Goose Creek, SC 29445 at 8:30 am EST. The Government PM shall guide contractors to the location. The Point of Contact (POC) is ____________ (843) ____________.

b. Attendance of the site visit is required for an offerer to be to be considered responsive, unless otherwise specificed. Failure to visit the project site will not relieve the Offeror from responsibility for performance of the work and compliance with the terms and conditions of any resultant contract. In no event will a failure to inspect the site constitute grounds for a claim after award of the task order.

c. All questions shall be submitted in writing, via Attachment 4 - JB Charleston Question and Answer Form. The deadline for all questions pertaining to the solicitation will be _________, 2:00 p.m EST. Remarks and explanations provided at the site visit shall NOT alter the terms of the solicitation and statement of work.

Unless the solicitation is amended in writing, it will remain unchanged.

Pre-Proposal Site Visit:

PROPOSAL BOND: The offeror shall submit a Proposal Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the

Government. Proposal Bond, in the amount of 20 percent (20%) of the proposal price. The Proposal Bond penalty may be expressed in terms of a percentage of the proposal price or may be expressed in dollars and cents. The contractor shall submit a Performance Bond (Standard Form 25) and a

Payment Bond (Standard Form 25-A) with good and sufficient surety and sureties to the Government within 15 days of award. The penal sum of such bonds will be as follows:

Bond Requirements:

X PERFORMANCE BOND: The penal sum of the performance bonds shall equal one hundred percent (100%) of the contract price. PAYMENT BOND: The penal sum of the payment bonds shall equal one hundred percent (100%) of the contract price.

X

Evaluation Factors:

In accrodance with ordering procedures, task order proposals will be evaluated for responsiveness and price. To be considered for award, proposals must be responsive (in compliance with the proposal request requirements) and the total proposed price must be reasonable and balanced. Proposals will be ranked by price and the award will be made to the lowest priced responsive offeror.

calendar days after the proposal due date.Proposals shall be valid for

Fair Opportunity Proposal Request (FOPR)

628th Contracting Squadron - Joint Base Charleston, SC 29404

Repair

Joint Base Charleston - Air BaseProject Location:1100820

Project Title:

Contracting Office:

Contractor Name:

Project Number:

Proposal Due Date: SEE SOLICITATION

$20M-$25M

5-Mar-25

___ Calendar Days from Notice to Proceed (NTP)Period of Performance (PoP):

Solicitation Date:

Project Magnitude: SEE SOLICITATIONSite Visit Date:

Signatures

Contracting Officer:Contractor Representative:

628 CONS

Name Position

Inspector

Project Manager

File details come from the government source that posted it. Updated .