REQUEST FOR INFORMATION (RFI) FORM
This is a standardized Request for Information template used in federal contracting to facilitate efficient communication between contractors and government officials regarding contract clarifications. The form is designed for JB CHS contracts and was last updated on August 24, 2021.
The form is structured in three main sections. Section I captures contractor information and allows the contractor to submit questions or issues related to the contract, with fields for the contractor name, quality control manager signature, and date. The section also includes checkboxes for priority level (High/Normal), potential time and cost impacts, schedule impacts, and critical path impacts, with an estimated days until critical path impact field. Additionally, contractors may propose solutions to their identified issues. Section II designates space for the RFI reviewer to document their recommended response, including reviewer title, name, signature, and date. Section III provides the space for the government official's final RFI response, with fields for the government official's title, name, signature, and date. The form also includes fields for cross-referencing relevant contract documents such as drawings, specification sections, paragraphs, and page numbers. A critical disclaimer notes that the RFI system does not authorize additional work and requires contractors to provide written notice to the Contracting Officer's Representative if the RFI response constitutes a changed condition under contract provisions.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION DATEACTIVITY ID
CONTRACT TITLECONTRACT NO RFI NO
RFI SUBJECT DWG NO
DWG DETAIL
DWG SHEET NO
SPEC SECTION
SPEC PARAGRAPH
SPEC PAGE NO
RFI PRIORITY?
POTENTIAL TIME/COST IMPACT?
SCHEDULE IMPACT?
CRITICAL PATH IMPACT?
HIGH NORMAL
YES NO
YES NO
YES NO
CONTRACTOR PROPOSED SOLUTION: (Reference All Attachments)
REVIEWER RECOMMENDED RFI RESPONSE:
CONTRACTOR QUESTION/ISSUE: (Reference All Attachments)
SECTION III - RFI RESPONSE
SECTION I - CONTRACTOR INFORMATION
SECTION II - RFI REVIEWER
DATENAME NAME OF GOVERNMENT OFFICIAL SIGNATURE SIGNATURE OF OF GOVERNMENT OFFICIALTITLE OF GOVERNMENT OFFICIAL DATE
NAME OF REVIEWER SIGNATURE OF REVIEWERTITLE OF REVIEWER DATE
NAME OF QC MANAGER SIGNATURE OF QC MANAGERNAME OF CONTRACTOR DATE
JB CHS REQUEST FOR INFORMATION, 20210824
EST DAYS UNTIL CP IMPACT:
NOTE: THE RFI SYSTEM IS INTENDED TO PROVIDE AN EFFICIENT MECHANISM FOR RESPONDING TO CONTRACTOR'S REQUESTS FOR INFORMATION. IT DOES NOT PROVIDE AUTHORITY TO PROCEED WITH ADDITIONAL WORK. IF THE CONTRACTOR CONSIDERS THE RFI RESPONSE A CHANGED CONDITION, PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER'S REPRESENTATIVE IN ACCORDANCE WITH CONTRACT PROVISIONS.
| CONTRACT NO: |
| CONTRACT TITLE: |
| RFI SUBJECT: |
| DWG NO: |
| SPEC PARAGRAPH: |
| DWG DETAIL: |
| SPEC PAGE NO: |
| DWG SHEET NO: |
| ACTIVITY ID: |
| Date: |
| Priority: Off |
| Time/Cost: Off |
| Schedule: Off |
| Critical Path: Off |
| Reviewer Solution: |
| Approving Autority Date: |
| Approving Autority Name: |
| Approving Autority Title: |
| Reviewer Date: |
| Reviewer Name: |
| Reviwer Title: |
| Cotnractor Name: |
| Contractor Date: |
| Contractor Title: |
| Contractor Solution: |
| Contractor Question: |
| RFI NO: |
| SPEC SECTION: |
| DAYS TO IMPACT: |
| Approving Autority Response: |