Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf

PDF 1 MB Posted

Attached to
JB Charleston Multiple Award Construction Contract
Solicitation number
FA441826R0009
Issued by

About this file

REQUEST FOR INFORMATION (RFI) FORM

This is a standardized Request for Information template used in federal contracting to facilitate efficient communication between contractors and government officials regarding contract clarifications. The form is designed for JB CHS contracts and was last updated on August 24, 2021.

The form is structured in three main sections. Section I captures contractor information and allows the contractor to submit questions or issues related to the contract, with fields for the contractor name, quality control manager signature, and date. The section also includes checkboxes for priority level (High/Normal), potential time and cost impacts, schedule impacts, and critical path impacts, with an estimated days until critical path impact field. Additionally, contractors may propose solutions to their identified issues. Section II designates space for the RFI reviewer to document their recommended response, including reviewer title, name, signature, and date. Section III provides the space for the government official's final RFI response, with fields for the government official's title, name, signature, and date. The form also includes fields for cross-referencing relevant contract documents such as drawings, specification sections, paragraphs, and page numbers. A critical disclaimer notes that the RFI system does not authorize additional work and requires contractors to provide written notice to the Contracting Officer's Representative if the RFI response constitutes a changed condition under contract provisions.

View the file

Other files

File Type Posted
Solicitation Amendment FA441826R00090004.pdf PDF
Statement of Work - JBLG Rev01.pdf PDF
Solicitation Amendment FA441826R00090003.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings_20260918.pdf PDF
Solicitation Amendment - FA441826R00090002.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings.pdf PDF
Solicitation Attachment - B466 Mechanical RFIs.pdf PDF
Attachment YU - Seed Project Schedule B.pdf PDF
Solicitation Attachment - Wage Determination SC20260030 - Sumter County.pdf PDF
Solicitation Attachment - Pre-Proposal Conference Slides 2026.pptx PPTX presentation
Solicitation Attachment - Geotechnical Report 14 April 2025.pdf PDF
B464 Photos.pdf PDF
Attachment XT - JB Charleston Question and Answer Form (Completed).xlsx XLSX spreadsheet
Solicitation Attachment - Site Visit Sign-In Sheet.pdf PDF
Solicitation Attachment - Wage Determination SC20260023 - Charleston County.pdf PDF
Solicitation Attachment - Salvage Storage List.docx DOCX document
Solicitation Attachment YS Seed Project Specifications_Mark Up.pdf PDF
Solicitation Attachment - Wage Determination NC20260012 - Wayne County.pdf PDF
Solicitation Attachment - Wage Determination SC20260022 - Berkeley County.pdf PDF
B466 Photos.pdf PDF
Solicitation Attachment - Hydrant Flow Test Data.pdf PDF
Solicitation Amendment FA441826R00090001.pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A_E).pdf PDF
Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx DOCX document
Solicitation - FA441826R0009.pdf PDF
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx XLSX spreadsheet
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.xlsx XLSX spreadsheet
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf PDF
Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf PDF
Solicitation Attachment XV - Past Performance Survey.pdf PDF
Solicitation Attachment YS Seed Project Specifications.pdf PDF
Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx DOCX document
Solicitation Attachment XZ - Past Performance Project List.xlsx XLSX spreadsheet
Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx DOCX document
Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx DOCX document
Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx XLSX spreadsheet
Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx DOCX document
Solicitation Attachment YT Seed Project Drawings.pdf PDF
Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx DOCX document
Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf PDF
Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx DOCX document
Statement of Work - Attachment 14 - 01 35 26 - Attachment A Accident Investigation (CIRS).pdf PDF
Statement of Work - JB CHS MACC.pdf PDF
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.pdf PDF
Solicitation Attachment XY - On and Off-Ramp Procedures (1).pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf PDF
Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx DOCX document
Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf PDF
Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule-Pay Calendar Example 2.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION DATEACTIVITY ID

CONTRACT TITLECONTRACT NO RFI NO

RFI SUBJECT DWG NO

DWG DETAIL

DWG SHEET NO

SPEC SECTION

SPEC PARAGRAPH

SPEC PAGE NO

RFI PRIORITY?

POTENTIAL TIME/COST IMPACT?

SCHEDULE IMPACT?

CRITICAL PATH IMPACT?

HIGH NORMAL

YES NO

YES NO

YES NO

CONTRACTOR PROPOSED SOLUTION: (Reference All Attachments)

REVIEWER RECOMMENDED RFI RESPONSE:

CONTRACTOR QUESTION/ISSUE: (Reference All Attachments)

SECTION III - RFI RESPONSE

SECTION I - CONTRACTOR INFORMATION

SECTION II - RFI REVIEWER

DATENAME NAME OF GOVERNMENT OFFICIAL SIGNATURE SIGNATURE OF OF GOVERNMENT OFFICIALTITLE OF GOVERNMENT OFFICIAL DATE

NAME OF REVIEWER SIGNATURE OF REVIEWERTITLE OF REVIEWER DATE

NAME OF QC MANAGER SIGNATURE OF QC MANAGERNAME OF CONTRACTOR DATE

JB CHS REQUEST FOR INFORMATION, 20210824

EST DAYS UNTIL CP IMPACT:

NOTE: THE RFI SYSTEM IS INTENDED TO PROVIDE AN EFFICIENT MECHANISM FOR RESPONDING TO CONTRACTOR'S REQUESTS FOR INFORMATION. IT DOES NOT PROVIDE AUTHORITY TO PROCEED WITH ADDITIONAL WORK. IF THE CONTRACTOR CONSIDERS THE RFI RESPONSE A CHANGED CONDITION, PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER'S REPRESENTATIVE IN ACCORDANCE WITH CONTRACT PROVISIONS.

CONTRACT NO:
CONTRACT TITLE:
RFI SUBJECT:
DWG NO:
SPEC PARAGRAPH:
DWG DETAIL:
SPEC PAGE NO:
DWG SHEET NO:
ACTIVITY ID:
Date:
Priority: Off
Time/Cost: Off
Schedule: Off
Critical Path: Off
Reviewer Solution:
Approving Autority Date:
Approving Autority Name:
Approving Autority Title:
Reviewer Date:
Reviewer Name:
Reviwer Title:
Cotnractor Name:
Contractor Date:
Contractor Title:
Contractor Solution:
Contractor Question:
RFI NO:
SPEC SECTION:
DAYS TO IMPACT:
Approving Autority Response: