This is a pre-proposal conference presentation for the Joint Base Charleston Multiple Award Construction Contract (MACC), solicitation FA441826R0009, issued by the Department of the Air Force Air Mobility Command. The presentation highlights key aspects of the solicitation but does not constitute contractual requirements. The MACC is a competitive HUBZone and SDVOSB business set-aside using trade-off procedures with an overall capacity of $400 million over 5.5 years (12-month base plus four one-year options and one six-month option). The contract supports construction programs at Joint Base Charleston in South Carolina and will provide emergency support to Shaw AFB and Seymour Johnson AFB in North Carolina. Task orders are anticipated to range from $3,000 to $30 million, with the majority between $1 million and $10 million. The government projects awarding up to six primary contractors and identifying up to three on-ramp contractors. Work includes new construction, alterations, repairs, demolitions, design-build projects, and utility infrastructure work at multiple simultaneous locations.

The presentation identifies evaluation criteria and contractor performance expectations. Price proposals will be evaluated first, followed by past performance, with nine offerors receiving substantial confidence ratings to move forward. Offerors must submit responsive proposals for 75 percent of task order requests over a twelve-month period to remain on the contract, with mandatory site visits for individual task orders unless otherwise noted. Site visit attendance is required or proposals become non-responsive. The presentation covers the seed project (Repair Dormitory B.464), which exceeds $10 million in estimated cost and includes interior renovations, system replacements, seismic upgrades, and a 450-calendar-day completion schedule. Questions were due August 20, 2026, with answers posted by August 27, 2026. The proposal due date was extended to October 14, 2026 via Amendment 002.

View the file

Other files

File Type Posted
Solicitation Amendment FA441826R00090003.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings_20260918.pdf PDF
Solicitation Amendment - FA441826R00090002.pdf PDF
Attachment YU - Seed Project Schedule B.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings.pdf PDF
Solicitation Attachment - Salvage Storage List.docx DOCX document
Solicitation Attachment - Site Visit Sign-In Sheet.pdf PDF
Attachment XT - JB Charleston Question and Answer Form (Completed).xlsx XLSX spreadsheet
B466 Photos.pdf PDF
Solicitation Attachment - Wage Determination NC20260012 - Wayne County.pdf PDF
Solicitation Attachment - Wage Determination SC20260022 - Berkeley County.pdf PDF
Solicitation Attachment - Hydrant Flow Test Data.pdf PDF
B464 Photos.pdf PDF
Solicitation Attachment - Wage Determination SC20260030 - Sumter County.pdf PDF
Solicitation Attachment - Wage Determination SC20260023 - Charleston County.pdf PDF
Solicitation Attachment - B466 Mechanical RFIs.pdf PDF
Solicitation Attachment - Geotechnical Report 14 April 2025.pdf PDF
Solicitation Attachment YS Seed Project Specifications_Mark Up.pdf PDF
Solicitation Amendment FA441826R00090001.pdf PDF
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.pdf PDF
Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx XLSX spreadsheet
Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx DOCX document
Statement of Work - Attachment 14 - 01 35 26 - Attachment A Accident Investigation (CIRS).pdf PDF
Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf PDF
Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx DOCX document
Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx DOCX document
Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx DOCX document
Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf PDF
Statement of Work - JB CHS MACC.pdf PDF
Solicitation Attachment YT Seed Project Drawings.pdf PDF
Solicitation Attachment YS Seed Project Specifications.pdf PDF
Solicitation Attachment XY - On and Off-Ramp Procedures (1).pdf PDF
Solicitation Attachment XV - Past Performance Survey.pdf PDF
Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf PDF
Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx DOCX document
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf PDF
Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx DOCX document
Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A_E).pdf PDF
Solicitation - FA441826R0009.pdf PDF
Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 9 - 01 33 00 - Attachment A - JB CHS Transmittal Form 4025.pdf PDF
Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule-Pay Calendar Example 2.xlsx XLSX spreadsheet
Statement of Work - Attachment 6 - 01 32 00 - Attachment A - Schedule- Pay Calendar Example 1.pdf PDF
Solicitation Attachment XZ - Past Performance Project List.xlsx XLSX spreadsheet
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.xlsx XLSX spreadsheet
Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Joint Base Charleston Multiple Award Construction Contract (MACC) Pre-Proposal Conference 06 Aug 2026

Thank you for attending!

Please sign in

Mission Ready Warfighters Deterring Conflict…TOGETHER!

Please Note This is not a solicitation document. This document is provided to highlight certain aspects of the solicitation. All contractual requirements can be found within the solicitation sections and the appropriate attachments.

Overview General Information Regarding JB Charleston’s MACC On and Off Ramp Considerations Proposal Information Evaluation Information Teaming Arrangements & Joint Ventures Seed Project, B464 Information Continue to Seed Project, B464 Site Visit

General Information Summary of Solicitation Documents Solicitation FA441826R0009 Solicitation Attachments XT - YT Solicitation Schedule B – JB CHS MACC – Seed Statement of Work – JB CHS MACC Statement of Work – Attachments 1 & 2 Statement of Work – Attachments 3 -17

Design Build Sample Division 01 Specifications Provided for Future T.O.’s Provided for Future T.O.’s For Seed Project Only For Overall MACC Information

(Ref. Section H): All Questions due 20 Aug at 1400.

Please utilize the Question and Answer Form (Solicitation Attachment XT)

(Ref. Section M): Up to 6 Awarded & 3 On-Ramp Identified Contractors

(Ref. Section B, Overall): $400M Overall Capacity

(Ref. Section B, Overall): 5-1/2 Years 12 Month Base, (4-Ea) Option Years, (1-Ea) 6 Month Option

(Ref. Section H): Task Orders (TO) = $3K - $30M, Majority = $1M - $10M

(Ref. Section C): Shaw AFB (SC) & Seymour Johnson AFB (NC) General Information

8/6/2026

Work Load Estimate (Ref. Attachment XW)

JB Charleston Multiple Award Construction Contract (MACC)
Work Load Estimate
Fiscal YearPossible TO Rough Order of Magnitude Cost/Number
<$1M$1M - $5M$5M - $10M>$10M
FY2711032
FY280313
FY290305
FY303922
FY312613

*Numbers provided are projections only based on data currently available and contingent on availability of future funds.

The Government may off-ramp a contractor for reasons below:

Failure to submit responsive proposals on 75% of task order proposal requests over a twelve (12) month period of performance.

(Ref. Section L) - Site visits for individual TOs will be mandatory for MACC contractors unless otherwise noted in the Task Order Proposal Request (TOPR). If a contractor chooses not to attend the site visit for a specific TO, that contractor’s proposal for the TO will be considered non-responsive.

Late performance of TO workload = prolonged startup, completing TOs late, or being assessed LDs on TOs.

Inability of prime or subcontractors performing work to maintain proper certification(s).

Poor TO performance as evidenced by CO notification or CPARS ratings under “Satisfactory.”

Unresponsiveness to warranty work.

Failure to provide responsive (72 hrs.) customer service. Maximum of five (5) occurrences over a twelve (12) month period.

Unsafe site conditions resulting in an OSHA discrepancy.

The Government may identify up to three (3) On-Ramp IDIQ contractors, with effective dates To Be Determined (TBD).

On and Off Ramp Considerations (Ref. Attachment XY)

(Ref. Section L): Part I – Factor I = Seed Project – Price Proposal Section A – SF 1442 Rpr Dormitory – B.464 (> $10M ROM) Complete Section B (Seed) - Schedule B for Price Information Complete the necessary fill-ins and certifications in Sections I through K. Section K shall be returned in its entirety. For Sections C through I, the Offeror shall submit only those pages that require a fill-in.

(Ref. Section L): Part II – Factor II = Past Performance Information (50 page limitation) Complete Attachment XZ – Past Performance Project List as a Cover Sheet Quality and Satisfaction Ratings – Letters, metrics, customer surveys, independent surveys, etc.

Complete Attachment XV – Past Performance Surveys for each individual project No more than 15 Projects within the last 5 years:

(No more than 2) Design-Build projects (No more than 10) Existing facility whole building renovation projects (No more than 5) Utility infrastructure repair or construction projects Attachment XU – Past Performance Customer Questionnaires (do not count toward page limitation.)

Proposal Information

(Ref. Section L) - If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. (Note: Clients are highly encouraged to submit questionnaires directly to the Offeror. However, if the client requests, questionnaires may be submitted directly to the Government's Point of Contact, robert.melton.6@us.af.mil.

8/6/2026

(Ref. Section M): Price Evaluation (1st Step) Reasonableness of an Offeror’s price and balance of an offeror’s CLIN structure [Seed – B464] All offerors will be sorted, in ascending order, by Price.

(Ref. Section M): Past Performance Evaluation (2nd Step) Recency: One (1) day of performance occurred within five (5) years of the release of the solicitation.

Relevancy:

Occurred within SBA Region IV (SE Region) – AL, FL, GA, KY, MS, NC, SC, TN Contracts with a preponderance of work associated with existing facility whole building renovation work involving Mechanical, Electrical, Plumbing, Fire Protection, Building Envelope and other systems, and with values equaling or exceeding $1M-$30M.

Contracts with a preponderance of work associated with Water, Wastewater, or Electrical utility infrastructure, and with values equaling or exceeding $1M-$30M.

Design Build contracts with a preponderance of work associated with existing facility whole building renovation work and/or utility infrastructure work with values equaling or exceeding $1M-$30M.

Offerors will receive an integrated performance confidence assessment rating. Past Performance evaluations will continue in ascending order of Price until nine (9) offerors rated with Substantial Confidence or all offerors have been evaluated, whichever comes first.

Evaluation Information

Past Performance Relevancy Rating (assigned to each past performance project)

Performance Confidence Assessment (assigned to each evaluated offeror)

(Ref. Section L): The offeror must provide complete information as to the arrangement, including identifying the responsibilities of each entity, and the contractual relationships and authorities of the firms involved. The offeror should provide a list of any relevant and recent past/present performance information on previous teaming arrangements or joint ventures with the same teaming or joint venture partner. Joint ventures must align with the current guidance provided by the Small Business Administration (SBA).

The offeror shall submit a consent letter executed by each teaming partner and/or joint venture partner authorizing the release of adverse past performance information to the offeror. Provide with the proposal a letter from all subcontractors that will perform major or critical aspects of the requirement, consenting to the release of their Past Performance information to the prime contractor.

(Ref. Section M): Consideration will be given to the entity that performed the work. Past performance of the offeror will have a greater weight than past performance of other business entities or personnel. Demonstration of previous working relationships with the proposed entity will have a greater weight than a new relationship. Teaming partners supported by written agreements will have a greater weight than partners with no written agreement.

Teaming Arrangements & Joint Ventures

(Ref. 01 11 00, para 1.1.1) –The work includes, but is not limited to, interior renovations, window replacement, door replacement, HVAC system replacement, plumbing improvements, fire alarm system replacement, fire suppression system improvements, emergency replacement, interior lighting replacement, electrical improvements. Seismic upgrades include, but are not limited to, foundation improvements, shear wall additions and other improvements.

(Ref. Block 11 of SF 1442) – 450 Calendar Days after Notice to Proceed (NTP) (Ref. 01 30 00, para 1.6.1) – One (1) Superintendent required (Ref. 01 45 00, para 3.2.5.1) – One (1) QC Manager required (Ref. 01 35 26, para 1.5.1.1) – One (1) Site Safety and Health Officer (SSHO) required (Ref. 01 35 26, para 1.5.1.2) – QC Manager can be the SSHO, if dual qualified (Ref. 01 32 00, para 3.2) – Cost Loaded CPM Schedule due 30 Days after TO Award.

(Ref. 01 45 00, para 3.2.4.c) – Contractor Code Compliance Affidavit’s required for HVAC, Electrical, Lightning Protection, Fire Protection, & Plumbing trades.

(Ref. 01 45 35) – Special Inspections Required (Ref. 01 91 00.15 10) – Total Building Commissioning Required Seed Project Information Rpr Dormitory – B.464