Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx
XLSX spreadsheet 297 KB Posted
- Solicitation number
- FA441826R0009
About this file
This is a Submittal Register template (Form 4288-R) used to track and manage construction submittals for the JB Charleston Multiple Award Construction Contract (MACC) under contract number FA4418-XX-X-XXXX. The form serves as an administrative tool for organizing and documenting the submission, review, and approval of various construction-related documents and materials throughout the project lifecycle.
The register is designed to track eleven categories of submittals: preconstruction items, shop drawings, product data, samples, design data, test reports, certificates, manufacturer's instructions, manufacturer's field reports, operation and maintenance data, and closeout documentation. Each submittal entry captures critical information including the transmittal number, specification section reference, description of the item, submittal type code, classification code (FIO, GA, DA, CR, DA/CR, DA/GA), CPM schedule activity identification, submission dates, government action codes, approval timelines, and material delivery requirements. The three example entries provided reference utility outage requests, road closure requests, and Air Force Work Clearance Permits, indicating the types of preconstruction administrative submittals contractors must prepare and submit for government approval before commencing work at Joint Base Charleston locations.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register SUBMITTAL REGISTER JB CHS ENG FORM 4288-R Contract No. Contract No.: FA4418-XX-X-XXXX
| Project Title and Location | Contractor | ||||||||||||||||||||||||
| Transmittal No | Item No | Specification Section or Drawing Sheet Reference | Specification Paragraph Number | Description of Submittal Item | Submittal Type Code | Classification Code | Contractor Schedule Dates | Contractor Action | Government Action | Remarks | |||||||||||||||
| SD-01 - Preconstruction | SD-02 - Shop Drawings | SD-03 - Product Data | SD-04 - Samples | SD-05 - Design Data | SD-06 - Test Reports | SD-07 - Certificates | SD-08 - Manufacturer's Instructions | SD-09 - Manufacturer's Field Reports | SD-10 - O&M Data | SD-11 - Closeout | FIO, GA, DA, CR, DA/CR, DA/GA | CPM Schedule Activity ID | Sumbit By | Approval Needed By | Material Needed By | Date Submitted to Government | Government Action Code | Date Returned | Government Review Time | ||||||
| a. | b. | c. | d. | e. | f. | g. | h. | i. | j. | k. | l. | m. | n. | o. | p. | q. | r. | s. | t. | u. | v. | w. | x. | y. | z. |
| 1 | 01 11 00 | 1.6.2 | Utility Outage Requests | X | 0 | N/A | |||||||||||||||||||
| 2 | 01 11 00 | 1.6.2 | Road Closure Requests | X | 0 | N/A | |||||||||||||||||||
| 3 | 01 11 00 | 1.6 | Air Force Work Clearance Permit | X | 0 | N/A |
JB CHS ENG FORM 4288-R, JUN 2021 Page &P of &N