| Question | Answer | |
| 1 | Concerning J-5 Attachment 5 Pricing Tables, tab 5. Prices. We noticed that some of the Key labor categories are listed as .5 per year positions. Is it INL’s intent that the PSO Director, Business Operations (Business Analyst), Enterprise Architect and Procurement Manager (Contracts) are proposed as part time positions? | No, it is not the intent that these positions are part time. Attachment 5, Pricing Tables, are updated via Amendment 001 to reflect 1 FTE. |
| 2 | Is it INL’s expectations that these Key personnel work in Melbourne or can they work out of the contractor’s office? | The Government will have space available as outlined in Section H-6. The Contractor may choose to utilize this space or its own office space. |
| A. If Key Personnel can work out of the contractor’s office space is there a defined distance or time frame between the contractor’s facility and Patrick AFB? | The Contractor should be available to meet with INL/A within one hour of being notified. | |
| B. Is telecommuting an option with the understanding Key Personnel are on call and should be available for meetings at Patrick AFB? | Yes, telecommuting is an option as long as acceptable quality levels are met. |
3 J-5 Attachment 5 Pricing Tables FINAL, Tab 5 Lines 64/65 indicates 8 positions for Country Site Manager and 7 Positions for FOL Site Manager, however the PWS only indicates 5 countries and 4 FOLS please clarify if this in error or the government expects us to employ a minimum of 8 Country Site Managers for the 5 locations? Attachment 5, Pricing Tables, is updated via Amendment 001 to clarify.
4 "Under Section H-005 Export-Controlled Items (APR 2010), "the Contractor shall comply with all applicable laws and regulations regarding export-controlled items, including, but not limited to, the requirement for contractors to register with the Department of State in accordance with the ITAR." Considering this, could you please confirm whether the PSO Prime Contractor or a team member must be registered with the Directorate of Defense Trade Controls (DDTC) or be able to perform this function at the proper time? The PSO Prime Contractor does not have to be registered with the DDTC in order to comply with its oversight responsibilites. All import and export duties fall under the responsibility of the Logistics contractor. However, it needs to have the expertise and procedural knowledge to effectively ensure we are in full compliance with all the DDTC mandates.
5 In 8.1, the RFP says that the offeror can use Power Point slides during Orals. Can the offeror use a video to help explain a system that it wants to implement so the panel can understand the process? A video presentation is acceptable to help explain a system that it wants to implement.
6 Will the PSO contractor be responsible for placing individuals in each country cited in the RFP? Yes, the PSO contractor will be responsible for placing PSO individuals in each country cited in the RFP.
7 I understand that under Section H-005 Export-Controlled Items (APR 2010), "the Contractor shall comply with all applicable laws and regulations regarding export-controlled items, including, but not limited to, the requirement for contractors to register with the Department of State in accordance with the ITAR." In the Questions and Answers summary, dated 10-15-2013, the question of whether the PSO (Prime) would have export compliance oversight responsibilities over subcontractors (associated contracts) was answered in the affirmative. However, could you please confirm whether the PSO Prime Contractor must be registered with the Directorate of Defense Trade Controls (DDTC). The PSO Prime Contractor does not have to be registered with the DDTC in order to comply with its oversight responsibilites. All import and export duties fall under the responsibility of the Logistics contractor. However, it needs to have the expertise and procedural knowledge to effectively ensure we are in full compliance with all the DDTC mandates.
| Discussion: The document “SAQMMA13R0044”, paragraph 2.2.2, page 112 of 152 states, “The Key Personnel commitment letter requirement to provide the key person’s proposed salary and a summary description of any benefits packages that have been offered to the key person; and, The Total Compensation Plan, as described in FAR 52.222-46 (Evaluation of Compensation for Professional Employees), which shall be submitted in Volume VI, Section F.” On page 146 of 152, under Factor 5, the requirements for the commitment letter state, “Provide a commitment letter for each proposed key person.The commitment letter will include the following: The name of the key person; The position to be occupied by the key person; A narrative statement that specifies the key person’s commitment to the contract which will include the duration, degree and breadth of the key person’s commitment. The key person and offeror will sign and date the commitment letter.” | ||
| 8 | Question: The requirements for the Commitment Letter are different. Should we following the guidance on page 112 or on page 146? | Follow the guidance of Factor 5 for designated Key Personnel and the format of FAR 52.222-46 for other non-key Professional Personnel. |
| Discussion: The document “SAQMMA13R0044”, paragraph 2.2.2, page 9 of 152 states, “Five SAIDIQ contracts will be competed concurrently to support the Department of State’s Worldwide Aviation Mission.The solicitations are: SAQMMA13R0044 Aviation Program Support Services; SAQMMA13R0390 Aviation Maintenance Services; SAQMMA13R0391 Aviation Flight Operations Services; SAQMMA13R0392 Aviation Logistics Services; SAQMMA13R0393Aviation Information Technology Services.” Paragraph “Associate Contracts”, page 25 of 152 states, “The Safety Compliance contract will be an IDIQ type support contract to conduct independent, third party inspections at the request of USG. They may be tasked to support in safety related training or testing activities. They are independent of the daily working of the INL/A Safety Program, which is run by the PSO and associate contractors as a daily routine.” | ||
| 9 | Question: Will the Associate Contracts include a separate Safety contract as shown on page 25? | Yes, a separate Safety Compliance contract will be issued in the Spring of 2014. |
| Discussion: In document J-11 PSO Table Minimum Qualifications 11.2.13, a requirement for the Safety Project Manager and Safety Specialist is “FAA Commercial and Instrument Airman’s Certificate (Any category or class).” | ||
| 10 | Question: Can a FAA Airman's Certificate (pilot) or equivalent military certification / rating be substituted for a Commercial Instrument License? | Yes, Attachment J-11 is updated via Amendment 001 |
| Discussion: The document “SAQMMA13R0044”, Table 2.2, page 109 of 152 states that Volume 2 has a 50 page limit and includes several non-counted pages. Paragraph 4.1, page 112 of 152 states “4.1 Volume II shall have a strict limit of 50 numbered pages, except where volume title indicates “not counted” in table 2.2. Number all 50 pages sequentially, represented as 1 of 50, 2 of 50, etc.” However, the proposal organization specifies in Table 2.2 that that non-counted pages be include in Volume 2 and implies that the non-counted pages be interspersed within the counted page sections. | ||
| 11 | Question: Is it permissible to separate the “counted” and “non-counted” pages in Volume 2 with references in the counted pages to the location/attachment number of the non-counted pages, all provided inside Volume 2? | No. Please number Volume 2 sequentially and comply with the count limit. |
| 12 | The PWS states that it’s a draft, is there another “Final” being released? | No this is the final version. However, Amendment 0001 will publish an updated MSWord version of the PWS to reflect changes noted in this Q&A document. |
| 13 | If it’s the intent of the government to not provide work in office locations at PAFB for all PSO personnel, should the cost be factored into indirect costs or ODCs? | The Government has limited available space for contractor use. Therefore, the contractor should factor costs for office space. |
14 Section 3.c.6.b states both bi-monthly and then contradicts itself by stating monthly safety inspections, which one is correct? The correct frequency is monthly. The PWS is updated and will be posted via Amendment 001
15 Section 3.c.6.g, providing Stage I and II IS-BAO Certification will require considerable program-wide investment, in time, money and documentation, will this be a Government ODC cost and/or funded under a Task Order? The effort will be proposed by the contractor as part of their proposal to attain the desired levels of certification as outlined in the PWS.
16 Sections 7.f.1.b, and 8.f.1.b, these SOR requirements are written for Colombia, what is the PSO responsibility of the PSO at FOLs? 7.f.1.b is deleted and 8.f.1.b is updated to reflect operations in Afghanistan. The PWS is updated and will be provided via Amendment 001.
| Section H-016 in the PWS contains the following table which specifies key personnel: | ||
| 17 | J-5_Attachment 5, Tabs 4 and 5 specify the Labor Categories the government wishes the offerors to bid. In comparing the above table and the Tabs in the pricing sheets there is a disconnect. For example the above table specifies the following Labor Categories: Contracts Manager, Operations Manager and Site/Program Manager; however these three Labor Categories are not reflected in Tabs 4 and 5 on the pricing table. Please clarify. | Section J, Attachments 5 and 11 are updated via Amendment 001. |
18 Table 2.2, Proposal Organization lists the specific sections of each Volume. With regards to Volume VI, Business, the following sections are required: Business Proposal, requires the following information, however these requirements are not reflected in table 2.2 above. Please clarify the government’s intent for the content of this volume. Sections 9.1 - 9.6. Sections 9.1 - 9.6 should be submitted in Section D - Company Information.
19 Section 2.2.2, Cost or Pricing Information states the requirement for a Total Compensation Plan, Section L does not include instructions to provide Compensation Plan under Volume VI, please clarify the requirement to provide a Compensation Plan and please define any required contents. Total Compensation Plan should be submitted under Section F, "Additional Contractor Plans
20 Section 3.c.2.c, If chosen as the QASP SW solution, will SEESOR.net continue to be GFE; if not will a replacement or alternative solution be GFE or an ODC? SeeSOR.net will not be provided as GFE. The QASP SW solution should be priced as an ODC.
21 Please clarify the requirement for having more than one specialized degree for the Safety Officer and Safety Project Manager. This would indicate these positions would require a Masters plus an MBA or PhD. Please clarify the requirement for having a bachelor’s degree in Quality Management or Quality Assurance. These types of degrees don’t exist. A person can earn a minor in these specialties such as a Bachelor’s degree in Aviation Management with a minor in Quality Assurance. Section J, Attachment 11 is updated via Amendment 001 to clarify.
22 In the PWS, Page, 116, Factor 3, the requirement is to “Submit a sample IMS which identifies the three (3) most critical projects among your requirements”. Two paragraphs below this requirement in the same block, the government asks “Beyond those three (3) critical elements, identify…” Are these three elements referring to the 3 critical projects in the first paragraph? Yes, these three elements refer to the 3 critical projects in the first paragraph.