S02 Sol R0036 AttE SOW.Att10_Infection Control Barrier Sample.pdf

PDF 2 MB Posted

Attached to
Z1DA--578-25-003 Renovate Elevators B200 (Construction) at the Hines VA Hospital in Hines, IL
Solicitation number
36C25225R0036_3
Issued by

About this file

The images show a detailed setup for infection control and pressure monitoring in a construction area, likely part of a renovation project at a VA hospital. The first image depicts a door with safety signage, including "Construction Area Keep Out" and "Hard Hat Area" warnings, along with various labeled documents and a manometer showing a pressure reading of -0.045.

The second and third images show a Dwyer DigiMag digital pressure gauge installed on an edge guard. The description indicates the device is connected to the positive side to provide accurate room pressure readings, with instructions that the HEPA filter machine should be blowing out of the room. This suggests a carefully controlled environment to maintain negative air pressure and prevent the spread of contaminants during medical facility construction, which is critical for infection control during renovation work.

View the file

Other files

File Type Posted
36C25225R0036 0007.docx DOCX document
S06 36C25225R0036 006_Att04 _ Wage Rates IL20250009.R3 2025.08.01.pdf PDF
36C25225R0036 0006.docx DOCX document
S06 36C25225R0036 006_Att02 25-0725 Supplemental Sketches.pdf PDF
BLDG200F14R2010.xls XLS spreadsheet
BLDG200F5R2010.xls XLS spreadsheet
BLDG200F2R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att08 GKT15-30W-10_Specification.pdf PDF
BLDG200F1R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att09 Hines State Tax Exempt 2025.pdf PDF
BLDG200F4R2010.xls XLS spreadsheet
BLDG200F11R2010.xls XLS spreadsheet
S06 36C25225R0036 006_Att05 Physical Access Control Clarifications.pdf PDF
BLDG200F9R2010.xls XLS spreadsheet
BLDG200 F10R2010.xls XLS spreadsheet
BLDG200F3R2010.xls XLS spreadsheet
S06 36C25225R0036 0005.pdf PDF
S06 36C25225R0036 0005.docx DOCX document
S06 36C25225R0036 004 578-25-003_Att Finish Schedule.pdf PDF
S06 36C25225R0036 002 578-25-003.docx DOCX document
S06 36C25225R0036 002 Att1 Sign-in Site Visit_01.pdf PDF
S06 36C25225R0036 002 Att2 Sign-in Site Visit_02.pdf PDF
36C25225R0036 0001.docx DOCX document
S06 001 Att1 Sign-in Site Visit_01 for 578-25-003 Elevators 2025.06.18.pdf PDF
36C25225R0036_3.docx DOCX document
S02 Sol R0036 AttE SOW.Att16_578-25-003 Basis of Design Existing Condition Photos 2024.11.04.pdf PDF
S02 Sol R0036 AttE SOW.Att14b _578-25-003_Replace Elevators B200_SPECS VOL 2of 2_updated.pdf PDF
S02 Sol R0036 AttE SOW.Att17_Building 200 Elevator Study Existing Condition Photos.pdf PDF
S02 Sol R0036 AttE SOW.Att18a_Building 200 Colored Space Drawings.pdf PDF
S02 Sol R0036 AttE SOW.Att15b_578-25-003 100 perc DWGS_Part 2of5 2025.01.24.pdf PDF
S02 Sol R0036 AttE SOW.Att02_Contractor Parking.pdf PDF
S02 Sol R0036 AttE SOW.Att15c_578-25-003 100 perc DWGS Part 3of5_2025.01.24.pdf PDF
S02 Sol R0036 AttE SOW.Att18b_Building 220 Colored Space Drawings.pdf PDF
S02 Sol R0036 AttE SOW.Att05_Safety and Health During Construction Activities.pdf PDF
S02 Sol R0036 AttA VAAR 852.219-75 Certification 578-25-003.docx DOCX document
S02 Sol R0036 AttH Past Performance Client Questionnaire 578-25-003.pdf PDF
S02 Sol R0036 AttE SOW.Att15e_578-25-003 100 perc DWGS Part 5of5_2025.01.24.pdf PDF
S02 Sol R0036 AttI Wage Rates IL20250009.R3 2025.05.23 current as of 2025.06.05.pdf PDF
S02 Sol R0036 AttE SOW.Att00_Descriptive Project Scope of Work 578-25-003_r.pdf PDF
S02 Sol R0036 AttF SOW.Att19_Subcontractor Info Consent 578-25-003.pdf PDF
S02 Sol R0036 AttE SOW.Att08_Interim Life Safety Measures_ILSM.pdf PDF
S02 Sol R0036 AttB Contractor Info 578-25-003.docx DOCX document
S02 Sol R0036 AttG Brand Name or Equal_Basis of Design 578-25-003.xlsx XLSX spreadsheet
S02 Sol R0036 AttC Contractor EMR Safety Info 578-25-003.docx DOCX document
S02 Sol R0036 AttE SOW.Att04_No Smoking Policy 10-1-19.pdf PDF
36C25225R0036_3.docx DOCX document
S02 Sol R0036 AttE SOW.Att15a_578-25-003 100 perc DWGS_Part 1of5_2025.01.24.pdf PDF
S02 Sol R0036 AttE SOW.Att09_Infection Control Risk Assessment_ICRA-1.3.pdf PDF
S02 Sol R0036 AttE SOW.Att03_Emergency Contact List.pdf PDF
S02 Sol R0036 AttE SOW.Att14a _578-25-003_Replace Elevators B200_SPECS VOL 1of 2_updated.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHAHINDoyleL Text Box Entrance

VHAHINDoyleL Text Box Manometer

VHAHINDoyleL Text Box

ICRA

VHAHINDoyleL Text Box

PCRA

VHAHINDoyleL Text Box

ILSM

VHAHINDoyleL Text Box Sign-in

VHAHINDoyleL Line

VHAHINDoyleL Line

VHAHINDoyleL Line

VHAHINDoyleL Line

VHAHINDoyleL Line

VHAHINSidleB Image

VHAHINSidleB Text Box Dwyer DigiMag Installed on edge guard. Poly is connected to positive side (+) to give accurate reading of room pressure. Hepa filter machine should be blowing out of room.

VHAHINSidleB Image

File details come from the government source that posted it. Updated .