This scope of work document outlines facility renovation, improvement, and repair projects at the Woodlawn and Bath National Cemeteries. The projects include renovations to administrative buildings, maintenance buildings, maintenance yards, site work, and physical security upgrades at Woodlawn Cemetery, as well as renovations to an administrative building, paving work, replacement of a footbridge and bridge abutments at Bath Cemetery. Offerors are required to provide pricing breakdowns by work element for each cemetery as line items in their proposals. The construction contractor will be responsible for providing all labor, materials, tools, and equipment to complete the projects according to the specifications in the attached bid documents within 300 calendar days of notice to proceed. The solicitation was issued by the Department of Veterans Affairs National Cemetery Administration for the facility renovation projects at the two national cemeteries.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work (SOW) FY 20 Construction Projects
Woodlawn National Cemetery Facility Renovation, Improvements, and Repairs Project Number 824IC3005
Bath National Cemetery Facility Renovation, Improvements, and Repairs Project Number 803IC3015
Project Scope For Construction
Department of Veterans Affairs National Cemetery Administration Office of Construction Management June, 2020
1. GENERAL
1.1. This Scope of work (SOW) identifies the goal and objectives of this construction project.
1.2. The construction contractor shall provide all labor, materials, tools and equipment, and services necessary to construct this project per the construction documents and specifications.
1.3. The construction contractor shall be responsible for the quality and completeness of the construction project. Complete and accurate coordination between the trades and quality control of all sub-contractor’s work shall be required.
2. PROJECT GOAL
2.1. Woodlawn National Cemetery; Facility renovation, improvements and repairs per construction documents and specifications attached herewith.
2.2. Bath National Cemetery; Facility renovation, improvements and repairs per construction documents and specifications attached herewith.
3. BACKGROUND
3.1. Woodlawn National Cemetery is in Chemung County, N.Y. The address is 1825 Davis
Street, Elmira, NY.
3.2. Bath National Cemetery is located in Steuben County, N.Y. The address is San Juan Ave.
VA Medical Center, Bath, NY.
Woodlawn National Cemetery Aerial Photo
Bath National Cemetery
4. OPERATIONAL CONSIDERATIONS
4.1. Each national cemetery is managed by VA National Cemetery Administration (NCA) personnel in conformance with national and regional (North Atlantic District) policies, priorities, goals, and objectives. The functions of a national cemetery include the operation and maintenance of all aspects of the cemetery. Typically, this includes burial of veterans and eligible family members, the interment of cremated remains, and the placement and maintenance of a headstone or grave marker. Cemetery operations include the conduct of Memorial Day and other special ceremonies, as well as the care of graves, structures and grounds. Woodlawn and Bath National Cemeteries is operated and maintained by local NCA staff supervised by the cemetery director. Operating hours are Monday through Friday, 8:00 am – 4:30 pm. Closed federal holidays except Memorial Day and Veterans Day.
4.2. All work must take place during normal operating hours. Any request to work over these hours must be requested in writing and approved by Cemetery Director in conjunction with COR a minimum of 24hrs in advance. Also, the Cemetery hosts numerous ceremonies and events. Work that interferes with these ceremonies will cease during ceremonies. Notice will be provided by the Cemetery staff 5 days in advance of scheduled ceremonies whenever possible. Occasionally events are scheduled with less than 5 days’ notice in which case the Cemetery will provide as much notice as is possible.
4.3. Parking is limited. Construction staff vehicle parking areas are to be coordinated with the COR and cemetery director.
4.4. No smoking inside cemetery grounds.
4.5. Proper attire and professional conduct are required at all times.
4.6. All work must cease during the time an internment is taking place near the construction site.
Special care must be taken to accommodate visitors and to ensure work does not interfere with their visit and ensure that there are no safety hazards present.
5. ENVIRONMENTAL COMPLIANCE
5.1. Based upon Department of Veterans Affairs “Environmental Effects of VA Actions,” 38 CFR
Part 26, the Woodlawn and Bath Cemetery projects are “categorically excluded” from the need for environmental documentation, specifically Section 26.6 of said code paragraph (b)(2). The contractor shall not be responsible for environmental compliance under
NEPA.
6. HISTORIC COMPLIANCE
6.1. This project is located in the Woodlawn and Bath National Cemeteries, which are eligible for listing in the National Register of Historic Places (NRHP). The proposed scope of work for this project is subject to compliance with Section 106 of the National Historic Preservation Act (P.L. 89-665, as amended).
7. PROJECT SCOPE (Construction contract is to include all work associated with items 7.1 thru 7.10) VA NCA requires the offeror to submit a price breakdown in proposal cost detail for each scope of work element as listed below as a roll up under Contract Line Item 01 and Contract Line Item 02.
Contract line item 01; Woodlawn NC, project number 824IC3005
7.1. Work element 01, Woodlawn NC Administrative Building
7.2. Work element 02, Woodlawn NC Maintenance Building
7.3. Work element 03, Woodlawn NC Maintenance Yard
7.4. Work element 04, Woodlawn NC Site work
7.5. Work element 05, Woodlawn NC Physical Security at Confederate Monument and
Adjacent burial section
Contract Line Item 02; Bath NC, project number 803IC3015
7.6. Work element 06, Bath NC Administrative Building
7.7. Work element 07, Bath NC Paving Work
7.8. Work element 08, Bath NC New Footbridge
7.9. Work element 09, Bath NC Remove Old Bridge Abutments
7.10. Work element 10, Bath NC New Metal Storage Building to replace existing sheds
8. Government Provided Construction Document Package/Basis of Design/Bid
Set/Specifications;
8.1. The following bid documents are attached for your use.
8.1.1. Woodlawn 824IC3005
• 824IC3005 Bid Dwgs Woodlawn
• 824IC3005 Bid Specs Woodlawn
• 824IC3005 Geotech Woodlawn
8.1.2. Bath 803IC3015
• 803IC3015 Bid Dwgs Bath
• 803IC3015 Bid Specs Bath
• 803IC3015 Geotech Bath
8.2. Accessibility- All features of the project shall be accessible in compliance with the
Americans with Disabilities Act-1990, Architectural Barriers Act of 1968, as amended and local accessibility requirements. To achieve compliance, the National Cemetery Administration uses as its standard for building and facility design the ABA Accessibility Standard for Federal Facilities (ABAAS). The standards are found at the following URL:
http://www.access-board.gov/ada-aba/aba-standards-gsa.cfm. All aspects of compliance related to this project are to be discussed and exceptions may apply based on site conditions.
8.3. Design Criteria- See bid documents.
8.4. Construction Performance Schedule; 300 calendar days from notice to proceed.
Signed by Michael J. Borgman ____________________________________________ 6/11/2020 http://www.access-board.gov/ada-aba/aba-standards-gsa.cfm