This document contains a construction fire safety checklist attachment for a federal construction project. It outlines 53 fire safety requirements that must be followed under sections related to fire extinguishers, ignition hazards, indoor storage, flammable and combustible liquids, temporary heating devices, signs and barricades, welding and cutting, electrical safety, demolition, temporary buildings and trailers, and exit pathways. The related federal contract opportunity is for installing a fan array in an air handling unit and replacing exhaust fans at the James A. Haley Veterans Medical Center in Tampa, Florida. The solicitation number is 36C24823R0068 and the point of contact is listed as amy.shaw3@va.gov. The work is to be performed for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8.

View the file

Other files

File Type Posted
S05_RFI 3 Tracking Log 673_22_109 DB Install Fan Array AHU OR 2_7_Final.pdf PDF
36C24823R0068 0008.docx DOCX document
S04_Site Visit 2 Sign in.pdf PDF
36C24823R0068 0007.docx DOCX document
P01_SOW_PN 673_22_109_Change of Scope Revision.docx DOCX document
S02_RFP Attachment_INSTRUCTIONS TO OFFERORS_Install Fan Array_Updated.docx DOCX document
S05_RFI 2 Tracking Log 673_22_109 DB Install Fan Array AHU OR 2_7_Final.docx DOCX document
P09_SOW 673_22_109 FINAL_RFI 2 Revision.docx DOCX document
S02_RFP Attachment_EF Mech Dwg.pdf PDF
S02_RFP Attachment_EF Schedule.pdf PDF
S04_Site Walk 1 Sign In.pdf PDF
36C24823R0068 0006.docx DOCX document
S02_RFP Attachment_EF Electrical Dwg.pdf PDF
36C24823R0068 0005.docx DOCX document
36C24823R0068 0004.docx DOCX document
36C24823R0068 0003.docx DOCX document
S02_RFP Attachment_INSTRUCTIONS TO OFFERORS AND EVALUATION INFO_Install Fan Array_10Feb2023.docx DOCX document
S05_RFI Tracking Log 673_22_109 DB Install Fan Array AHU OR 2_7_Final.docx DOCX document
S02_RFP Attachment_Pages from 8_As_Built Drawings_Mechanicals.pdf PDF
36C24823R0068 0002.docx DOCX document
S02_RFP Attachment_Pages from 8_As_Built DrawingsAHU.pdf PDF
S02_RFP Attachment_23_74_13 Packaged Outdoor Central Station AHU REV.pdf PDF
P09_SOW 673_22_109 FINAL_RFI Revision.docx DOCX document
36C24823R0068 0001.docx DOCX document
Experience Information Sheet.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Adopted Codes General Requirements - Appendix B.pdf PDF
S02_RFP Attachment_VA 01 00 00 Safety and Infection Control Guide General Requirements - Appendix D.pdf PDF
S02_RFP Attachment_VA 01 00 00 Contractor Work Plan Peer Review General Requirements.pdf PDF
S02_RFP Attachment_SPEC 01 35 26_Safety Requirements 673-22-107.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Fire Safety Inspection Checklist for Hot Work General Requirements.pdf PDF
S02_RFP Attachment_Architectural - Bldg 1 second.pdf PDF
S02_RFP Attachment_DB Wage Rate FL20220208 dtd 09.09.22.txt TXT text file
S02_RFP Attachment_VA 01 00 00 Facility Management Alerts General Requirements - Appendix C.pdf PDF
S02_RFP Attachment_SPEC 23 05 11 Common Work for HVAC.pdf PDF
S02_RFP Attachment_INSTRUCTIONS TO OFFERORS AND EVALUATION INFORMATION_Install Fan Array.docx DOCX document
S02_RFP 36C24823R0068_Final.pdf PDF
S02_RFP Attachment_VA 01 00 00 Approved OSHA Training Providers List General Requirements - Appendix A.pdf PDF
S02_RFP Attachment_SPEC 23 05 93 Testing Adjusting and Balancing for HVAC.pdf PDF
S02_RFP Attachment_SPEC 01 00 00_General Requirements 673-22-107.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Sprinkler Work Notifications General Requirements - Attachment 1a and 1b.pdf PDF
S02_RFP Attachment_Price Matrix.xlsx XLSX spreadsheet
S02_RFP Attachment_OR Reno As Built Drawings.pdf PDF
S02_RFP Attachment_SPEC 01 45 00 Quality Control.pdf PDF
S02_RFP Attachment_EMR.pdf PDF
S02_RFP Attachment_SPEC 01 32 16 16_Network Analysis Schedule_Design-Build Only.docx DOCX document
S02_RFP Attachment_Existing Panel Schedules.pdf PDF
S02_RFP Attachment_VA 01 00 00 VA Information and Information System General Requirements - Attachment 6.pdf PDF
S02_RFP Attachment_SPEC 01 42 19 Reference Standards.pdf PDF
S02_RFP Attachment_SPEC 01 33 23_Shop Drawings 673-22-107.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Notification Of Hot Work General Requirements - Attachment 2.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 4

Construction Fire Safety Checklist

SECTION 01 00 00

GENERAL REQUIREMENTS

ATTACHMENT #4

CONSTRUCTION FIRE SAFETY CHECK LIST

(For protection of VA property, patients, visitors and personnel)

PROJECT No. & Title:

DATE:

A. FIRE EXTINGUISHERS (OSHA 1926.150[c])

(1) Extinguisher rated not less than 2A within 100 feet.

(2) Extinguisher rated not less than 10B within 50 feet, if flammable liquids or gases present.

B. IGNITION HAZARDS (OSHA 1926.1511[a])

(1) Internal combustion engines located away from combustibles.

(2) Smoking is prohibited in fire hazard areas (flammables, combustibles, etc.).

C. INDOOR STORAGE (OSHA 1926.151[d])

(1) Site kept free from accumulation of unnecessary combustibles.

(2) Storage shall not obstruct means of egress.

(3) Minimum clearance maintained around lights and heating units.

D. FLAMMABLE AND COMBUSTIBLE LIQUIDS (OSHA 1926.152)

(1) Stored in approved containers only.

(2) No storage in areas of exits, stairways or pedestrian traffic.

(3) Maximum in room storage of 25 gal., otherwise store in approved cabinet.

E. TEMPORARY HEATING DEVICES (OSHA 1926.154)

(1) Adequate ventilation for workmen and heater combustion.

(2) Minimum clearance (at least 3 feet) of combustibles from heaters.

(3) Stability of heater.

F. SIGNS AND BARRICADES (OSHA 1926.200)

(1) Danger signs where immediate hazards exist.

(2) Caution signs where potential hazards exist.

(3) Safety instruction signs, where necessary.

(4) Barricades to protect persons from hazards, where necessary.

G. WELDING AND CUTTING (NFPA-51B & OSHA 1910.252) - HOT WORK PERMIT

(1) Inspection of area before permit given.

(2) Minimum distance of 35 feet from combustibles.

(3) Properly rated fire extinguisher in immediate area.

Section 01 00 00, General Requirements – Attachment #4

Revised March 2018

(4) Wall and floor openings covered.

(5) No flammable liquids present.

(6) Inspection after work.

H. ELECTRICAL (OSHA 1924.400-2, 1926.302, & NFPA 241-4)

(1) All temporary wiring grounded and in accordance with National Electric Code (NEC).

(2) Precautions taken to make any open wiring inaccessible to other than authorized personnel.

(3) Temporary light bulbs equipped with guards, heavy duty cords, and not suspended by their cords (unless specifically designed for that use.)

(4) Runs of open conductors located away from possible damage and fastened at intervals of no greater than 10 feet.

(5) Outlets in construction sites have GFCI or assured equipment grounding.

(6) Extension cords protected from damage. No worn or frayed cables. Not hung from nails or suspended by wire.

(7) Fuses or circuit breaker provided for each feeder or branch circuit.

(8) Electrical powered operated hand tools shall either be of the approved double insulated type or properly grounded.

I. DEMOLITION (OSHA 1926.850-858 and NFPA 241 – Ch.7)

(1) Electric, gas, water, steam, etc. shut off prior to work.

(2) Any utilities that are necessary to be maintained need protection.

(3) Masonry walls shall not be permitted to fall on floors such that it would exceed the safe carrying capacity of the floor.

(4) Floor openings within 10 feet of any wall being demolished shall be planked solid except when no one below.

(5) The storage of waste material and debris shall not exceed the floor loading limit.

(6) Construction of dust barriers as needed (not OSHA).

(7) Notification of shut off and protect smoke detectors, etc. during day time only (not OSHA).

Coordinated with COTR.

(8) Precautions if floors are soaked with oil or flammable liquids, if dust accumulation is present or other combustibles a present and hot work is being performed.

(9) Smoking is prohibited throughout demolition (NFPA 241, 7-4, 2).

(10) Flammable and combustible liquids removed from area.

(11) Water supplies must be available from fire hydrants in the vicinity of the structure or area.

(12) Prior to demolition, asbestos abatement and breakables (i.e., glass) shall be removed.

Section 01 00 00, General Requirements – Attachment #4

J. TEMPORARY BUILDINGS, TRAILERS (NFPA 241, Ch.2)

(1) Temporary offices, trailers, sheds, etc. of combustible construction at least 30 feet from permanent buildings.

(2) Safety Office approved only heating devices installed. Per NFPA 211, maintain minimum clearance around stoves, heaters and chimneys.

K. ROOFING OPERATIONS (NFPA 241, Ch.6)

(1) Asphalt and tar kettles located outside the building or on a noncombustible roof away from combustibles. Kettles must have gravity lids, tight fitting.

(2) Torch applied roofing systems shall be installed using extreme caution. Follow manufacturer’s instructions. Caution around roof openings, penetrations or flashings.

(3) Fire extinguisher, 20-B minimum, within 30 feet of roof kettle. At least one extinguisher

2A:20-B:C on the roof being repaired; also one within 30 feet of torch applied roofing equipment.

(4) Fuel containers at least 10 feet away from burner flame.

(5) Notify building occupants who might be affected. Coordinate with COTR.

(6) Investigate location of supply air intakes. Coordinate shutdowns as necessary with COTR.

(7) Roof edges shall be guarded by typical roof protection or a safety monitoring system.

L. EXIT PATHWAYS (NFPA 241, Ch.5; also reference NFPA 101)

(1) Every building and area will remain accessible to fire department apparatus and personnel.

Roadways will be maintained with 20 feet of all buildings.

(2) Adequate egress paths, including stairs and corridors, will be maintained at all times. Exits may only be blocked temporarily if unavoidable and when adequate alternate measures are provided (signage, temporary fire detection, training, etc.) to warn personnel. Coordinate with

COTR.

WORK LOCATION:

NOTIFIERS SIGNATURE & DATE:

NAME & PHONE No.:

CONTRACTOR:

COR SIGNATURE & DATE:

Section 01 00 00, General Requirements – Attachment #4

CONSTRUCTION FIRE SAFETY CHECK LIST

Project # and Title:
Date:
Check Box3: Off
Check Box4: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box9: Off
Check Box10: Off
Check Box11: Off
Check Box12: Off
Check Box13: Off
Check Box14: Off
Check Box15: Off
Check Box16: Off
Check Box17: Off
Check Box18: Off
Check Box19: Off
Check Box21: Off
Check Box22: Off
Check Box23: Off
Check Box24: Off
Check Box25: Off
Check Box26: Off
Check Box27: Off
Check Box28: Off
Check Box29: Off
Check Box30: Off
Check Box31: Off
Check Box32: Off
Check Box33: Off
Check Box34: Off
Check Box35: Off
Check Box36: Off
Check Box37: Off
Check Box38: Off
Check Box39: Off
Check Box40: Off
Check Box41: Off
Check Box42: Off
Check Box43: Off
Check Box44: Off
Check Box45: Off
Check Box46: Off
Check Box47: Off
Check Box48: Off
Check Box49: Off
Check Box50: Off
Check Box51: Off
Check Box52: Off
Check Box53: Off
Check Box54: Off
Check Box55: Off
Check Box56: Off
Check Box57: Off
Work Location:
Name and Phone #:
Contractor:
Clear: