S05_RFI 3 Tracking Log 673_22_109 DB Install Fan Array AHU OR 2_7_Final.pdf
PDF 134 KB Posted
- Attached to
- Z1DA--FY23 NRM-Tier 1 (PROJ 673-22-109) D/B: Install Fan Array in AHU OR2-7 and Replace Exhaust Fans
- Solicitation number
- 36C24823R0068
About this file
This document contains a tracking log of questions and responses related to a request for information (RFI) for a construction project at a Veterans Affairs medical center. The project involves installing a new fan array in air handling unit OR2-7 and replacing exhaust fans at the James A. Haley VA Medical Center in Tampa, Florida. The solicitation number for this project is 36C24823R0068. Questions addressed in the log relate to the use of variable frequency drives, coordination of work with hospital services, staging areas, required testing, access and security procedures, disposal of old equipment, utility shutdown coordination, crane access plans, treatment of any additional necessary scope discovered after bidding, and consideration of alternative solutions. Responses provide details on allowable work hours and downtimes, temporary HVAC needs, required testing and balancing, key and access provisions, expectations for equipment disposal and unforeseen conditions, and openness to alternative approaches.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information (RFI) #3
D/B Install Fan Array AHU OR 2-7 & Replace Exhaust Fans Project 673-22-109
Attachment 2 RFI Tracking Log
RFI NBR Question/ Response
Company Submitted By
Dated Received
1. Multiple VFD’s were mentioned. Should we plan for one per fan or is additional redundancy desired?
Milicon 5/15/23
VA Response: One per fan
2. Will the space served by the air handler require temporary air conditioning while the fans are being replaced?
Milicon 5/15/23
VA Response: No. Downtime on the unit must only occur on nights/weekends, which will avoid the need for temp air.
3. Will the General Contractor be able to work on nights and weekends?
Milicon 5/15/23
VA Response: Yes. All work affecting the usability of the Unit (or crane lifts that will require evacuation of areas flown over) must be done on off hours.
4. Does this project overlap with other projects throughout the hospital that require additional coordination?
Milicon 5/15/23
VA Response: No – coordination will be needed with the affected services but no other construction will interfere.
5 Will there be a staging area (Material storage, dumpster, etc.) Milicon 5/15/23
VA Response: Yes. Will be addressed at kickoff
6 When installing the Fans what is the desire schedule to work for the VA?
Milicon 5/15/23
VA Response: All work affecting the usability of the Unit (or crane lifts that will require evacuation of areas flown over) must be done on off hours. Unit must be back in service by Monday morning following any weekend downtime
7 Will the GC need to provide temporary air conditioning while work is going on? or will the area shut down during the installation process?
Milicon 5/15/23
VA Response: See answer to #2
8 Will the GC need to do a pre-construction Test and Balance on the affected areas? or will this not be required?
Milicon 5/15/23
VA Response: Yes, Pre- and Post- TAB must be conducted by contractor
9 Will the VA provide specialized keys and fobs, or would we need a VA Chaperone all the times?
Milicon 5/15/23
VA Response: Construction keys will be provided to Project Manager, Superintendent, and SSHO. Access and use of loading dock must be coordinated with CORs
10 Would this project allow to work on weekends and at nighttime? Milicon 5/15/23
VA Response: Yes. All work affecting the usability of the Unit (or crane lifts that will require evacuation of areas flown over) must be done on off hours.
Request for Information (RFI) #3
D/B Install Fan Array AHU OR 2-7 & Replace Exhaust Fans Project 673-22-109
Attachment 2 RFI Tracking Log
11 What are we doing with the old equipment? Are they garbage or do we have to turn them in to the hospital?
Milicon 5/15/23
VA Response: Acknowledgement from COR for any disposed equipment.
12 Does the VA expect to have electrical hot work, or will the GC need to coordinate any electrical shutdowns?
Milicon 5/15/23
VA Response: GC will need to coordinate all shutdowns through COR using Utility Shutdown procedures and workplan coordination
13 If needed, does the VA have a preferred staging plan for a crane to fly out / in equipment from the roof? If so, which is it?
Milicon 5/15/23
VA Response: Contractor is responsible for submitting plan to COR for location approval. All occupied areas flown over must be vacated so most minimal affect to the facility should be considered.
14 If it is discovered during the design phase that any of the deleted scope of work in Phase II of the bid needs to be performed during the project's construction phase, will this be considered as an unforeseen situation and qualify for future economic adjustment?
Milicon 5/15/23
VA Response: Any work discovered and deemed necessary to the success of the project will be considered by CORs and CO for a modification
15 Does the VA expect any unforeseen condition that were found after or during this bid time that needs to be considered?
Milicon 5/15/23
VA Response: The VA does not expect any unforeseen conditions. However, any conditions that contractor sees prior to project award shall be brought to the attention of the VA via RFI and/or in the contractor’s proposal to avoid any contract modifications post-award.
16 Will you accept alternate solutions? OST 5/10/23
VA Response: Yes, alternate ideas will be considered assuming they at a minimum, meet the requirements to fulfill the project intent.