P09_SOW 673_22_109 FINAL_RFI 2 Revision.docx

DOCX document 62 KB Posted

Attached to
Z1DA--FY23 NRM-Tier 1 (PROJ 673-22-109) D/B: Install Fan Array in AHU OR2-7 and Replace Exhaust Fans
Solicitation number
36C24823R0068
Issued by

About this file

This statement of work describes a design-build project to replace the supply fan in an air handling unit and replace six exhaust fans at the James A. Haley Veterans Hospital in Tampa, Florida. The contractor will be responsible for site investigation, design, drawings, specifications, construction, equipment installation, and commissioning. Key deliverables include 35%, 65%, 95%, and 100% design submissions within 119 days of the design notice to proceed, with construction to be completed within 244 days of the project notice to proceed. The contractor must follow all applicable safety, security and records management regulations and coordinate life safety reviews. Subcontractor oversight and training requirements are also outlined.

View the file

Other files

File Type Posted
S05_RFI 3 Tracking Log 673_22_109 DB Install Fan Array AHU OR 2_7_Final.pdf PDF
36C24823R0068 0008.docx DOCX document
S04_Site Visit 2 Sign in.pdf PDF
36C24823R0068 0007.docx DOCX document
P01_SOW_PN 673_22_109_Change of Scope Revision.docx DOCX document
S02_RFP Attachment_INSTRUCTIONS TO OFFERORS_Install Fan Array_Updated.docx DOCX document
S05_RFI 2 Tracking Log 673_22_109 DB Install Fan Array AHU OR 2_7_Final.docx DOCX document
S02_RFP Attachment_EF Mech Dwg.pdf PDF
S02_RFP Attachment_EF Schedule.pdf PDF
S04_Site Walk 1 Sign In.pdf PDF
36C24823R0068 0006.docx DOCX document
S02_RFP Attachment_EF Electrical Dwg.pdf PDF
36C24823R0068 0005.docx DOCX document
36C24823R0068 0004.docx DOCX document
36C24823R0068 0003.docx DOCX document
S02_RFP Attachment_INSTRUCTIONS TO OFFERORS AND EVALUATION INFO_Install Fan Array_10Feb2023.docx DOCX document
S05_RFI Tracking Log 673_22_109 DB Install Fan Array AHU OR 2_7_Final.docx DOCX document
S02_RFP Attachment_Pages from 8_As_Built Drawings_Mechanicals.pdf PDF
36C24823R0068 0002.docx DOCX document
S02_RFP Attachment_Pages from 8_As_Built DrawingsAHU.pdf PDF
S02_RFP Attachment_23_74_13 Packaged Outdoor Central Station AHU REV.pdf PDF
P09_SOW 673_22_109 FINAL_RFI Revision.docx DOCX document
36C24823R0068 0001.docx DOCX document
Experience Information Sheet.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Adopted Codes General Requirements - Appendix B.pdf PDF
S02_RFP Attachment_VA 01 00 00 Safety and Infection Control Guide General Requirements - Appendix D.pdf PDF
S02_RFP Attachment_VA 01 00 00 Contractor Work Plan Peer Review General Requirements.pdf PDF
S02_RFP Attachment_SPEC 01 35 26_Safety Requirements 673-22-107.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Fire Safety Inspection Checklist for Hot Work General Requirements.pdf PDF
S02_RFP Attachment_Architectural - Bldg 1 second.pdf PDF
S02_RFP Attachment_DB Wage Rate FL20220208 dtd 09.09.22.txt TXT text file
S02_RFP Attachment_VA 01 00 00 Facility Management Alerts General Requirements - Appendix C.pdf PDF
S02_RFP Attachment_SPEC 23 05 11 Common Work for HVAC.pdf PDF
S02_RFP Attachment_INSTRUCTIONS TO OFFERORS AND EVALUATION INFORMATION_Install Fan Array.docx DOCX document
S02_RFP 36C24823R0068_Final.pdf PDF
S02_RFP Attachment_VA 01 00 00 Approved OSHA Training Providers List General Requirements - Appendix A.pdf PDF
S02_RFP Attachment_SPEC 23 05 93 Testing Adjusting and Balancing for HVAC.pdf PDF
S02_RFP Attachment_SPEC 01 00 00_General Requirements 673-22-107.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Sprinkler Work Notifications General Requirements - Attachment 1a and 1b.pdf PDF
S02_RFP Attachment_Price Matrix.xlsx XLSX spreadsheet
S02_RFP Attachment_OR Reno As Built Drawings.pdf PDF
S02_RFP Attachment_SPEC 01 45 00 Quality Control.pdf PDF
S02_RFP Attachment_EMR.pdf PDF
S02_RFP Attachment_SPEC 01 32 16 16_Network Analysis Schedule_Design-Build Only.docx DOCX document
S02_RFP Attachment_Existing Panel Schedules.pdf PDF
S02_RFP Attachment_VA 01 00 00 VA Information and Information System General Requirements - Attachment 6.pdf PDF
S02_RFP Attachment_SPEC 01 42 19 Reference Standards.pdf PDF
S02_RFP Attachment_SPEC 01 33 23_Shop Drawings 673-22-107.docx DOCX document
S02_RFP Attachment_VA 01 00 00 Notification Of Hot Work General Requirements - Attachment 2.pdf PDF
S02_RFP Attachment_SPEC 23 34 00 HVAC Fans.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

James A. Haley VA Hospital Install Fan Array in AHU OR’s 2-7 And Replace Exhaust Fans 673-22-109

STATEMENT OF WORK

Install Fan Array in AHU OR’s 2-7 And Replace Exhaust Fans 673-22-109

I. SCOPE OF WORK:

Furnish all necessary professional services, equipment, labor materials, supervision, tools, testing, and specialty services to perform a design-build for the NRM Project # 673-22-109, replace the existing supply fan within AHU-OR2-7 with new fan arrays with individual VFD’s per fan and replace the six existing Exhaust Fans on OR lab roof. AHU-OR2-7 is one unit that serves the hospital’s operating rooms 2 through 7. This project provides redundancy to units that are serving critical areas within the facility as well as energy savings associated to the smaller high efficiency fans. Also, the existing piping arrangement makes maintenance and replacement of parts very difficult. Pipework shall be reworked to ensure ease of maintenance and replacement. The new fan wall arrangement will include upgrade to the BAS system to the newest version compatible to a new, contractor-provided and installed SNE and CGM and allow more flexibility to the unit for any future servicing. The contractor shall also clean the AHU coils while unit is down for fanwall conversion. Work to be completed during abnormal business hours in Building 1 as designed in the hospital areas identified in the project description in this SOW. The DB Team is to include subcontractors performing professional services under this contract, shall perform its services consistent with the professional skill and care ordinarily provided by architects/engineers practicing in the same or similar locality under the same or similar circumstances. The DB Team shall perform its services as expeditiously as is consistent with such professional skill and care and the orderly progress of the project.

The design phases will include 35%, 65%, 95% and 100% review stages. This includes drawings, narrative, and specifications. Specifications must meet TIL and facility standards, including those attached in this contract and other applicable requirements. If the documents do not meet all the requirements of each submission, then the portions of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the DB Team prior to moving on to the next scheduled submission.

The VA will provide requested As-Built drawings (in either AutoCAD, PDF, or JPG form) electronically to the A/E as reference for design purposes. The A/E is responsible for reviewing all drawings with the assigned VA representative COR to verify what existing drawings are available and accurate. The A/E shall coordinate with the VA representative COR prior to viewing the drawings located at the VA and shall not remove any documents from the files.

The existing drawings on file at the VA may not be 100% accurate and may not exactly reflect the current conditions of the James A. Haley VA Hospital. It is the responsibility of the A/E to review the existing drawings and verify the existing conditions.

A. Project Description:

Provide services to "Install Fan Array in AHU 0R’s 2-7 and Replace Exhaust Fans on OR Roof Building 1 at the James A. Haley VA Hospital, located at 13000 Bruce B. Downs Boulevard, Tampa, Florida, 33612. The work includes, but is not limited to site investigation, design and preparation of drawings, phase planning, specifications, construction, and installation Removal and disposal of existing 50-HP supply air fan. Provide, set, and secure equivalent capacity fan wall with the following features/options A (4) fan supply fan array for AHU-OR 2-7 that will connect to new individual VFDs per fan. The fans shall have the following or equivalent: 12 HP – Toshiba Premium Efficiency Motors NEMA4 – Motor overload panel for each motor Disconnect, aux MSP dry contact, array of indicator lights Zero static backdraft damper for each fan cube 2 spare motors provided to the VA for future replacement. If needed Modify existing electrical wiring as required; existing breakers and conductor feeders will be utilized. Existing pipework shall be reworked as needed to increase maintainability. Modify existing controls, programming, and graphics as required, providing and connecting to a new SNE. VFDs and JCI panels shall be relocated to existing mechanical room. Existing Temperature and static pressure sensors will be Replaced. Install new access doors to easily service the new fan wall. Clean AHU coils while unit is down for fanwall conversion. Perform official startup and recommissioning of the system and log performance Pre and Posttest and balance to verify system performance. Replace the following 6 Exhaust Fans on the OR Lab Roof of Building 1: EF-LAB1, EF-LAB2, EF-LAB3, EF-OR1, EF-OR2, EF144.

. Work time will be coordinated with affected services to avoid the use of a temporary unit. This may include some off-hour work to avoid disruption to facility operations. Contractor is required to perform value engineering if required to stay with project funding limitations.

The DB Team shall evaluate the project areas to determine if utilities or any other objects will need to be relocated or addressed in the design. The DB Team shall also review the as–Built drawings and the site drawings for the areas affected to ensure proper operation of AHU.

The DB Team shall show a detailed containment plan for infection control for this design. This plan shall be detailed showing locations and what infection control requirements are to be used for each area. The HPMs for Safety and Infection Control will be provided to the D/B Team for their use. Construction barriers will be required for the duration of the construction to isolate patients and staff from dust, debris and construction hazards as determined by the Safety Officer and Infection Control representatives. The D/B Team will also have to indicate these construction barriers on their drawings.

New work includes, but is not limited to designing and preparing drawings, phasing planning, and specifications for all disciplines to replace the supply fan in AHU-OR2-7 with a fanwall and replace the existing exhaust fans on the OR Lab roof in the hospital campus areas listed in this SOW. The D/B Team will be required to attend phase meetings at 35%, 65%, and 95% to discuss progress with the VA staff. The D/B Team will be required to take meeting minutes and distribute to the VA for approval and as documentation of what was covered in the meeting.

B. Design Tasks (Some disciplines included will have little to no impact on scope of this project. D/B Team shall include as needed to meet project goals):

1. SITE INVESTIGATION: Design Services shall conduct a site survey of the project area to ensure that the design is feasible and without any major obstacles. Available as–built drawings and related other project drawings are available to the DB Team, but field verification by the DB Team must be completed to verify existing site conditions and to collect data as required for design development work to successful completion of design and construction documents.

2. DEMOLITION: The project demolition work may include structural, architectural, mechanical, plumbing, and electrical demolition to clear space for the new systems. No equipment shall be left abandoned in place or create dead legs.

3. CIVIL / STRUCTURAL: Work may include architectural modification and structural work. Structural engineering is expected to be completed by a Florida Licensed Structural Engineer for any needed structural reinforcements. All required borings and structural testing shall be completed by the DB Team. The D/B team shall proceed with a structural design that will not impede on pedestrian traffic in patient areas.

4. ARCHITECTURAL: Field verification of elevations and architectural dimensions are crucial to the success of this project, as the existing drawings are best represented. Exterior work must blend into the surrounding buildings and architectural appearances.

Patient and Family Centered Care concepts are to be included in the design of this project. These concepts are outlined in the VA technical information library design guide documents. See paragraph I.D.2 for additional information.

5. INTERIOR DESIGN: The VA Interior Designer will perform all interior color and material selections from the D/B Team’s recommended items. The D/B team will coordinate all interior selections with the VA interior design staff.

6. ELECTRICAL: The D/B team must evaluate the electrical systems serving the design scope area to determine if there is enough, and provide modifications and extensions to the existing electrical systems, security system, communications system, fire / safety system, controls, etc. as needed and with available capacity.

7. PLUMBING/PIPING: The plumbing systems need to be evaluated and updated to meet the latest Plumbing Codes, including VA Legionella guidance. Design modifications, additions and relocations to the plumbing systems and fire protection system must follow the VISN 8 policy and Life Safety codes and other applicable code requirements for a complete certified functional system.

8. HEATING, VENTILATION, AND AIR CONDITIONING (HVAC): The HVAC systems need to be evaluated and updated to meet the latest HVAC and Controls Design Criteria. The A/E must evaluate the AHU and exhaust fan systems serving the design scope area. If necessary, relocation of piping or ductwork may be needed in certain areas.

9. EQUIPMENT: The D/B Team shall coordinate the design work directly with the suppliers / manufacturers of the new equipment to produce a completely designed operational project. All drawings, schematics, and other data available from the equipment suppliers shall be incorporated in the A/E drawings and specifications. The D/B Team is to determine the points of connection between old and new equipment and clearly detail these connections on the drawings.

10. Design the project by using site measurements and verifying site conditions. The D/B Team shall not rely solely on the As–Built drawings.

11. The D/B Team shall provide other documentation (i.e., calculations, reports, recommendations, etc.) that is appropriate to support the design effort and to keep the Government fully informed of all issues or potential problems. Provide computations and sizing calculations for any anticipated new loads, altered loads, and existing loads for electrical, mechanical (HVAC, plumbing, medical gas and steam), sanitary, structural and fire protection designs. For computerized calculations, submit complete and clear documentation of computer programs, interpretation of input / output, and description of program procedures. Provide an investigation and explanation of code requirements incorporated into the design. Furnish a copy of each code quoted or used in the design, when necessary to provide additional understanding of design decisions.

12. The D/B Team shall provide all schedules and tables used on the drawings in MS Excel.

C. Additional Requirements and Information:

1. LIFE SAFETY: Requirement for acquiring and incorporating a Certified Independent Third-Party Safety Professional review of design documents. The D/B Team shall design the necessary Life Safety and Interim Life Safety provisions for impacted areas, both temporary and permanent measures. The D/B Team shall provide and coordinate the review of the Life Safety Provisions of the project design with a third party, independent licensed Fire Protection Engineer. The following areas will be reviewed by the third party:

a. NFPA Code Compliance

b. Environmental / EPA Impacts, Permits, etc.

c. OSHA Compliance (i.e., Excavation, Demolition, etc.)

d. Security Property / Infrastructure Management, Homeland Security, etc.

e. Emergency preparedness

f. Disability Accessibility Compliance

g. National and Local Codes. The D/B Team shall deliver a letter certifying compliance with all Life Safety Codes and Requirements applicable to this project from the third party.

In addition, it is required that the D/B Team update all Life Safety Drawings associated with the designed space and affected by the project.

2. NOTES: NFPA 101 primarily addresses life safety and fire protection features while the IBC addresses a wide range of considerations, including, but not limited to, structural strength, stability, sanitation, adequate light and ventilation, and energy conservation. VA buildings must meet the requirements of NFPA 101 and documents referenced by NFPA 101 in order to comply with the accreditation requirements of the joint Commission. Therefore, designs shall comply with the requirements of the latest edition of NFPA 101 and documents referenced therein. Design features not addressed by NFPA 101 or documents referenced therein shall comply with the requirements of the latest edition of the IBC or as otherwise addressed above in this Program Guide. For design features that are addressed by both the IBC as well as NFPA 101 or a document referenced by NFPA 101, the requirements of NFPA 101 or the document referenced by NFPA 101 shall be used exclusively. This applies even if the IBC requirements are different.

3. Conflicts between Nationally Recognized Codes and Standards and VA Requirements: Should a conflict exist between VA requirements and VA adopted nationally recognized codes and standards, the conflict shall be brought to the attention of the VA. The resolution of the conflict shall be made by the authority having jurisdiction for the VA to ensure a consistency system wide.

4. DRAWINGS: The A/E shall provide electronic copies of drawings at each review step generated in the latest version of AutoCAD or its companion products (digitally signed DWGs) and PDF format in individual sheet files. Include all associated support files (i.e. plot styles, external referenced files, etc.). This facility currently uses AutoCAD 2020. The standard drawing size shall be ARCH E1 (30” x 42”). The format to be used in creating the CAD drawings (i.e. layer / level structure, fonts, font sizing, file naming conventions, etc.) is that of the latest edition of the National CAD Standard (www.nationalcadstandard.org).

a. The D/B Team shall follow these level / layer formats, file – naming conventions, and symbol library.

b. Drawings are to be drawn from the VA’s “As-Built” or construction drawings updated by site verification, not scanned reproductions.

c. The final sets of the new construction drawings, including the film copies, shall be sealed (embossed & ink stamps) and signed by each respective Professional Engineer in their discipline, Industrial Hygienist, Architect and other necessary licensed professional consultants.

5. SPECIFICATIONS: The D/B Team may obtain the list of the complete VA Construction Specifications from the VA Facilities Management Technical Information Library (TIL), which is located at http://www.cfm.va.gov/TIL/spec.asp#02. The Tampa VA has specifications that have been edited for general use at this facility and are the preferred specification to be used. If there are missing specifications sections from the Tampa VA specific specification then the specifications from the Technical Information Library shall be used. Any specifications that are edited by the contractor shall be submitted to the VA for approval. The edited version of the specification shall be in Microsoft Word in the editing format and all changes shall be in RED. Contact the project COR to obtain a copy of these specifications. This facility will provide the specification sections needed based on the master list provided in the first review. The A/E shall provide the final edited specifications electronically in Microsoft Word and PDF. The format shall be 1.5 spaced, left justified, 2-sided, laser quality, and courier-new size 10 font. The specifications shall be provided in two (2) copies with rubber bands around one (1) of the copies. The remaining copy shall be in a colored, 3-“D”-ring loose-leaf binder, with identification labels on the binding and cover so the project title and number are readily visible and with tabbed dividers between each specification section. Any files submitted electronically (including but not limited to specifications and drawings) shall not have the following characters in their file name: \ / : * ? “ < > | # { } % ~ &.

6. DESIGN SCHEDULES: Design schedules shall be submitted to the VA as an 11x17 Microsoft Projects file at the beginning of the Notice to Proceed, with each invoice for payment and shall never be more than 4 weeks old. Approximate time frames are presented below. Actual timelines submitted for approval should reflect the project complexity and follow the format presented below:

i. Schematics

ii. Begin Design Development (Notice to Proceed): NTP

iii. First Submission of Design Development (35%): NTP + 15 Days

iv. First Review Meeting and Return First Submission: NTP + 21 Days

v. Second Submission (65%) NTP + 35 Days

vi. Second Review Meeting and Return Second Submission: NTP + 49 Days

x. Third Submission Contract Documents (95%): NTP + 63 Days

xi. Third Review Meeting and Return Third Submission: NTP + 77 Days

xiv. Fourth Submission (Deliver Final Contract Documents) (100%): NTP + 91 Days

xv. Fourth Review Meeting and Return Fourth Submission: NTP + 105 Days

xvi. Final design submission: NTP + 119 Days

7. REVIEW MEETINGS: The DB Team is required to attend a design review meeting after each submission during the design process and provide meeting minutes to the VA for approval and distribution.

1. Sections of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the A/E prior to moving on to the next scheduled submission.

D. COMPLIANCE

· The contractor shall be fully responsible for compliance with all VA, local, state, and Federal occupational safety laws, rules, and regulations.

· The contractor shall follow life and safety codes and take necessary actions to avoid conditions that may be hazardous to the health and safety of hospital personnel and patients.

· The contractor is responsible for meeting all applicable OSHA and VA guidelines for safe working procedures.

· All work for the duration of the contract shall be performed by certified trained technicians.

E.CONTRACTOR EMPLOYEES

Contractor personnel shall present a neat appearance and be easily recognized as contract employees. Example: wearing steel toe boots and safety glasses ID badges and or name tags.

F.CONTRACTOR EMPLOYEE IDENTIFICATION

All contractor employees must be clearly identified as contractors (not VA employees) when performing services under this contract. This includes visual (appearance), verbal (phone), and electronic (email). The contractor must provide all employees with a contractor identification (ID) badge at the contractor’s expense prior to performing work under this contract. Contractor employees are always required to display this badge when performing services under this contract.

Employees released from service by the contractor must have their badge collected by the contractor. All badges must contain an expiration date and photograph of the employee.

All contractor employees must also be required to wear VA issued badges and must always display these badges while in the performance of this contract and/or as instructed by the COR.

The contractor supervisor must ensure that all contractor employees display their VA issued badges.

The contractor supervisor must be responsible for managing all VA issued badges provided to contractor employees and immediately collect these badges from employees no longer working on the contract.

G.CONTRACTOR EMPLOYEE CONDUCT

· The contractor is completely responsible for all actions and conduct of their employees. Contractor employees must be well-groomed and neat in appearance.

· Contract employees must be professional in attire and must not wear any offensive clothing.

· Contractor employees must conduct themselves in a socially acceptable manner appropriate for an office work environment; Loudness, vulgarity, rudeness, smoking, or other similar offensive conduct by a contractor employee may be grounds for denying the employee further access to VA premises.

· Contractor employees must not consume alcohol or illegal drugs during working hours or at any other time the employees are performing work under this contract.

H.CONTRACTOR RESPONSIBILITY

· The contractor shall obtain all necessary licenses and/or permits as required to perform this work.

· He/she shall take all reasonable precautions necessary to protect persons and property from injury or damage during the performance of this contract.

· He/she shall be responsible for any injury to himself/herself, his/her employees, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by his/her employees’ fault or negligence and shall maintain personal liability and property damage insurance having coverage for a limit as required by the laws of the State of Florida.

· Further, it is agreed that any negligence of the Government, its officers, agents, servants and employees, shall not be the responsibility of the contractor hereunder with the regard to any claims, loss, damage, injury, and liability resulting there from.

I.UNSCHEDULED REPAIRS AND EMERGENCY SERVICE:

· Contractor shall provide a telephone number for repair services assistance. Contractor shall notify the COR immediately if the telephone number is changed.

· Contractor shall respond to emergency repair calls with their installation/warranty by phone normally within two (2) hours but no more than four (4) hours. Contractor shall provide an on-site response time of no more than four (4) hours or next business day if call is made after 1:00 p.m. and be required to repair the equipment and place it back in service within twenty-four (24) hours after notification by telephone call (unless another specified time is agreed to by the COR placing the service call request). Response time is defined as time contractor is first notified until the time vendor arrives on station. Failure to meet the required on-site response or repair time shall allow the Government an option to contact a third-party vendor to provide services. Costs for services provided by a third party shall be billed against the Contractor.

J.CONTRACT AWARD MEETING:

· The contractor shall not commence performance on the tasks in this SOW until the CO has conducted a Kickoff Meeting or advised the contractor that a kickoff meeting is waived.

K.PERIOD OF PERFORMANCE:

· This shall be a firm-fixed price contract. Warranty period for the installation and repair will be provided as part of the original contract documents for the project.

L. CHANGES TO THE Statement of Work

· Any changes to this SOW shall be authorized and approved only through written correspondence from the CO. A copy of each change will be kept in a project folder with all other products of the project. Costs incurred by the contractor through the actions of parties other than CO shall be borne by the contractor.

M. Performance Requirements:

· Contractor shall provide the necessary personnel and equipment to meet or exceed required service. Contractor shall have the following responsibilities:

· Provide licensed and trained personnel to perform the project in the State of Florida.

· Provide all supervision, labor and materials to complete all requirements described in this SOW.

· Contractor shall obtain all necessary licenses and permits required to perform this work required by this SOW, with each having completed the Occupational Safety & Health Administration (OSHA) approved 10-hour Construction Outreach Training or General Industry Outreach Training.

· Contractor shall take all precautions necessary to protect persons and property from injury and/or damage during performance of this contract.

· Contractor shall be responsible for any injury to their employees as well as for any damages to personnel or Government property that occurs during the performance of this contract that is caused by the Contractor’s fault or negligence.

· Contractor shall insure that all areas where equipment is serviced under this contract are left in a clean, neat and orderly condition.

· Contractors shall have technical training and evident track records of working experience in HVAC and related components in healthcare, industrial, educational, or commercial facilities for a minimum of five (5) years.

· Contractors shall possess and utilize all necessary tools, equipment, and Personal Protective Equipment (PPE) to perform all work safely, effectively, and timely. Tools, equipment, and PPE shall comply with OSHA Standard 29 CFR 1910, (Subpart I), and NFPA 70E. Prior to initiating work, the Contractor shall provide documentation demonstrating that all instruments, test equipment, tools, and PPE possess current calibration and safety inspections. Dated calibration and safety inspection labels shall be visible on all equipment as applicable

· Arrange and pay for all proper disposal of waste and debris. Waste disposal shall be tracked and reported to the COR monthly. Invoices submitted may not be approved until receipt of this record.

· Maintain project schedule agreed upon in the purchase order documents.

· Provide all OSHA site safety for each employee during work.

· Contractor employees shall have background checks completed.

N.DELIVERABLES

· The Contractor shall perform the services necessary to complete the tasks in accordance with the procedures described in a timely and professional manner, consistent with industry standards, at the location, place and time that the VA has set aside, and all in accordance with the SOW and RFP documents.

· Contactor shall provide a copy of the inspection document used (field report) on the day of each performed inspection.

O.TESTING SPECIFICATIONS

· All testing/inspections of the shall be in accordance with applicable industry standards and manufacturers recommendations. The initial test schedule shall be submitted to the COR no later than 10 days after award. The inspection schedule shall be submitted to the COR sixty (60) days prior to the start of the next inspection.

P.ROLES AND RESPONSIBILITIES:

· Contracting Officer (CO) - A person duly appointed with the authority to enter, administer and terminate contracts on behalf of the Government. The CO is the only person who can legally commit the Government and only the CO, as the Government's agent, can modify the contract/order. The CO is the final authority for determining the adequacy of the Contractor's performance. CO decisions arising under or relating to the contact are final.

· Contracting Officer's Representative (COR) — An individual designated in writing by the CO to perform specific technical and administrative functions within the scope and limitations of their written appointment (e.g., surveillance of Contractor's performance, accept services). The COR is not empowered to make any contractual commitments or authorize any changes to the order/contract or in any way obligate additional funds by the Government; such authority' rests solely with the CO. The COR’s primary duty is to monitor the Contractor's performance by physically checking to see that tasks are completed, reports are submitted, and desired outcomes are achieved. When a surveillance observation results in an unacceptable evaluation, the COR will report the unacceptable performance to the COR. The COR is not authorized to direct work, offer advice on how the work should be performed, change the contract, or in any way obligate payment of funds by the Government.

· METHOD OF SURVEILLANCE: Simplified methods of surveillance will be used by the Government to evaluate contractor performance. The primary methods of surveillance are periodic assessments of service and customer feedback.

· Periodic Assessment of Services — For services that occur over several months, the COR shall evaluate contractor performance on a quarterly basis and upon completion of services. Generally, the Government will rely on the Contractor's Quality Control system to ensure that services conform to contract quality requirements before they are tendered to the Government for acceptance.

· Customer Feedback — Customer feedback is typically obtained via telephone or email. Telephonic customer complaints must be followed up in writing/email. To be considered valid, the customer complaint must clearly articulate the nature of the complaint, time, date, etc. The COR will investigate the complaint; if determined valid, the COR will advise the CO and the Contractor of the deficiency. Copies of valid complaints and the resolution must be retained in the official contract file.

Q. SECURITY CLAUSES:

With No Sensitive Data but Requires Training

VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY LANGUAGE

NARA RM CONTRACT LANGUAGE CLAUSE

1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

4. James A Haley Veterans’ Hospital and Clinics and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of James A. Haley Veterans’ Hospital and Clinics or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701.

In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to James A. Haley Veterans’ Hospital and Clinics. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to James A. Haley Veterans’ Hospital and Clinics control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and James A. Haley Veterans’ Hospital and Clinics guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with James A. Haley Veterans’ Hospital and Clinics policy.

8. The Contractor shall not create or maintain any records containing any non-public James A. Haley Veterans’ Hospital and Clinics information that are not specifically tied to or authorized by the contract.

9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

10. The James A. Haley Veterans’ Hospital and Clinics owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which James A Haley Veterans’ Hospital and Clinics shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.

11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #4192704, Records Management for Everyone. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.

[Note: To the extent an agency requires contractors to complete records management training, the agency must provide the training to the contractor.]

R. Flow down of requirements to Subcontractors

1. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this [contract vehicle], and require written subcontractor acknowledgment of same.

2. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contract

III. COMPLETION TIME

A. Project must be completed within 244 days of notice to proceed.

a. Final design submission must be provided to the VA for final acceptance within 119 days of design notice to proceed.

b. Construction phase cannot begin prior to construction notice to proceed given by the contracting officer. Unless exception is given, the construction NTP will not be given until the final design drawings are approved by the VA.

-END-