S02_RFP Attachment_VA 01 00 00 Fire Safety Inspection Checklist for Hot Work General Requirements.pdf
PDF 83 KB Posted
- Attached to
- Z1DA--FY23 NRM-Tier 1 (PROJ 673-22-109) D/B: Install Fan Array in AHU OR2-7 and Replace Exhaust Fans
- Solicitation number
- 36C24823R0068
About this file
This document contains a fire safety inspection checklist for hot work operations and details for a federal contract opportunity to install a fan array and replace exhaust fans. The inspection checklist outlines safety requirements for hot work areas including ensuring floors are clean and wet down, combustible materials are removed or shielded, wall and floor openings are covered with suspended covers to collect sparks, and that a fire watch is provided during and for 30 minutes after hot work operations. The related federal contract opportunity is solicitation number 36C24823R0068 to install a fan array for Air Handling Unit OR2-7 and replace exhaust fans at the James A. Haley Veterans Affairs Medical Center in Tampa, Florida, with the point of contact being Amy Shaw and the contracting agency being the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3
Fire Safety Inspection Checklist for Hot Work
Operations Area
SECTION 01 00 00
GENERAL REQUIREMENTS
ATTACHMENT #3
FIRE SAFETY INSPECTION CHECKLIST FOR HOT WORK OPERATIONS AREA
PROJECT No. & TITLE:
DATE:
Floor swept clean of combustibles.
Floors wet down, covered with damp sand, metal or other shields.
Combustibles material or flammable liquids removed from area, whenever possible.
Combustibles and flammable liquids protected with covers, guards, or metal shields.
All wall and floor openings covered.
Covers suspended beneath work to collect sparks.
WORK BEING DONE ON WALLS OR CEILINGS
Ensure wall construction is noncombustible and is without combustible covering.
Move combustibles away from opposite side of wall.
WORK BEING DONE ON ENCLOSED EQUIPMENT-(TANKS, DUCTS, ETC.)
Remove all combustibles from enclosures.
Purge of flammable vapors. Ensure continuous purge so no vapors accumulate during work.
FIRE WATCH
To be provided during and until 30 minutes after operation.
Provide a 10-pound dry chemical or halon extinguisher and small hose.
Workers trained in use of equipment and in sounding fire alarm.
FINAL CHECK-UP
Conducted 30 minutes after completion of any operation, unless fire watch is provided.
Notify Safety Office (extension 7292) when work is complete. (Contractors - notify COR)
Notify Graphic Control Center (extension 7080), if any fire zones were by-passed
HOT WORK LOCATION:
NOTIFIERS SIGNATURE & DATE:
NAME & PHONE No.:
CONTRACTOR:
COR SIGNATURE & DATE:
Section 01 00 00, General Requirements – Attachment #3
Revised March 2018
| Contract Information: |
| Project No: |
| and Title: |
| Date: |
| Check Box138: Off |
| Check Box139: Off |
| Check Box140: Off |
| Check Box142: Off |
| Check Box143: Off |
| Check Box145: Off |
| Check Box146: Off |
| Check Box147: Off |
| Check Box148: Off |
| Check Box149: Off |
| Check Box150: Off |
| Check Box151: Off |
| Check Box152: Off |
| Check Box153: Off |
| Check Box154: Off |
| Check Box155: Off |
| Hot Work Location: |
| Notifiers Name and Phone #: |
| Contractor Company Name: |
| Reset: |