S02 MRI Emg Generator Specs.pdf
PDF 2 MB Posted
- Attached to
- Y1GC--523A5-24-011 MRI Generator UST
- Solicitation number
- 36C24124B0030
About this file
This document is a Specification for the MRI Emergency Generator Underground Storage Tank (UST) Project Number 523A5-24-011 at the Veterans Administration Boston Healthcare System (VA BHS) Brockton Campus in Brockton, Massachusetts.
The key details are:
- The project involves infrastructure improvements including general construction, renovations, safety, infection control measures, environmental protection, testing, quality control, waste management, earthwork, underground utilities, concrete, facility fuel oil systems, tank monitoring, leak detection, temperature controls, electrical, and communications systems.
- The base bid is for the general contractor to be responsible for all construction management and work, with a 150-day period of performance.
- Unit pricing is provided for removal and disposal of contaminated/unsuitable soil.
- The contractor must develop a detailed Construction Phasing Plan to maintain the existing MRI emergency generator in service without interruption during construction.
- Specific security, access, and documentation requirements for the contractor are outlined, including background checks, restricted areas, vehicle access, and protection of sensitive information.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT TITLE:
SPECIFICATION
MRI Emergency Generator Underground Storage Tank (UST)
PROJECT NUMBER: 523A5-24-011
LOCATION: Veterans Administration, Boston Healthcare System (VA BHS)
Brockton Campus 940 Belmont Street
Brockton, MA 02301
PHASE: Final Bid Documents
DATE: July 12, 2023
523A5-24-011 – MRI Emergency Generator UST Date: July 12, 2023
VA Boston Healthcare System – Brockton Campus Final Bid Documents
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules 11-21
01 33 23 Shop Drawings, Product Data, and Samples 06-21
01 35 26 Safety Requirements 11-21
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 01-21
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 10 00 Facility Fuel Systems 04-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 41 Underground Electrical Construction 01-17
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
31 20 06 Handling and Disposal of Contaminated Soil *
31 23 19 Dewatering 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
- - - END - - -
GENERAL
CSK-02
CSK-02/H4.00
Tank and Bollard Location
HVAC Site Plan
CSK-02/H4.01 HVAC Generator & Fuel Oil Details
CSK-02/H4.02 HVAC Schematic
CSK-02/E0.01 Electrical site plan and details
CSK-02/E5.00
CSK-02/E5.01
Electrical Schedules
Electrical Schedules
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall provide all necessary supervision, demolition, labor, material, equipment, and coordination necessary to complete the work described by the contract documents or reasonably inferable from them as being necessary to produce the indicated results and perform work for MRI Emergency Generator UST, PROJECT NUMBER 523A5-24-011, Veteran’s
Medical Center, Brockton, Massachusetts as required by drawings and specifications.
1. The Contractor shall develop and present to, VHA BHS Engineering, for review and approval, a written Construction Phasing Plan (CPP) that identifies all required information to accomplish the intended work of the construction sequencing. The building 3 MRI Emergency
Generator must be available to always provide emergency power to the
MRI equipment (24/7/365) without interruption. The work must be planned so that the building 3 MRI Emergency Generator is uninterrupted, or the contractor must provide a separate temporary emergency power system to provide emergency power to the MRI equipment. The temporary emergency power system must be equivalent to the existing MRI Emergency Generator to provide the necessary capacity. The CPP shall indicate phasing sequence, length of intended phases and shutdowns and clearly define all systems and spaces that are affected. The contractor shall not be permitted to commence construction activities until all submittals identified within the drawings and specifications have been submitted and are approved by the Government. Only after all submittals are approved may the Contractor then submit an official written request to start construction activities at a minimum of 90 days in advance of the requested start date.
2. Information on existing conditions and associated design intent for the Work described in the contract documents is based on non-destructive and visual site observations of areas accessible in an occupied structure. Drawings are diagrammatic. They indicate general arrangements of each portion of the Work. They do not show exact arrangements and configurations required, nor do they show the exact routings, physical locations, or alignments necessary for coordination with existing conditions and other portions of the
Work. Contractor shall coordinate modifications in layout as necessary to complete the Work in accordance with the design intent.
In some instances, it may have been impracticable to detail all the items described in the contract documents because of variances in the means and methods of achieving the necessary results. In such instances, at no additional cost or time to the Government, the
Contractor shall furnish all labor, material, equipment, coordination, drawings, services, and other work necessary to produce complete operational interfaced systems, appurtenances and equipment which are complete, functional, and ready for proper operation by facility personnel and for the intended purpose in accordance with facility needs and manufacturer’s requirements.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.
C. Before placement and installation of work subject to tests by testing laboratory, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
E. Hours of Work: The normal working hours of this facility are Monday through Friday 7:00AM to 5:30PM. Work shall be scheduled to be performed during normal operating hours whenever possible, and after hours whenever deemed necessary by the VA Project Engineer (COR) due to operational requirements of the Medical Center. Work conducted in occupied areas, work that will create medical center interruptions, work that will create utility shutdowns/disruptions, work that will create noise & vibrations is designated as after-hours. Any after-hours work shall be scheduled in writing by the Contractor using the facility standard request form. Specific special work hours for individual projects shall be as follows for coordinating shutdowns and after-hours work.
F. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
G. Submittal Schedule: Provide a Submittal Schedule within fourteen (14) days after receipt of Notice to Proceed and before any items are submitted for review. Compile a complete and comprehensive schedule for all submittals anticipated to be made during progress of the work and submit to the VA Project Engineer (COR) for approval.
The schedule of submittals must be coordinated with the Contractor’s construction schedule. Include a list of each type of item for which Contractor’s drawings, shop drawings, certificates of compliance, material samples, guarantees, or other types of submittals are required. For each submittal item indicate the specification section and paragraph or other source within the contract documents where the requirements for the submittal item are described. Indicate whether proposed materials, equipment, and other items are as specified or will be submitted as an “or equal” or as a substitution. Upon review and approval by the VA Project Engineer (COR), the contractor will be required to adhere to the schedule except where specifically otherwise permitted.
H. For written Requests for Information, Contractors shall use the form listed as
Appendix A to this specification section.
01 00 00 -2
1.3 STATEMENT OF BID ITEM(S)
A. BASE BID: The General Contractor will be responsible for all facets of construction management, construction work, and the management of subcontractors to facilitate a construction project to install the MRI Emergency Generator UST at the VA Boston
Healthcare System – Brockton Campus. The scope of this project includes, but is not limited to, the following infrastructure improvements: general construction, renovations, safety, infection control measures, environmental protection, testing laboratory services, quality control, construction waste management, earth moving, excavation & trenching, thermal and moisture protection, facility fuel oil systems, tank fluid level monitoring & alarm systems, signage, leak detection systems for tanks & underground piping, temperature controls, bollards & barricades, fuel oil pumps, emergency generator, building management system, direct digital controls, electrical systems piping systems, underground piping & systems, communications, concrete, underground utility locating/GPR and schedule management. See drawings and specifications for more information. Period of Performance for Base Bid Offer:
Completion time for Base Bid Offer is one-hundred fifty (150) days from Notice to Proceed.
01 00 00 -3
B. Unit Prices:
1. Unit Price No. 1: Contaminated/unsuitable Soil Removal and
Disposal. Includes excavation, handling, stockpiling, transportation, and disposal of contaminated/unsuitable soil encountered during excavation and trenching for installation of the new storage tank. Also includes backfilling of the excavation with an equal quantity of approved material as described in Section 31 20 00 of the Specifications. Per ton.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at
Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. I n accordance with VA
Directive 0735 Personal Identity Verification of Federal
Employees and Contractors, all contractors on VA premises are required to obtain proper PIV identification cards. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give two week’s notice to the Contracting Officer and Contracting office representative (COR) so that security arrangements can be provided for the employees. This notice is separate from
01 00 00 -4 any notices required for utility shutdown described later in this section. The contractor shall also submit the badge application and all related documents for each employee, including subcontractors, scheduled to be on site at least 6 business days before starting work.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General
Contractor may return to the site only with the written approval of the Contracting Officer.
5. For working outside the “regular hours” as defined in the contract, the General Contractor shall give 5 business days’ notice to the VA Project Engineer (COR) and Contracting
Officer so that notifications can be distributed if needed, services informed and coordinated with and so VA Police &
Engineering M&O are made aware of off-hours work. This notice is separate from any notices required for utility shutdown described in the contract documents.
C. Information Technology Security: The contractor, their personnel, and their subcontractors shall be subject to the Federal laws, regulations, standards, and VA Directives and Handbooks regarding information and information system security as delineated in this contract.
1. See appendix H for HB6500 6 Handbook requirements. Contractor, their personnel and their subcontractors are required to review and sign.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
E. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining
01 00 00 -5 confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting
Officer upon request.
01 00 00 -6
4. These security documents shall not be removed or transmitted from the project site without the written approval of
Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the
VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
Security, access, and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General
Contractor and its employees for parking in designated areas only. Contractor to coordinate with Healthcare System Facility
Manager.
3. Traffic Control Plan (TCP)
a. Contractor shall submit a detailed phasing narrative, Traffic
Control Plan (TCP) with marked-up site plans and Google Earth images, Partial Road Closure Permit, and proposed specific phasing schedule showing how each phase will be accomplished. TCP shall be a comprehensive method of how traffic is proposed to be handled during the duration of each Phase. The TCP shall include, but not be limited to construction sections, work zone pavement
01 00 00 -7 markings, channelization devices, signage appropriate for the various phases, detour routes, temporary signals, dynamic message signs, etc.) Detailed Phasing plan shall include all fields required from the partial road closure at a minimum, as well as a detailed sequence of work narrative, etc. Phasing shall be accomplished to minimize disruptions to the VA Medical Center operations and City of Brockton, ensure safety of the traveling public and construction personnel, ensure environmental protection, ensure patient safety and construct the proposed phasing in the most effective manner possible. The general contractor, once phasing request has been accepted by the VA, shall coordinate with the City of Brockton, Brockton Fire
Department, Brockton Police Department, MA State Police, MA DOT, emergency forces that serve the VA Medical Center (i.e. ambulance service, etc.) and provide written confirmation of coordination with whom was contacted, name of company/department/service, contact information (address, email, phone, etc.), date contacted, meeting minutes of conversation, etc. General contractor shall perform all necessary work required to install the new security manhole covers the same day the existing manhole cover is removed. No grates, catch basins, inlets, manholes shall be uncovered and not covered in the same business day
4. Partial Road Closure
a. Contractor shall submit a Partial Road Closure Form at a minimum three (3) weeks in advance to VA Project Engineer (COR) for review, acceptance and campus notification. The general contractor and subcontractors shall not be permitted to fully close a road; only partial road closures are permitted. The written request shall include, but not be limited to, Project #, Date of Request, name of general contractor, name(s) of sub-contractor(s), date(s) of requested partial road closure, time(s) of requested road closure, location description, include a marked-up Google Earth image of the location, (showing construction activity limits, normal traffic flow routes, new proposed traffic flow reroutes, protection, barriers, cones, flagmen positions, traffic signage, etc.), description of work to be completed. Protection required, but not limited to, solid barricade with flashing lights, warning cones/signs and construction barriers, construction fencing, flagmen to direct
01 00 00 -8 vehicular and pedestrian traffic, traffic signage, etc. Cover partial road work with steel plates to permit traffic flow prior to performing work on other side of roadway. One lane shall always be open and passable. The general contractor shall bear the cost to obtain Brockton Police Department and/or MA State
Police flagmen at work along Belmont Street, Manley Street, West
Chestnut Street, etc. VA Police do not perform flagmen duties on site, the general contractor shall include flagmen whose sole responsibility is flagmen duties during site work when necessary.
Road closure requests previously accepted by engineering may be canceled or postponed, (up to 24 hours prior to work being completed) by the VA Project Engineer (COR) if required for VA
Medical Center operations, events, etc. at no delay, cost or time impact to the government.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from
01 00 00 -9 liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the
Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be within the limits of construction.
E. Workers are subject to rules of the VA Boston Healthcare System –
Brockton Campus applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of the VA Boston Healthcare System – Brockton Campus as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit
01 00 00 -10 vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas. Provide unobstructed access to the
VA Boston Healthcare System – Brockton Campus areas required to remain in operation.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
All such actions shall be coordinated with the COR or Utility
Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Boston Healthcare system – Brockton Campus must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
01 00 00 -11
2. The general contractor and subcontractors shall not be permitted to fully close a road; only partial road closures are permitted. The written request shall include, but not be limited to, Project #, Date of Request, name of general contractor, name(s) of sub-contractor(s), date(s) of requested partial road closure, time(s) of requested road closure, location description, include a marked-up Google Earth image of the location, (showing construction activity limits, normal traffic flow routes, new proposed traffic flow reroutes, protection, barriers, cones, flagmen positions, traffic signage, etc.), description of work to be completed.
Protection required, but not limited to, solid barricade with flashing lights, warning cones/signs and construction barriers, construction fencing, flagmen to direct vehicular and pedestrian traffic, traffic signage, etc. Cover partial road work with steel plates to permit traffic flow prior to performing work on other side of roadway; seal steel plate to roadway. One lane shall always be always open and passable. VA
Police do not perform flagmen duties on site, the general contractor shall include flagmen whose sole responsibility is flagmen duties during site work when necessary. Road closure requests previously accepted by engineering may be canceled or postponed, (up to 24 hours prior to work being completed) by the Boston Healthcare System – Brockton Campus at no delay, cost or time impact to the government.
3. The general contractor shall submit a detailed phasing narrative, Traffic Control Plan (TCP) with marked-up site plans and Google Earth images, Partial Road Closure Permit, and proposed specific phasing schedule showing how each phase will be accomplished. TCP shall be a comprehensive method of how traffic is proposed to be handled during the duration of each Phase. The TCP shall include, but not be limited to construction sections, work zone pavement markings, channelization devices, signage appropriate for the various
01 00 00 -12 phases, detour routes, temporary signals, dynamic message signs, etc.) Detailed Phasing plan shall include all fields required from the partial road closure at a minimum, as well as a detailed sequence of work narrative, etc. Phasing shall be accomplished to minimize disruptions to the VA Medical
Center operations, including but not limited to Police patrols, Boiler Plant operations, laundry operations, Grounds operations and Patient, Staff and Visitor traffic, ensure safety of the traveling public and construction personnel, ensure environmental protection, ensure patient safety, and construct the proposed phasing in the most effective manner possible. The general contractor, once phasing request has been accepted by the Boston Healthcare System – Brockton
Campus,, shall coordinate with the Brockton Fire Department and other emergency forces that serve the Boston Healthcare
System – Brockton Campus, (i.e. Brewster ambulance service, etc.) and provide written confirmation of coordination with whom was contacted, name of company/department/service, contact information (address, email, phone, etc.), date contacted, meeting minutes of conversation, etc. to ensure all parties have been made aware of detours, partial road closures, etc.
4. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR three weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to Boston
Healthcare System – Brockton Campus, as follows:
5. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in
01 00 00 -13 affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Boston
Healthcare System – Brockton Campus operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc.
to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans
Affairs so that Medical Center operations will continue during the construction period.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m
(seven feet) minimum height, around the entirety of the construction area/lay-down area/dumpster location/trailer location/Conex trailer location/etc. that was requested by the general contractor and accepted by the VA Healthcare Engineer
(COR) and Contracting Officer prior to construction commencement or mobilization. Provide gates as required for access with necessary hardware, including hasps and padlocks. Provide three
(2) keys to VA Healthcare Engineer (COR). Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches).
Fence portable feet shall utilize concrete filled plastic (HDPE +
UV stabilized) mold bottoms in safety orange color (not-fade, 01 00 00 -14 sun/weather material); sandbags or plain concrete blocks are not acceptable. Bottom of fences shall extend to no greater than 25mm
(one inch) above grade. Construction fence shall be entirely wrapped (full fence height and length) with heavy-duty knitted
HDPE construction coupled high grade privacy fence screen. Screen shall be mold and mildew resistant. Privacy screen material shall conform to ASTM D-5041. Privacy screen shall be enforced with 12-gauge galvanized steel, hog ring C shaped fasteners that are crimped into the grommet holes for a secure and strong attachment. Contractor shall ensure adequate quantity of acceptable concrete filled plastic mold bottoms are utilized to secure the fencing from blowing-over with the privacy screen being used. Remove the fence when directed by VA Healthcare
Engineer (COR) & Contracting Officer.
K. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C
(40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for Boston
Healthcare System – Brockton Campus at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or
01 00 00 -15 conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 28 05 11, COMMON
WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Boston
Healthcare System – Brockton Campus. Interruption time approved by Boston Healthcare System – Brockton Campus may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
01 00 00 -16
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of
Boston Healthcare System – Brockton Campus traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
01 00 00 -17
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
P. Coordination: Coordinate work and products meeting the requirements associated with all applicable specification sections and plans to produce a system complete, functional and ready for the purpose intended. No statements here in shall relieve the Contractor of responsibilities described elsewhere in the contract documents.
1. Pre-worksite Re-visit Requirements … Before starting work in a particular area, visit the worksite and carefully examine the areas to verify complexity, existing conditions and difficulties that will affect work including all work done under various specification sections and the VA. Commencement of work shall be construed as acceptance of the existing conditions and difficulties. No change to the contract price or schedule shall be allowed for work caused by unfamiliarity with the site conditions that are visible or readily construed by an experienced observer. Ground Penetrating Radar service is required to be performed prior to excavation/trenching. A GPR map must be furnished and provided to the Government with the Excavation and Trenching permit to demonstrate the general contractor is familiar with the underground status.
2. Coordinate the location of all work, equipment and components with other trades and equipment installers to prevent interferences, and maintain proper use and access to all items and spaces. General Contractor is responsible for coordinating all equipment and components being installed with the placement location and dimension requirements. Prior to job execution each trade shall formally submit “complete” coordinated shop drawings indicating all equipment and material layouts with locations from walls/columns, bottom/top elevations, vibration isolators, supports, dimensions, utility requirements and equipment submittal numbers for review and approval. Each trade shall maintain a set of working drawings to document as-built information as the work progresses and submit to the Project Engineer monthly for review.
01 00 00 -18
3. All work shall be installed and connected to existing work neatly and carefully and shall be coordinated with other trades to avoid conflicts and to obtain a neat competent installation that will afford maximum accessibility for easy and proper operation, maintenance, service and headroom. All work shall be installed in a manner that permits easy accessibility and proper removal of system components requiring periodic service. Disturbed or damaged work shall be replaced or repaired to new conditions. Any items determined to be in non-compliance shall be corrected by the Contractor at no additional expense to the
Government.
4. The drawings show or describe the general arrangement of equipment, articles, assemblies, appurtenances but do not show all required fittings, drains, air vents, supports and may not identify all required accessories, components, fittings, and offsets that are necessary to properly complete the installation for the purpose intended. The contract drawings are diagrammatic only intended to show general layout of conduit, ductwork, piping, equipment, terminals, specialties and not intended to show all required offsets, details, accessories and equipment to be connected. Provide all necessary fittings, offsets and pipe runs based on field measurements and reviewed coordination drawings. Coordinate with other trades for space available and relative location of equipment and accessories to be connected at all locations. The
Contractor shall alter locations of items where necessary to avoid interference and clearance difficulties. Locations of components and equipment shall be adjusted to accommodate the work with interferences anticipated and encountered. The Contractor shall determine the exact routing and location of systems prior to fabrication and installation. Accurate field measurements and coordination drawings shall be prepared to establish the locations and characteristics of the various systems (new and existing to remain). It is the intent of the drawings/specifications that the Contractor provides all materials, labor and coordination necessary to complete the work described or implied by the contract documents at no additional cost/time to the
Government. The Contractor shall propose with submitted coordination drawings other dimensions with similar characteristics where necessary to avoid interferences and clearance difficulties. Should the contract documents not agree with themselves the greater quantity of superior work and materials shall be performed.
01 00 00 -19
5. Coordinate all mechanical (eg, HVAC), electrical, plumbing (MEP) utility service, excavation/trenching, fire protection sprinkler system shutdowns and space access three (3) weeks in advance with the VA PROJECT ENGINEER
(COR). Due to facility scheduling and access difficulties, some shutdowns and the performance of certain work, as determined by the VA PROJECT ENGINEER
(COR), shall be performed during off-hours (after normal working hours) after coordination with the VA PROJECT ENGINEER (COR). Arrange phases and perform work to insure utility services for other buildings and areas at all times as required. All work being done in staff and patient areas of the Medical Center shall be done after normal working hours.
6. Before placement and installation of work subject to tests the Contractor shall coordinate and notify the VA Project Engineer (COR) in sufficient time to enable VA personnel to be present at the site in time for proper witnessing, testing and field inspection. Such prior notice shall be not less than two (2) weeks unless otherwise designated by the VA PROJECT ENGINEER (COR).
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply
Service, of areas in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existence and conditions of items such as pavement, curbs, building walls, electrical fixtures, equipment, etc., required by drawings to be either reused or relocated, or both.
2. Shall note any discrepancies between drawings and existing conditions at site.
3. Shall designate areas for working space, materials storage and routes of access which have been agreed upon by Contractor and
COR.
01 00 00 -20
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
01 00 00 -21
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas involved. They shall furnish a report on conditions then existing as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor despite protection measures and will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
2. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner
01 00 00 -22 as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by
COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor the Boston Healthcare System –
Brockton Campus.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
01 00 00 -23
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. Environmental Protection
Agency (EPA) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair.
2. Providing waste receptacles at convenient locations and provide regular collection of wastes.
3. Locating equipment wash down areas on site and provide appropriate control of wash-waters.
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials;
and
5. Providing adequately maintained sanitary facilities.
01 00 00 -24
6. The contractor is responsible to comply with EPA Construction
General Permit, which includes storm water discharges from construction activities (such as clearing, grading, excavating, stockpiling, etc.) that disturb one or more acres.
General contractor shall review EPA’s Construction General
Permit requirements, initiate the process, submit complete forms (including a SWPPP), and provide final accepted hard and electronic copies to the VA Healthcare Engineer (COR), A/E and
VA GEMS during the submittal process prior to construction activities and prior to mobilization.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility
01 00 00 -25 services or of fire protection systems and communications systems
(including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS"
(FAR 52.236-2).
1.11 PHYSICAL DATA – SOIL CONDITIONS
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(FAR 52.236-4)
B. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and any available logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans
Affairs, bidders will be permitted to make subsurface explorations of their own at site. The contractor will be held responsible for completing full GPR and providing map survey results prior to excavation.
1.12 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the
Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
01 00 00 -26
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, 01 00 00 -27 materials, and labor required to lay out any part of the work.
The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the
Contracting Officer. The Contractor shall…