About this file

This memorandum provides construction recommendations for the Russian River Campground Access, Phase 2 project. The project scope is to reconstruct approximately 0.9 miles of road within the Chugach National Forest in Alaska. Key elements include replacing two major culverts with 60-inch diameter pipes at milepost locations 612+89 and 615+05. An existing riprap embankment along the Kenai River just outside project limits must be minimally disturbed. Temporary flow diversions for culvert work require a minimum capacity of 15 cubic feet per second at each location, and must be three feet above the stream bottom with a maximum two-foot depth. The contractor must dewater work areas down to the groundwater level and use lined ditches or pipes to convey streamflow during construction. Regulatory agencies may require turbidity monitoring during discharge.

The related federal contract opportunity is solicitation number 69056722B000007 issued by the Department of Transportation Federal Highway Administration. The solicitation documents were attached but no further product, service, or pricing details were provided in the memorandum. The contractor will be responsible for completing the road reconstruction and culvert replacement work according to the specifications outlined.

View the file

Other files for this federal contract opportunity

Other files attached to AK FS CNF 1015(2), Russian River Campground Access Phase 2, newest first.
File Type Posted
BidTab AK FS CNF 101(2).pdf PDF
BidSum AK FS CNF 1015(2).pdf PDF
QA_07-06a-2022.pdf PDF
QA_07-06-2022.pdf PDF
QA_07-05a-2022.pdf PDF
QA_07-05-2022.pdf PDF
Amendment A005.pdf PDF
QA_07-01a-2022.pdf PDF
QA_07-01-2022.pdf PDF
QA_06-30-2022.pdf PDF
Amendment A004.pdf PDF
QA_06-29-2022.pdf PDF
QA_06-24-2022.pdf PDF
Amendment A003.pdf PDF
QA_06-23-2022.pdf PDF
QA_06-22-2022.pdf PDF
Amendment A002.pdf PDF
Amendment A001 .pdf PDF
ak-f-cnf101502_Appr_Calcs_EW_AP603LT_100.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP603LT.xlsx XLSX spreadsheet
ak-f-cnf-101502_Horiz_Ali_Rpt.xlsx XLSX spreadsheet
IFB AK FS CNF 1015(2).pdf PDF
ak-f-cnf_101502_EW_ElemCompQtysRpt_100.pdf PDF
GR 04-22 AK FS CNF 1015(2) - Russian River Campground Phase II Geotechnical Report (REVISED 5-3-22).pdf PDF
RussianRiver_CG_controlsheet.xlsx XLSX spreadsheet
ak-f-cnf-101502_Prof_Rpt_AP640LT.xlsx XLSX spreadsheet
Final ak-f-cnf101502_Plan_Set.pdf PDF
ak-f-cnf_101502_EW_CorrCompQtysRpt_100.pdf PDF
Physical Data.zip ZIP file
ak-f-cnf-101502_Super_Rpt.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP640LT.xlsx XLSX spreadsheet
ak-f-cnf101502_Appr_Calcs_EW_AP640LT_100.pdf PDF
AK_signedSWPPP_AK FS CNF 1015(2) for contract.pdf PDF
ak-f-cnf101502_xs_01_new.pdf PDF
RussianRiverRd_RetainingWallMemo 12-10-2019.pdf PDF
ak-f-cnf101502_xs_01_culv.pdf PDF
ak-f-cnf-101502_Prof_Rpt.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP640LT.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP603LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP640LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP603LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP603LT.xlsx XLSX spreadsheet
ak-f-cnf-101502_Super_Rpt.xlsx XLSX spreadsheet
ak-f-cnf-101502_Prof_Rpt.xlsx XLSX spreadsheet
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Memorandum

Western Federal Lands Highway Division 610 E. Fifth Street

Vancouver, WA 98661-3801

RUSSIAN RIVER CAMPGROUND ACCESS, PHASE II

HYDRAULICS CONSTRUCTION HANDOFF

To: Reuben Johnson, WFLHD Project Manager From: Matthew F. Dillin, P.E., WFLHD Hydraulics Engineer Date: September 21, 2021 Project: AK_FS_CNF_1015(2) – Russian River Campground Access, Phase 2

Background The scope of the Phase 2 project is to reconstruct approximately 0.9 miles of the Russian River Campground Access Road, located in the Chugach National Forest. The Russian River Campground Access Road is a paved two-lane, two-mile loop road. The roadway begins at Milepost 52.5 on the Sterling Highway and terminates at a small day use parking area (Grayling Parking Area). Western Federal Lands Highway Division is providing the full PS&E package with environmental documentation and construction engineering for contract work. The roadway will be owned and maintained by the National Forest Service. Key design elements and construction recommendations related to hydraulics are presented.

Construction Recommendations Major Culverts Two major drainage culverts are proposed within the project limits.

60-inch Culvert – MP 612+89 60-inch Culvert – MP 615+05

Major culverts recommendations:

• Follow recommendations outlined in the dewatering/diversion section below.

• Temporary diversions in place must have a minimum flow capacity equal to the 2-year discharge:

• MP 612+89 15-cfs

• MP 615+05 15-cfs

• Place geotextile filter between riprap and adjacent soils.

• Limit disturbance to existing riprap outfall protection to the maximum extent possible.

• Conserve and reuse any disturbed riprap pieces.

Existing Embankment An existing riprap revetment is located along the Kenai River, just outside project limits.

• Limit disturbance to the existing embankment revetment to the maximum extent possible.

• Conserve and reuse any disturbed riprap pieces.

• When necessary, place geotextile filter between riprap and adjacent soils.

Memo to: Reuben Johnson, WFLHD Project Manager September 21, 2021

Dewatering/Diversions Dewatering/Diversions recommendations:

• Temporary flow deflectors placed for isolating the work area and diverting the stream flow must have a minimum of 3-feet above the stream bottom and be stable assuming 8 feet per second parallel flow and 2-feet maximum depth.

• Use plastic-lined channels or pipes for temporarily conveying stream flow through the construction area.

• Contractor is instructed to work in the dry, achieved through dewatering and/or temporary diversions.

• Full construction area dewatering is expected up to the groundwater level for excavation and installing the culvert, pipe bedding material, backfill, and riprap.

• Diversion will require the use of plastic lined ditches or pipes to temporally convey stream through construction area.

• Temporary diversion in place must have a minimum flow capacity equal to the 2-year discharge.

• Contractor must protect diversion outfalls from erosion.

• Water pumped from work area must be discharged at an upland area near the site.

• Contractor is to limit disturbance to downstream riprap.

• Regulatory agencies may require turbidity control and monitoring, and should be contacted for specific requirements and allowable discharge limits.

Please contact the WFLHD Hydraulics Team if there are any questions.

cc: Sven Leon, WFHD Hydraulics Functional Team Lead

Background
Construction Recommendations