QA_07-06-2022.pdf
PDF 114 KB Posted
- Attached to
- AK FS CNF 1015(2), Russian River Campground Access Phase 2 Federal contract opportunity
- Solicitation number
- 69056722B000007
About this file
This document contains the questions and answers from a pre-bid meeting for federal contract number 69056722B000007 for construction work on the Russian River Campground Access Phase 2 project by the Federal Highway Administration. Key details include that the work involves constructing retaining walls, including soldier pile walls and MSE walls, demolition of an existing gabion wall, and installation of ground anchors and geocomposite sheet drains. The document provides answers to clarify contract requirements and design questions from potential bidders. Bidders are instructed to submit bids based on the quantities shown in the solicitation documents. No extensions to the bid opening date are planned.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AK FS CNF 1015(2)
Russian River Campground Access Phase 2
# General Technical Question Answer Date
1 X What is the intent of the ALLOWANCE quantities shown on sheets B.1‐B.3?
Any added allowance quantity for a pay item increases the estimated quantity for that pay item by the amount of allowance quantity shown on Sheets B.1‐B.3.
6/22/2022
2 X How are the ALLOWANCE quantities used during the course of the contract?
The allowance quantities are part of the estimated quantities for the solicitation that bids are submitted for, and may become the contract quantities if the
Government awards a contract with these estimated quantities.
6/22/2022
3 X Do the ALLOWANCE quantities get paid for regardless of whether they are used?
No. See last paragraph of FP‐14 Subsection
109.05.
6/22/2022
4 X
Please consider delaying the opening of the bid by a week. Receiving/evaluating quotes from busy suppliers/subcontractors is challenging enough to get into a normal bid and sent to
Washington from Alaska. A bid opening that follows a holiday weekend with a lot of specialty suppliers/subcontractors will be very difficult.
The Government does not intent to extend the bid opening date for this project.
Please submit bids according to the solicitation documents.
6/23/2022
5 X
For the construction of MSE walls, is it acceptable to use welded wire forms that deviate from the plans according to the following: W4xW4; 10‐feet length; and 90 degree bend?
This will be addressed under Amendment
A003.
6/23/2022
6 X
Would an alternate Facing Detail ‐ Rock Fill that does not require the primary uniaxial geogrid wrap be allowed?
The Government will not be revising its design or evaluating proposed design changes before contract award. Please submit bids according to the solicitation documents.
6/23/2022
7 X
Drawing No. H.8 detail “anchor detail” indicates the strand anchor and an 8” diameter pipe penetrates through both flanges and the web of each soldier pile. Typically a waler would be used across the face of soldier piles to prevent weakening of the soldier pile caused by penetrations. Please confirm the design is correct.
The design shown on the plans is correct. 6/23/2022
8 X
In addition to the question #7, shop cutting of these penetrations prior to galvanizing will result in limited adjustment ability to pile tip elevations. Will field cutting via torch and field galvanizing repairs be acceptable?
This will be addressed under Amendment
A003.
6/23/2022
Check General or Technical
9 X
The strand anchor bond length is subject to change based on contractor design and results of performance/proof tests. Initial discussion with DSI indicates a 15‐ft. bond length will not be sufficient for most anchors. Please address the following:
a. Strand anchors are intended to be manufactured/delivered to jobsite based on contractor design prior to construction. These are long lead items and adjustments to anchor lengths will not be feasible once materials have been ordered and construction has started.
b. Shall bidders assume a 15‐ft. bond length as the basis of bid and that additional anchor bond length needed to meet the design criteria will be paid for via change order upon completion of the contractor’s anchor design calculation submittal?
Bidders should not assume a 15‐foot bond length as the basis of bid because the plans show a minimum bond length of 15 feet.
Determine actual bond lengths according to the solicitation documents; see
Subsections 109.05, 256.11, and 256.12;
and bid the quantities shown in the bid schedule.
6/23/2022
10 X
Would WFLHD consider removing the requirements of Subsection 255.02A since there there has not been 3 projects with similar complexity constructed in the State of Alaska over the past 5 years, so sourcing personnel to meet this requirement would require the Small
Business Contractor to search the “Lower 48
States” for a Large Contractor with this specific attribute at a higher cost to the project.
The Government will not be removing this requirement. Please submit bids according to the solicitation documents.
6/23/2022
11 X The requirements of Subsections 256.03(e) and
263.03(b) are identical. Is this correct?
This will be addressed under Amendment
A003.
6/23/2022
12 X
Do the qualification requirements of Subsection
263.03(b) apply to the Contractor or subcontractor performing the Soldier Pile installation, Ground Anchor installation, excavation, installing the lagging, and installing the geocomposite sheet drain?
The qualification requirements of
Subsection 263.03(b) applies to
Contractors or subcontractors performing work under Section 263.
6/23/2022
13 X
Is it required to have one contractor or subcontractor perform the soldier pile work, ground anchor work, lagging and geocomposite sheet drain to adhere to Subsection 263.03(b)?
The solicitation requirements do not require a single contractor or subcontractor to perform all of this listed work.
6/23/2022
14 X
Please confirm structural excavation necessary for construction of the walls will be measured for payment and compensated via pay item
20401‐0000.
See Subsections 109.05, 208.12, 208.13, and 209.12.
6/29/2022
15 X Can 4 x 4 W4 x W4 welded wire forms be used in lieu of 4 x 4 W5 x W5 welded wire forms?
No. Please submit bids according to the solicitation documents.
6/30/2022
16 X
Can you provide us with some WFL projects that would meet the requirements "soldier piles retaining wall projects of similar size and complexity over the past 5 years"?
Is there a way to see a general list of all the vendors that are asking questions regarding the project? In general for Alaska, almost no vendors are listed anymore on SAM's interested vendors list?
FHWA doesn’t maintain a plan holders list. 6/30/2022
17 X
Plan sheets D.3 through D.5 indicate the scope includes demolition of a continuous existing gabion wall that is approximately 1,600 linear feet. Page 54 of the Geotechnical Report provides a single photograph of the existing gabion basket wall at STA 608+20. Page 55 of the Geotechnical Report provides a photograph of an existing bin wall and rip rap armoring at the Toe of Schooner Bend Landslide Area. The drawings do not include any reference to this existing bin wall. Please confirm the existing gabion wall runs full length as depicted in the
‘D’ drawings and the existing bin wall and associated rip rap armoring remain intact and do not interfere with construction of the new
MSE/Soldier Pile walls.
Removing 1,600 linear feet of existing gabion wall is not in the scope of work. See
Removal of obstruction (gabion wall) callout in the profile view of Sheet D.4, and the existing bin wall to remain callout in the plan view on Sheet D.4, and submit bids according to the solicitation documents.
6/30/2022
18 X
Plan sheet H.12 indicates gabion rock at face
12” min at mid height of panel. Specification
255.05 states gabion rock shall be placed within
18” of wall face. Please advise which is correct.
Both. 6/30/2022
19 X
Plan Please confirm gabion rock placed at the face of MSE wall is not measured for payment and is inclusive of pay item 25501‐1000.
In accordance with the first sentence of FP‐
14 Subsection 255.07 and the bid schedule;
gabions gabion rocks for MSE wall are not measured for payment. See Subsection
109.05 and please submit bids according to the solicitation documents.
7/1/2022
(Revised)
6/30/2022
20 X
Plan sheet H.12 “facing detail” indicates geotextile filter, class 2, type A, non‐woven is placed inside the reinforcement geogrid, type
III. Does this extend to the full grid length ‘L’ to match the geogrid or shall the geotextile filter, class 2, type A only be placed to the 4’ return limit? The geotextile appears to terminate in the facing detail.
No, the installation limits for the geotextile filter, class 2, type A, non‐woven are as shown in the facing detail on Sheet H.12.
6/30/2022
21 X
Please confirm reinforcement geogrid, type III and geotextile filter, class 2, type A, non‐woven placed within the MSE wall limits are not measured for payment and are inclusive of pay item 25501‐1000.
In accordance with the first sentence of FP‐
14 Subsection 255.07 and the bid schedule;
geogrid, type III and geotextile filter, class
2, type A, non‐woven placed within the
MSE wall limits are not measured for payment. See Subsection 109.05 and please submit bids according to the solicitation documents.
6/30/2022
22 X
Please confirm select granular backfill placed within the MSE grid length limits is not measured for payment and is inclusive of pay item 25501‐1000.
In accordance with the first sentence of FP‐
14 Subsection 255.07 and the bid schedule;
select granular backfill for MSE walls are not measured for payment. See Subsection
109.05 and please submit bids according to the solicitation documents.
6/30/2022
23 X
Confirm geocomposite sheet drain shown on sheet H.12 is not measured for payment and is inclusive of pay item 25501‐1000.
In accordance with the first sentence of FP‐
14 Subsection 255.07 and the bid schedule;
geocomposite sheet drain for MSE walls are not measured for payment. See
Subsection 109.05 and please submit bids according to the solicitation documents.
6/30/2022
24 X Do owner housing and vehicles need to be provided during winter shutdown?
No. Housing and Vehicles for Government personnel will not be required during periods of winter shutdown
7/1/2022
25 X On plan sheet G.1, what is the allowable pipe material RC?
This will be addressed under Amendment
A005.
7/1/2022
26 X Should there be a Removal of Asphalt
Pavement contract bid item?
There is no Removal of Asphalt Pavement contract bid item for this project. See
Subsection 109.05, and submit bids according to the solicitation documents.
7/5/2022
27 X Which contract pay item is Removal of Asphalt
Pavement indirectly associated with?
The Government does not determine how bidders estimate the work they are to perform. Please submit bids according to the solicitation documents.
7/5/2022
28 X
Which materials on the drawings H.12 are considered Foundation Fill material? The
Foundation Fill material qty is on Sheet H.11.
This will be addressed under Amendment
A005.
7/5/2022
29 X
Sheet H.4 states there are 68 ground anchors and 4 performance tests. There are 64 piles on the RT wall that receive anchors. The bid schedule includes 71 ground anchors and 5 performance tests. Is the bid schedule correct?
Please submit bids for the quantities shown in the solicitation documents. Note that the bid schedule includes allowances that are not shown in the other plan sections.
7/5/2022
30 X
Will Amendment 5 be including an extension to the bid opening? We are really down to the wire to mail our bids out and suppliers/subs are holding their quotes until the amendment is issued.
We have posted Amendment A005. The
Government does not intend to extend the bid opening date for this project. Please submit bids according to the solicitation documents, and note that Page A‐2 of the solicitation states bids may be modified or withdrawn by email.
7/5/2022
31 X
At Section 609+82.41, how does the select borrow confined by the subgrade, existing ground, and soldier pile wall get paid for?
This work is part of the work specified under Sections 208 and 263. See
Subsections 109.05, 208.13, and 263.10;
and please submit bids according to the solicitation documents.
7/6/2022