This document contains answers to technical questions regarding federal solicitation number 69056722B000007 for construction of Phase 2 of the Russian River Campground Access project in Alaska. The solicitation involves construction of mechanically stabilized earth walls and soldier pile walls. Key details include that bidders should not assume a 15-foot bond length for strand anchors and should determine actual bond lengths according to specifications. Structural excavation necessary for wall construction will be measured for payment under pay item 20401-0000. Qualification requirements for soldier pile installation, ground anchor installation, excavation, lagging installation, and geocomposite drain installation apply to contractors or subcontractors performing that work. Housing and vehicles for government personnel will not be required during winter shutdown periods. Allowable pipe material RC will be addressed in Amendment A005.

View the file

Other files for this federal contract opportunity

Other files attached to AK FS CNF 1015(2), Russian River Campground Access Phase 2, newest first.
File Type Posted
BidTab AK FS CNF 101(2).pdf PDF
BidSum AK FS CNF 1015(2).pdf PDF
QA_07-06a-2022.pdf PDF
QA_07-06-2022.pdf PDF
QA_07-05a-2022.pdf PDF
Amendment A005.pdf PDF
QA_07-05-2022.pdf PDF
QA_07-01-2022.pdf PDF
QA_06-30-2022.pdf PDF
Amendment A004.pdf PDF
QA_06-29-2022.pdf PDF
QA_06-24-2022.pdf PDF
Amendment A003.pdf PDF
QA_06-23-2022.pdf PDF
QA_06-22-2022.pdf PDF
Amendment A002.pdf PDF
Amendment A001 .pdf PDF
ak-f-cnf_101502_EW_ElemCompQtysRpt_100.pdf PDF
GR 04-22 AK FS CNF 1015(2) - Russian River Campground Phase II Geotechnical Report (REVISED 5-3-22).pdf PDF
RussianRiver_CG_controlsheet.xlsx XLSX spreadsheet
ak-f-cnf-101502_Prof_Rpt_AP640LT.xlsx XLSX spreadsheet
Final ak-f-cnf101502_Plan_Set.pdf PDF
AK_signedSWPPP_AK FS CNF 1015(2) for contract.pdf PDF
ak-f-cnf101502_xs_01_new.pdf PDF
RussianRiverRd_RetainingWallMemo 12-10-2019.pdf PDF
ak-f-cnf101502_xs_01_culv.pdf PDF
Russian River - Hydraulics_Construction_Handoff_Memo.pdf PDF
ak-f-cnf-101502_Prof_Rpt.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP640LT.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP603LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP640LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP603LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP603LT.xlsx XLSX spreadsheet
ak-f-cnf-101502_Super_Rpt.xlsx XLSX spreadsheet
ak-f-cnf-101502_Prof_Rpt.xlsx XLSX spreadsheet
ak-f-cnf_101502_EW_CorrCompQtysRpt_100.pdf PDF
Physical Data.zip ZIP file
ak-f-cnf-101502_Super_Rpt.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP640LT.xlsx XLSX spreadsheet
ak-f-cnf101502_Appr_Calcs_EW_AP640LT_100.pdf PDF
ak-f-cnf101502_Appr_Calcs_EW_AP603LT_100.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP603LT.xlsx XLSX spreadsheet
ak-f-cnf-101502_Horiz_Ali_Rpt.xlsx XLSX spreadsheet
IFB AK FS CNF 1015(2).pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AK FS CNF 1015(2)

Russian River Campground Access Phase 2

# General Technical Question Answer Date

1 X What is the intent of the ALLOWANCE quantities shown on sheets B.1-B.3?

Any added allowance quantity for a pay item increases the estimated quantity for that pay item by the amount of allowance quantity shown on Sheets B.1-B.3.

6/22/2022

2 X How are the ALLOWANCE quantities used during the course of the contract?

The allowance quantities are part of the estimated quantities for the solicitation that bids are submitted for, and may become the contract quantities if the Government awards a contract with these estimated quantities.

6/22/2022

3 X Do the ALLOWANCE quantities get paid for regardless of whether they are used?

No. See last paragraph of FP-14 Subsection 109.05.

6/22/2022

4 X

Please consider delaying the opening of the bid by a week. Receiving/evaluating quotes from busy suppliers/subcontractors is challenging enough to get into a normal bid and sent to Washington from Alaska. A bid opening that follows a holiday weekend with a lot of specialty suppliers/subcontractors will be very difficult.

The Government does not intent to extend the bid opening date for this project. Please submit bids according to the solicitation documents.

6/23/2022

5 X

For the construction of MSE walls, is it acceptable to use welded wire forms that deviate from the plans according to the following: W4xW4; 10-feet length; and 90 degree bend?

This will be addressed under Amendment A003.

6/23/2022

6 X Would an alternate Facing Detail - Rock Fill that does not require the primary uniaxial geogrid wrap be allowed?

The Government will not be revising its design or evaluating proposed design changes before contract award. Please submit bids according to the solicitation documents.

6/23/2022

7 X

Drawing No. H.8 detail “anchor detail” indicates the strand anchor and an 8” diameter pipe penetrates through both flanges and the web of each soldier pile. Typically a waler would be used across the face of soldier piles to prevent weakening of the soldier pile caused by penetrations. Please confirm the design is correct.

The design shown on the plans is correct. 6/23/2022

8 X

In addition to the question #7, shop cutting of these penetrations prior to galvanizing will result in limited adjustment ability to pile tip elevations. Will field cutting via torch and field galvanizing repairs be acceptable?

This will be addressed under Amendment A003.

6/23/2022

Check General or Technical

9 X

The strand anchor bond length is subject to change based on contractor design and results of performance/proof tests. Initial discussion with DSI indicates a 15-ft. bond length will not be sufficient for most anchors. Please address the following:

a. Strand anchors are intended to be manufactured/delivered to jobsite based on contractor design prior to construction. These are long lead items and adjustments to anchor lengths will not be feasible once materials have been ordered and construction has started.

b. Shall bidders assume a 15-ft. bond length as the basis of bid and that additional anchor bond length needed to meet the design criteria will be paid for via change order upon completion of the contractor’s anchor design calculation submittal?

Bidders should not assume a 15-foot bond length as the basis of bid because the plans show a minimum bond length of 15 feet.

Determine actual bond lengths according to the solicitation documents; see Subsections 109.05, 256.11, and 256.12; and bid the quantities shown in the bid schedule.

6/23/2022

10 X

Would WFLHD consider removing the requirements of Subsection 255.02A since there there has not been 3 projects with similar complexity constructed in the State of Alaska over the past 5 years, so sourcing personnel to meet this requirement would require the Small Business Contractor to search the “Lower 48 States” for a Large Contractor with this specific attribute at a higher cost to the project.

The Government will not be removing this requirement. Please submit bids according to the solicitation documents.

6/23/2022

11 X The requirements of Subsections 256.03(e) and 263.03(b) are identical. Is this correct?

This will be addressed under Amendment A003.

6/23/2022

12 X

Do the qualification requirements of Subsection 263.03(b) apply to the Contractor or subcontractor performing the Soldier Pile installation, Ground Anchor installation, excavation, installing the lagging, and installing the geocomposite sheet drain?

The qualification requirements of Subsection 263.03(b) applies to Contractors or subcontractors performing work under Section 263.

6/23/2022

13 X

Is it required to have one contractor or subcontractor perform the soldier pile work, ground anchor work, lagging and geocomposite sheet drain to adhere to Subsection 263.03(b)?

The solicitation requirements do not require a single contractor or subcontractor to perform all of this listed work.

6/23/2022

14 X

Please confirm structural excavation necessary for construction of the walls will be measured for payment and compensated via pay item 20401-0000.

See Subsections 109.05, 208.12, 208.13, and 209.12.

6/29/2022

15 X Can 4 x 4 W4 x W4 welded wire forms be used in lieu of 4 x 4 W5 x W5 welded wire forms?

No. Please submit bids according to the solicitation documents.

6/30/2022

16 X

Can you provide us with some WFL projects that would meet the requirements "soldier piles retaining wall projects of similar size and complexity over the past 5 years"?

Is there a way to see a general list of all the vendors that are asking questions regarding the project? In general for Alaska, almost no vendors are listed anymore on SAM's interested vendors list?

FHWA doesn’t maintain a plan holders list. 6/30/2022

17 X

Plan sheets D.3 through D.5 indicate the scope includes demolition of a continuous existing gabion wall that is approximately 1,600 linear feet. Page 54 of the Geotechnical Report provides a single photograph of the existing gabion basket wall at STA 608+20. Page 55 of the Geotechnical Report provides a photograph of an existing bin wall and rip rap armoring at the Toe of Schooner Bend Landslide Area. The drawings do not include any reference to this existing bin wall. Please confirm the existing gabion wall runs full length as depicted in the ‘D’ drawings and the existing bin wall and associated rip rap armoring remain intact and do not interfere with construction of the new MSE/Soldier Pile walls.

Removing 1,600 linear feet of existing gabion wall is not in the scope of work. See Removal of obstruction (gabion wall) callout in the profile view of Sheet D.4, and the existing bin wall to remain callout in the plan view on Sheet D.4, and submit bids according to the solicitation documents.

6/30/2022

18 X

Plan sheet H.12 indicates gabion rock at face 12” min at mid height of panel. Specification

255.05 states gabion rock shall be placed within 18” of wall face. Please advise which is correct.

Both. 6/30/2022

19 X Plan Please confirm gabion rock placed at the face of MSE wall is not measured for payment and is inclusive of pay item 25501-1000.

In accordance with the first sentence of FP- 14 Subsection 255.07 and the bid schedule;

gabions gabion rocks for MSE wall are not measured for payment. See Subsection

109.05 and please submit bids according to the solicitation documents.

7/1/2022 (Revised)

6/30/2022

20 X

Plan sheet H.12 “facing detail” indicates geotextile filter, class 2, type A, non-woven is placed inside the reinforcement geogrid, type III. Does this extend to the full grid length ‘L’ to match the geogrid or shall the geotextile filter, class 2, type A only be placed to the 4’ return limit? The geotextile appears to terminate in the facing detail.

No, the installation limits for the geotextile filter, class 2, type A, non-woven are as shown in the facing detail on Sheet H.12.

6/30/2022

21 X

Please confirm reinforcement geogrid, type III and geotextile filter, class 2, type A, non-woven placed within the MSE wall limits are not measured for payment and are inclusive of pay item 25501-1000.

In accordance with the first sentence of FP- 14 Subsection 255.07 and the bid schedule;

geogrid, type III and geotextile filter, class 2, type A, non-woven placed within the MSE wall limits are not measured for payment.

See Subsection 109.05 and please submit bids according to the solicitation documents.

6/30/2022

22 X

Please confirm select granular backfill placed within the MSE grid length limits is not measured for payment and is inclusive of pay item 25501-1000.

In accordance with the first sentence of FP- 14 Subsection 255.07 and the bid schedule;

select granular backfill for MSE walls are not measured for payment. See Subsection

109.05 and please submit bids according to the solicitation documents.

6/30/2022

23 X Confirm geocomposite sheet drain shown on sheet H.12 is not measured for payment and is inclusive of pay item 25501-1000.

In accordance with the first sentence of FP- 14 Subsection 255.07 and the bid schedule;

geocomposite sheet drain for MSE walls are not measured for payment. See Subsection

109.05 and please submit bids according to the solicitation documents.

6/30/2022

24 X Do owner housing and vehicles need to be provided during winter shutdown?

No. Housing and Vehicles for Government personnel will not be required during periods of winter shutdown

7/1/2022

25 X On plan sheet G.1, what is the allowable pipe material RC?

This will be addressed under Amendment A005.

7/1/2022