BidTab AK FS CNF 101(2).pdf

PDF 706 KB Posted

Attached to
AK FS CNF 1015(2), Russian River Campground Access Phase 2 Federal contract opportunity
Solicitation number
69056722B000007
Issued by
Department of Transportation Federal Highway Administration

About this file

This tabulation of bids report summarizes bids received in response to solicitation number 69056722B000007 for the Russian River Campground Access Phase 2 project. The project involves construction services including roadway excavation and construction, drainage installation, retaining walls, guardrails and fencing. Four contractors submitted bids by the July 8th deadline - Qayaq Construction LLC, Bristol Prime Contractors LLC, Tutka LLC, and the engineer's estimate. Bid amounts ranged from $7.7 million for the engineer's estimate to $15.5 million for Tutka LLC. The report provides unit pricing for over 150 line items and totals for each contractor. The Department of Transportation Federal Highway Administration will award the contract and notices an anticipated award date.

View the file

Other files for this federal contract opportunity

Other files attached to AK FS CNF 1015(2), Russian River Campground Access Phase 2, newest first.
File Type Posted
BidSum AK FS CNF 1015(2).pdf PDF
QA_07-06a-2022.pdf PDF
QA_07-06-2022.pdf PDF
QA_07-05a-2022.pdf PDF
QA_07-05-2022.pdf PDF
Amendment A005.pdf PDF
QA_07-01a-2022.pdf PDF
QA_07-01-2022.pdf PDF
QA_06-30-2022.pdf PDF
Amendment A004.pdf PDF
QA_06-29-2022.pdf PDF
Amendment A003.pdf PDF
QA_06-24-2022.pdf PDF
QA_06-23-2022.pdf PDF
QA_06-22-2022.pdf PDF
Amendment A002.pdf PDF
Amendment A001 .pdf PDF
ak-f-cnf101502_Appr_Calcs_EW_AP603LT_100.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP603LT.xlsx XLSX spreadsheet
ak-f-cnf-101502_Horiz_Ali_Rpt.xlsx XLSX spreadsheet
IFB AK FS CNF 1015(2).pdf PDF
ak-f-cnf_101502_EW_CorrCompQtysRpt_100.pdf PDF
Physical Data.zip ZIP file
ak-f-cnf-101502_Super_Rpt.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP640LT.xlsx XLSX spreadsheet
ak-f-cnf101502_Appr_Calcs_EW_AP640LT_100.pdf PDF
AK_signedSWPPP_AK FS CNF 1015(2) for contract.pdf PDF
ak-f-cnf101502_xs_01_new.pdf PDF
RussianRiverRd_RetainingWallMemo 12-10-2019.pdf PDF
ak-f-cnf101502_xs_01_culv.pdf PDF
Russian River - Hydraulics_Construction_Handoff_Memo.pdf PDF
ak-f-cnf-101502_Prof_Rpt.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP640LT.pdf PDF
ak-f-cnf-101502_Prof_Rpt_AP603LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP640LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP603LT.pdf PDF
ak-f-cnf-101502_Horiz_Ali_Rpt_AP603LT.xlsx XLSX spreadsheet
ak-f-cnf-101502_Super_Rpt.xlsx XLSX spreadsheet
ak-f-cnf-101502_Prof_Rpt.xlsx XLSX spreadsheet
ak-f-cnf_101502_EW_ElemCompQtysRpt_100.pdf PDF
GR 04-22 AK FS CNF 1015(2) - Russian River Campground Phase II Geotechnical Report (REVISED 5-3-22).pdf PDF
RussianRiver_CG_controlsheet.xlsx XLSX spreadsheet
ak-f-cnf-101502_Prof_Rpt_AP640LT.xlsx XLSX spreadsheet
Final ak-f-cnf101502_Plan_Set.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 07/08/22

1 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Contractor Responsive?

Engineer's Estimate

Bristol Prime Contractors, LLC

Qayaq Construction LLC

Tutka, LLC

Base Schedule A

$7,731,881.00

$12,139,898.49

$10,474,759.00

$15,465,034.00

Option: X

$779,809.00

$2,369,040.00

$918,003.00

$1,530,005.00

Contractor Responsive?

Engineer's Estimate

Bristol Prime Contractors, LLC

Qayaq Construction LLC

Tutka, LLC

Total Base Schedule A and Option(s): X

$8,511,690.00

$14,508,938.49

$11,392,762.00

$16,995,039.00

2 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: X

Schedule Type: Options

Solcitation No:

Division: Western Federal Lands

State: AK County: Kenai Peninsula

Federal Land: Opened at: WFL, Vancouver WA

Opened by: Marino Chea

Date: 07/08/22

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Qayaq Construction LLC $918,003.00 6700 Artic Spur Road Anchorage, AK 99518

Tutka, LLC $1,530,005.00 2485 E Zak Circle, Suite A Wasilla, AK 99654

Bristol Prime Contractors, LLC Calculated amount below does not match with Contractor's total bid for Schedule A.

$2,369,040.00 111 W. 16th Avenue, Third Floor Anchorage , AK 99501

Engineer's Estimate $779,809.00

Contracting Officer 07/08/2022

3 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0720 26303-0000 CONCRETE LAGGING (CAST-IN-PLACE CONCRETE FASCIA)

Qayaq Construction LLC $93.00 $918,003.00 Tutka, LLC $155.00 $1,530,005.00 Bristol Prime Contractors, LLC $240.00 $2,369,040.00 Engineer's Estimate 9,871 SQFT $79.00 $779,809.00

Total Schedule - All Items

Qayaq Construction LLC $918,003.00 Tutka, LLC $1,530,005.00 Bristol Prime Contractors, LLC $2,369,040.00 Engineer's Estimate $779,809.00

4 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Solcitation No:

Division: Western Federal Lands

State: AK County: Kenai Peninsula

Federal Land: Opened at: WFL, Vancouver WA

Opened by: Marino Chea

Date: 07/08/22

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Qayaq Construction LLC $10,474,759.00 6700 Artic Spur Road Anchorage, AK 99518

Bristol Prime Contractors, LLC Calculated amount below does not match with Contractor's total bid for Schedule A.

$12,139,898.49 111 W. 16th Avenue, Third Floor Anchorage , AK 99501

Tutka, LLC $15,465,034.00 2485 E Zak Circle, Suite A Wasilla, AK 99654

Engineer's Estimate $7,731,881.00

5 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Qayaq Construction LLC Lump Sum $850,000.00 Bristol Prime Contractors, LLC Lump Sum $795,114.00 Tutka, LLC Lump Sum $3,500,000.00 Engineer's Estimate ALL LPSM Lump Sum $828,000.00

A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

Qayaq Construction LLC Lump Sum $102,000.00 Bristol Prime Contractors, LLC Lump Sum $114,000.00 Tutka, LLC Lump Sum $100,000.00 Engineer's Estimate ALL LPSM Lump Sum $103,000.00

A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE

Qayaq Construction LLC Lump Sum $166,000.00 Bristol Prime Contractors, LLC Lump Sum $269,700.00 Tutka, LLC Lump Sum $275,000.00 Engineer's Estimate ALL LPSM Lump Sum $113,000.00

A0080 15401-0000 CONTRACTOR TESTING

Qayaq Construction LLC Lump Sum $421,000.00 Bristol Prime Contractors, LLC Lump Sum $63,000.00 Tutka, LLC Lump Sum $195,000.00 Engineer's Estimate ALL LPSM Lump Sum $51,000.00

A0100 15501-0000 CONSTRUCTION SCHEDULE

Qayaq Construction LLC Lump Sum $30,000.00 Bristol Prime Contractors, LLC Lump Sum $357,085.00 Tutka, LLC Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $13,000.00

A0120 15703-2000 SOIL EROSION CONTROL, TEMPORARY TURF ESTABLISHMENT

Qayaq Construction LLC $13,000.00 $27,300.00 Bristol Prime Contractors, LLC $36,161.90 $75,939.99 Tutka, LLC $38,000.00 $79,800.00 Engineer's Estimate 2.1 ACRE $6,250.00 $13,125.00

6 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0140 15705-1300 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL

Qayaq Construction LLC $160.00 $30,400.00 Bristol Prime Contractors, LLC $240.00 $45,600.00 Tutka, LLC $700.00 $133,000.00 Engineer's Estimate 190 LNFT $230.00 $43,700.00

A0160 15705-1400 SOIL EROSION CONTROL, FIBER ROLL (AT CULVERT INLET)

Qayaq Construction LLC $13.00 $8,580.00 Bristol Prime Contractors, LLC $17.00 $11,220.00 Tutka, LLC $17.00 $11,220.00 Engineer's Estimate 660 LNFT $8.00 $5,280.00

A0180 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Qayaq Construction LLC $8.00 $37,200.00 Bristol Prime Contractors, LLC $10.00 $46,500.00 Tutka, LLC $8.50 $39,525.00 Engineer's Estimate 4,650 LNFT $8.00 $37,200.00

A0200 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FIBER ROLL)

Qayaq Construction LLC $235.00 $2,820.00 Bristol Prime Contractors, LLC $780.00 $9,360.00 Tutka, LLC $475.00 $5,700.00 Engineer's Estimate 12 EACH $50.00 $600.00

A0220 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FILTER ROCK)

Qayaq Construction LLC $250.00 $3,250.00 Bristol Prime Contractors, LLC $752.00 $9,776.00 Tutka, LLC $550.00 $7,150.00 Engineer's Estimate 13 EACH $400.00 $5,200.00

A0240 15801-0000 WATERING FOR DUST CONTROL

Qayaq Construction LLC $90.00 $27,000.00 Bristol Prime Contractors, LLC $450.00 $135,000.00 Tutka, LLC $100.00 $30,000.00 Engineer's Estimate 300 MGAL $120.00 $36,000.00

7 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0260 20101-0000 CLEARING AND GRUBBING

Qayaq Construction LLC $13,000.00 $39,000.00 Bristol Prime Contractors, LLC $30,000.00 $90,000.00 Tutka, LLC $65,000.00 $195,000.00 Engineer's Estimate 3.0 ACRE $14,500.00 $43,500.00

A0280 20301-0100 REMOVAL OF BOLLARD

Qayaq Construction LLC $1,000.00 $3,000.00 Bristol Prime Contractors, LLC $500.00 $1,500.00 Tutka, LLC $250.00 $750.00 Engineer's Estimate 3 EACH $300.00 $900.00

A0300 20301-1100 REMOVAL OF GATE

Qayaq Construction LLC $900.00 $900.00 Bristol Prime Contractors, LLC $3,000.00 $3,000.00 Tutka, LLC $1,000.00 $1,000.00 Engineer's Estimate 1 EACH $1,250.00 $1,250.00

A0320 20301-1900 REMOVAL OF PIPE CULVERT

Qayaq Construction LLC $3,300.00 $13,200.00 Bristol Prime Contractors, LLC $600.00 $2,400.00 Tutka, LLC $3,200.00 $12,800.00 Engineer's Estimate 4 EACH $1,600.00 $6,400.00

A0340 20301-2400 REMOVAL OF SIGN

Qayaq Construction LLC $120.00 $1,080.00 Bristol Prime Contractors, LLC $220.00 $1,980.00 Tutka, LLC $300.00 $2,700.00 Engineer's Estimate 9 EACH $210.00 $1,890.00

A0360 20301-2700 REMOVAL OF STRUCTURE (TIMBER STAIRWAY)

Qayaq Construction LLC $6,000.00 $6,000.00 Bristol Prime Contractors, LLC $550.00 $550.00 Tutka, LLC $3,500.00 $3,500.00 Engineer's Estimate 1 EACH $1,000.00 $1,000.00

8 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0380 20301-3400 REMOVAL OF WHEELSTOP

Qayaq Construction LLC $380.00 $2,280.00 Bristol Prime Contractors, LLC $100.00 $600.00 Tutka, LLC $150.00 $900.00 Engineer's Estimate 6 EACH $200.00 $1,200.00

A0400 20302-1200 REMOVAL OF GUARDRAIL

Qayaq Construction LLC $2.50 $3,377.50 Bristol Prime Contractors, LLC $42.00 $56,742.00 Tutka, LLC $2.50 $3,377.50 Engineer's Estimate 1,351 LNFT $6.00 $8,106.00

A0420 20302-1300 REMOVAL OF GUARDRAIL, CONCRETE BARRIER

Qayaq Construction LLC $35.00 $4,375.00 Bristol Prime Contractors, LLC $20.00 $2,500.00 Tutka, LLC $50.00 $6,250.00 Engineer's Estimate 125 LNFT $25.00 $3,125.00

A0440 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (GABION WALL)

Qayaq Construction LLC Lump Sum $12,000.00 Bristol Prime Contractors, LLC Lump Sum $30,000.00 Tutka, LLC Lump Sum $24,000.00 Engineer's Estimate ALL LPSM Lump Sum $16,000.00

A0460 20401-0000 ROADWAY EXCAVATION

Qayaq Construction LLC $33.00 $469,095.00 Bristol Prime Contractors, LLC $13.00 $184,795.00 Tutka, LLC $36.00 $511,740.00 Engineer's Estimate 14,215 CUYD $22.00 $312,730.00

A0480 20411-0000 SELECT BORROW

Qayaq Construction LLC $32.00 $816,000.00 Bristol Prime Contractors, LLC $16.50 $420,750.00 Tutka, LLC $33.00 $841,500.00 Engineer's Estimate 25,500 TON $15.00 $382,500.00

9 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0500 20701-0100 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE A (WOVEN)

Qayaq Construction LLC $2.10 $31,668.00 Bristol Prime Contractors, LLC $8.00 $120,640.00 Tutka, LLC $3.80 $57,304.00 Engineer's Estimate 15,080 SQYD $3.25 $49,010.00

A0520 20702-0300 GEOTEXTILE FILTER, CLASS 1, TYPE C

Qayaq Construction LLC $7.00 $1,750.00 Bristol Prime Contractors, LLC $30.00 $7,500.00 Tutka, LLC $3.20 $800.00 Engineer's Estimate 250 SQYD $8.00 $2,000.00

A0540 20802-0000 FOUNDATION FILL

Qayaq Construction LLC $155.00 $71,300.00 Bristol Prime Contractors, LLC $100.00 $46,000.00 Tutka, LLC $120.00 $55,200.00 Engineer's Estimate 460 CUYD $150.00 $69,000.00

A0560 21101-1000 ROADWAY OBLITERATION, METHOD 1

Qayaq Construction LLC $35.00 $7,700.00 Bristol Prime Contractors, LLC $23.00 $5,060.00 Tutka, LLC $25.00 $5,500.00 Engineer's Estimate 220 SQYD $20.00 $4,400.00

A0580 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2 (PROTECTIVE APRON)

Qayaq Construction LLC $300.00 $21,000.00 Bristol Prime Contractors, LLC $330.00 $23,100.00 Tutka, LLC $265.00 $18,550.00 Engineer's Estimate 70 CUYD $170.00 $11,900.00

A0600 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3 (HEADWALL)

Qayaq Construction LLC $250.00 $33,250.00 Bristol Prime Contractors, LLC $300.00 $39,900.00 Tutka, LLC $275.00 $36,575.00 Engineer's Estimate 133 CUYD $80.00 $10,640.00

10 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0620 25101-0400 PLACED RIPRAP, METHOD A, CLASS 4 (RIPRAP END TREATMENT)

Qayaq Construction LLC $300.00 $33,000.00 Bristol Prime Contractors, LLC $275.00 $30,250.00 Tutka, LLC $280.00 $30,800.00 Engineer's Estimate 110 CUYD $140.00 $15,400.00

A0640 25120-0100 RIPRAP DITCH, METHOD A, CLASS 1

Qayaq Construction LLC $45.00 $27,900.00 Bristol Prime Contractors, LLC $75.00 $46,500.00 Tutka, LLC $45.00 $27,900.00 Engineer's Estimate 620 LNFT $32.00 $19,840.00

A0660 25201-1000 SPECIAL ROCK EMBANKMENT, MECHANICALLY-PLACED

Qayaq Construction LLC $190.00 $294,500.00 Bristol Prime Contractors, LLC $260.00 $403,000.00 Tutka, LLC $270.00 $418,500.00 Engineer's Estimate 1,550 CUYD $160.00 $248,000.00

A0680 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE

Qayaq Construction LLC $132.00 $1,939,080.00 Bristol Prime Contractors, LLC $60.00 $881,400.00 Tutka, LLC $175.00 $2,570,750.00 Engineer's Estimate 14,690 SQFT $72.00 $1,057,680.00

A0700 25601-0000 GROUND ANCHOR

Qayaq Construction LLC $8,600.00 $610,600.00 Bristol Prime Contractors, LLC $22,500.00 $1,597,500.00 Tutka, LLC $13,000.00 $923,000.00 Engineer's Estimate 71 EACH $5,000.00 $355,000.00

A0720 25605-0000 PERFORMANCE TEST

Qayaq Construction LLC $1,050.00 $5,250.00 Bristol Prime Contractors, LLC $2,000.00 $10,000.00 Tutka, LLC $1,300.00 $6,500.00 Engineer's Estimate 5 EACH $7,500.00 $37,500.00

11 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0740 26302-0000 TIMBER LAGGING

Qayaq Construction LLC $116.00 $971,964.00 Bristol Prime Contractors, LLC $90.00 $754,110.00 Tutka, LLC $130.00 $1,089,270.00 Engineer's Estimate 8,379 SQFT $100.00 $837,900.00

A0760 30202-2000 ROADWAY AGGREGATE, METHOD 2

Qayaq Construction LLC $43.00 $270,470.00 Bristol Prime Contractors, LLC $120.00 $754,800.00 Tutka, LLC $41.00 $257,890.00 Engineer's Estimate 6,290 TON $33.00 $207,570.00

A0780 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Qayaq Construction LLC $225.00 $648,000.00 Bristol Prime Contractors, LLC $210.00 $604,800.00 Tutka, LLC $200.00 $576,000.00 Engineer's Estimate 2,880 TON $160.00 $460,800.00

A0800 41201-0000 TACK COAT

Qayaq Construction LLC $1,200.00 $7,080.00 Bristol Prime Contractors, LLC $1,200.00 $7,080.00 Tutka, LLC $950.00 $5,605.00 Engineer's Estimate 5.9 TON $1,450.00 $8,555.00

A0820 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Qayaq Construction LLC $4,143.00 $389,442.00 Bristol Prime Contractors, LLC $5,851.00 $549,994.00 Tutka, LLC $4,865.00 $457,310.00 Engineer's Estimate 94 CUYD $3,000.00 $282,000.00

A0840 55505-0000 STRUCTURAL STEEL SOLDIER PILE

Qayaq Construction LLC $143.00 $391,820.00 Bristol Prime Contractors, LLC $317.00 $868,580.00 Tutka, LLC $205.00 $561,700.00 Engineer's Estimate 2,740 LNFT $200.00 $548,000.00

12 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0860 56501-0300 DRILLED SHAFT, 30-INCH DIAMETER

Qayaq Construction LLC $520.00 $743,600.00 Bristol Prime Contractors, LLC $954.00 $1,364,220.00 Tutka, LLC $1,005.00 $1,437,150.00 Engineer's Estimate 1,430 LNFT $550.00 $786,500.00

A0880 60201-0600 18-INCH PIPE CULVERT

Qayaq Construction LLC $248.00 $23,560.00 Bristol Prime Contractors, LLC $160.00 $15,200.00 Tutka, LLC $127.00 $12,065.00 Engineer's Estimate 95 LNFT $75.00 $7,125.00

A0900 60201-0800 24-INCH PIPE CULVERT

Qayaq Construction LLC $170.00 $129,200.00 Bristol Prime Contractors, LLC $162.00 $123,120.00 Tutka, LLC $230.00 $174,800.00 Engineer's Estimate 760 LNFT $160.00 $121,600.00

A0920 60201-1000 36-INCH PIPE CULVERT

Qayaq Construction LLC $350.00 $17,500.00 Bristol Prime Contractors, LLC $400.00 $20,000.00 Tutka, LLC $630.00 $31,500.00 Engineer's Estimate 50 LNFT $200.00 $10,000.00

A0940 60201-1400 60-INCH PIPE CULVERT

Qayaq Construction LLC $600.00 $66,000.00 Bristol Prime Contractors, LLC $580.00 $63,800.00 Tutka, LLC $815.00 $89,650.00 Engineer's Estimate 110 LNFT $700.00 $77,000.00

A0960 60501-0000 STANDARD UNDERDRAIN SYSTEM

Qayaq Construction LLC $64.00 $51,840.00 Bristol Prime Contractors, LLC $65.00 $52,650.00 Tutka, LLC $105.00 $85,050.00 Engineer's Estimate 810 LNFT $90.00 $72,900.00

13 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0980 60510-1000 8-INCH OUTLET PIPE

Qayaq Construction LLC $180.00 $30,600.00 Bristol Prime Contractors, LLC $35.00 $5,950.00 Tutka, LLC $135.00 $22,950.00 Engineer's Estimate 170 LNFT $32.00 $5,440.00

A1000 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS

Qayaq Construction LLC $40.00 $66,000.00 Bristol Prime Contractors, LLC $65.00 $107,250.00 Tutka, LLC $38.00 $62,700.00 Engineer's Estimate 1,650.00 LNFT $36.00 $59,400.00

A1020 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Qayaq Construction LLC $4,500.00 $9,000.00 Bristol Prime Contractors, LLC $6,000.00 $12,000.00 Tutka, LLC $4,500.00 $9,000.00 Engineer's Estimate 2 EACH $6,600.00 $13,200.00

A1040 61901-1300 FENCE, CHAIN LINK (PVC-COATED, BLACK)

Qayaq Construction LLC $48.00 $79,680.00 Bristol Prime Contractors, LLC $60.00 $99,600.00 Tutka, LLC $47.00 $78,020.00 Engineer's Estimate 1,660 LNFT $50.00 $83,000.00

A1060 61902-2000 GATE, METAL, 28 FEET WIDTH

Qayaq Construction LLC $9,000.00 $9,000.00 Bristol Prime Contractors, LLC $25,000.00 $25,000.00 Tutka, LLC $9,000.00 $9,000.00 Engineer's Estimate 1 EACH $9,400.00 $9,400.00

A1080 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $205.00 $8,200.00 Engineer's Estimate 40 HOUR $160.00 $6,400.00

14 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1100 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH

Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $180.00 $7,200.00 Engineer's Estimate 40 HOUR $150.00 $6,000.00

A1120 62201-1000 WHEEL LOADER, 4 CUBIC YARD MINIMUM RATED CAPACITY

Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $225.00 $9,000.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00

A1140 62201-2050 ROLLER

Qayaq Construction LLC $150.00 $6,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $200.00 $8,000.00 Engineer's Estimate 40 HOUR $170.00 $6,800.00

A1160 62201-2800 MOTOR GRADER, 8 FOOT MINIMUM BLADE

Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $210.00 $8,400.00 Engineer's Estimate 40 HOUR $210.00 $8,400.00

A1180 62201-3150 HYDRAULIC EXCAVATOR, CRAWLER MOUNTED, 1.0 CUBIC YARD MINIMUM CAPACITY WITH THUMB

ATTACHMENT

Qayaq Construction LLC $275.00 $11,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $270.00 $10,800.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00

A1200 62201-3750 CHAIN SAW

Qayaq Construction LLC $150.00 $3,000.00 Bristol Prime Contractors, LLC $100.00 $2,000.00 Tutka, LLC $165.00 $3,300.00 Engineer's Estimate 20 HOUR $70.00 $1,400.00

15 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1220 62301-0000 GENERAL LABOR

Qayaq Construction LLC $120.00 $4,800.00 Bristol Prime Contractors, LLC $100.00 $4,000.00 Tutka, LLC $115.00 $4,600.00 Engineer's Estimate 40 HOUR $96.00 $3,840.00

A1240 62406-0100 PLACING CONSERVED TOPSOIL, 2-INCH DEPTH

Qayaq Construction LLC $27,500.00 $60,500.00 Bristol Prime Contractors, LLC $24,500.00 $53,900.00 Tutka, LLC $15,000.00 $33,000.00 Engineer's Estimate 2.2 ACRE $8,500.00 $18,700.00

A1260 62501-0000 TURF ESTABLISHMENT (HYDRAULIC METHOD)

Qayaq Construction LLC $16,000.00 $35,200.00 Bristol Prime Contractors, LLC $12,300.00 $27,060.00 Tutka, LLC $24,000.00 $52,800.00 Engineer's Estimate 2.2 ACRE $8,300.00 $18,260.00

A1280 62901-0000 ROLLED EROSION CONTROL PRODUCT

Qayaq Construction LLC $10.00 $4,200.00 Bristol Prime Contractors, LLC $12.00 $5,040.00 Tutka, LLC $8.00 $3,360.00 Engineer's Estimate 420 SQYD $10.00 $4,200.00

A1300 63302-0000 SIGN SYSTEM

Qayaq Construction LLC $360.00 $6,300.00 Bristol Prime Contractors, LLC $65.00 $1,137.50 Tutka, LLC $175.00 $3,062.50 Engineer's Estimate 17.50 SQFT $300.00 $5,250.00

A1320 63316-1000 REMOVE AND RESET SIGN

Qayaq Construction LLC $480.00 $1,920.00 Bristol Prime Contractors, LLC $400.00 $1,600.00 Tutka, LLC $1,000.00 $4,000.00 Engineer's Estimate 4 EACH $475.00 $1,900.00

16 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1340 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE, 4-INCH)

Qayaq Construction LLC $0.75 $6,112.50 Bristol Prime Contractors, LLC $6.00 $48,900.00 Tutka, LLC $0.50 $4,075.00 Engineer's Estimate 8,150 LNFT $1.30 $10,595.00

A1360 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE, 6-INCH)

Qayaq Construction LLC $1.00 $12,790.00 Bristol Prime Contractors, LLC $12.00 $153,480.00 Tutka, LLC $0.50 $6,395.00 Engineer's Estimate 12,790 LNFT $1.30 $16,627.00

A1380 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Qayaq Construction LLC $1,400.00 $8,400.00 Bristol Prime Contractors, LLC $340.00 $2,040.00 Tutka, LLC $350.00 $2,100.00 Engineer's Estimate 6 EACH $360.00 $2,160.00

A1400 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

Qayaq Construction LLC $50.00 $300.00 Bristol Prime Contractors, LLC $50.00 $300.00 Tutka, LLC $60.00 $360.00 Engineer's Estimate 6 EACH $120.00 $720.00

A1420 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Qayaq Construction LLC $250.00 $22,625.00 Bristol Prime Contractors, LLC $50.00 $4,525.00 Tutka, LLC $60.00 $5,430.00 Engineer's Estimate 90.5 SQFT $46.00 $4,163.00

A1440 63703-0000 RESIDENTIAL HOUSING

Qayaq Construction LLC $67,000.00 $134,000.00 Bristol Prime Contractors, LLC $158,400.00 $316,800.00 Tutka, LLC $35,000.00 $70,000.00 Engineer's Estimate 2 EACH $27,000.00 $54,000.00

17 out of 17Source Selection Information - See FAR 2.101 & 3.104

Project No: AK FS CNF 1015(2)

Project Name: Russian River Campground Access Phase 2

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1460 63704-0000 VEHICLE

Qayaq Construction LLC $34,000.00 $68,000.00 Bristol Prime Contractors, LLC $52,500.00 $105,000.00 Tutka, LLC $55,000.00 $110,000.00 Engineer's Estimate 2 EACH $24,000.00 $48,000.00

Total Schedule - All Items

Qayaq Construction LLC $10,474,759.00 Bristol Prime Contractors, LLC $12,139,898.49 Tutka, LLC $15,465,034.00 Engineer's Estimate $7,731,881.00

2022-07-08T09:49:16-0700
DEAN ALAN UMATHUM

File details come from the government source that posted it. Updated .