This tabulation of bids report summarizes bids received in response to solicitation number 69056722B000007 for the Russian River Campground Access Phase 2 project. The project involves construction services including roadway excavation and construction, drainage installation, retaining walls, guardrails and fencing. Four contractors submitted bids by the July 8th deadline - Qayaq Construction LLC, Bristol Prime Contractors LLC, Tutka LLC, and the engineer's estimate. Bid amounts ranged from $7.7 million for the engineer's estimate to $15.5 million for Tutka LLC. The report provides unit pricing for over 150 line items and totals for each contractor. The Department of Transportation Federal Highway Administration will award the contract and notices an anticipated award date.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 07/08/22
1 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Contractor Responsive?
Engineer's Estimate
Bristol Prime Contractors, LLC
Qayaq Construction LLC
Tutka, LLC
Base Schedule A
$7,731,881.00
$12,139,898.49
$10,474,759.00
$15,465,034.00
Option: X
$779,809.00
$2,369,040.00
$918,003.00
$1,530,005.00
Contractor Responsive?
Engineer's Estimate
Bristol Prime Contractors, LLC
Qayaq Construction LLC
Tutka, LLC
Total Base Schedule A and Option(s): X
$8,511,690.00
$14,508,938.49
$11,392,762.00
$16,995,039.00
2 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: X
Schedule Type: Options
Solcitation No:
Division: Western Federal Lands
State: AK County: Kenai Peninsula
Federal Land: Opened at: WFL, Vancouver WA
Opened by: Marino Chea
Date: 07/08/22
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Qayaq Construction LLC $918,003.00 6700 Artic Spur Road Anchorage, AK 99518
Tutka, LLC $1,530,005.00 2485 E Zak Circle, Suite A Wasilla, AK 99654
Bristol Prime Contractors, LLC Calculated amount below does not match with Contractor's total bid for Schedule A.
$2,369,040.00 111 W. 16th Avenue, Third Floor Anchorage , AK 99501
Engineer's Estimate $779,809.00
Contracting Officer 07/08/2022
3 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0720 26303-0000 CONCRETE LAGGING (CAST-IN-PLACE CONCRETE FASCIA)
Qayaq Construction LLC $93.00 $918,003.00 Tutka, LLC $155.00 $1,530,005.00 Bristol Prime Contractors, LLC $240.00 $2,369,040.00 Engineer's Estimate 9,871 SQFT $79.00 $779,809.00
Total Schedule - All Items
Qayaq Construction LLC $918,003.00 Tutka, LLC $1,530,005.00 Bristol Prime Contractors, LLC $2,369,040.00 Engineer's Estimate $779,809.00
4 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Solcitation No:
Division: Western Federal Lands
State: AK County: Kenai Peninsula
Federal Land: Opened at: WFL, Vancouver WA
Opened by: Marino Chea
Date: 07/08/22
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Qayaq Construction LLC $10,474,759.00 6700 Artic Spur Road Anchorage, AK 99518
Bristol Prime Contractors, LLC Calculated amount below does not match with Contractor's total bid for Schedule A.
$12,139,898.49 111 W. 16th Avenue, Third Floor Anchorage , AK 99501
Tutka, LLC $15,465,034.00 2485 E Zak Circle, Suite A Wasilla, AK 99654
Engineer's Estimate $7,731,881.00
5 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
Qayaq Construction LLC Lump Sum $850,000.00 Bristol Prime Contractors, LLC Lump Sum $795,114.00 Tutka, LLC Lump Sum $3,500,000.00 Engineer's Estimate ALL LPSM Lump Sum $828,000.00
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
Qayaq Construction LLC Lump Sum $102,000.00 Bristol Prime Contractors, LLC Lump Sum $114,000.00 Tutka, LLC Lump Sum $100,000.00 Engineer's Estimate ALL LPSM Lump Sum $103,000.00
A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
Qayaq Construction LLC Lump Sum $166,000.00 Bristol Prime Contractors, LLC Lump Sum $269,700.00 Tutka, LLC Lump Sum $275,000.00 Engineer's Estimate ALL LPSM Lump Sum $113,000.00
A0080 15401-0000 CONTRACTOR TESTING
Qayaq Construction LLC Lump Sum $421,000.00 Bristol Prime Contractors, LLC Lump Sum $63,000.00 Tutka, LLC Lump Sum $195,000.00 Engineer's Estimate ALL LPSM Lump Sum $51,000.00
A0100 15501-0000 CONSTRUCTION SCHEDULE
Qayaq Construction LLC Lump Sum $30,000.00 Bristol Prime Contractors, LLC Lump Sum $357,085.00 Tutka, LLC Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $13,000.00
A0120 15703-2000 SOIL EROSION CONTROL, TEMPORARY TURF ESTABLISHMENT
Qayaq Construction LLC $13,000.00 $27,300.00 Bristol Prime Contractors, LLC $36,161.90 $75,939.99 Tutka, LLC $38,000.00 $79,800.00 Engineer's Estimate 2.1 ACRE $6,250.00 $13,125.00
6 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0140 15705-1300 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
Qayaq Construction LLC $160.00 $30,400.00 Bristol Prime Contractors, LLC $240.00 $45,600.00 Tutka, LLC $700.00 $133,000.00 Engineer's Estimate 190 LNFT $230.00 $43,700.00
A0160 15705-1400 SOIL EROSION CONTROL, FIBER ROLL (AT CULVERT INLET)
Qayaq Construction LLC $13.00 $8,580.00 Bristol Prime Contractors, LLC $17.00 $11,220.00 Tutka, LLC $17.00 $11,220.00 Engineer's Estimate 660 LNFT $8.00 $5,280.00
A0180 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Qayaq Construction LLC $8.00 $37,200.00 Bristol Prime Contractors, LLC $10.00 $46,500.00 Tutka, LLC $8.50 $39,525.00 Engineer's Estimate 4,650 LNFT $8.00 $37,200.00
A0200 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FIBER ROLL)
Qayaq Construction LLC $235.00 $2,820.00 Bristol Prime Contractors, LLC $780.00 $9,360.00 Tutka, LLC $475.00 $5,700.00 Engineer's Estimate 12 EACH $50.00 $600.00
A0220 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FILTER ROCK)
Qayaq Construction LLC $250.00 $3,250.00 Bristol Prime Contractors, LLC $752.00 $9,776.00 Tutka, LLC $550.00 $7,150.00 Engineer's Estimate 13 EACH $400.00 $5,200.00
A0240 15801-0000 WATERING FOR DUST CONTROL
Qayaq Construction LLC $90.00 $27,000.00 Bristol Prime Contractors, LLC $450.00 $135,000.00 Tutka, LLC $100.00 $30,000.00 Engineer's Estimate 300 MGAL $120.00 $36,000.00
7 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0260 20101-0000 CLEARING AND GRUBBING
Qayaq Construction LLC $13,000.00 $39,000.00 Bristol Prime Contractors, LLC $30,000.00 $90,000.00 Tutka, LLC $65,000.00 $195,000.00 Engineer's Estimate 3.0 ACRE $14,500.00 $43,500.00
A0280 20301-0100 REMOVAL OF BOLLARD
Qayaq Construction LLC $1,000.00 $3,000.00 Bristol Prime Contractors, LLC $500.00 $1,500.00 Tutka, LLC $250.00 $750.00 Engineer's Estimate 3 EACH $300.00 $900.00
A0300 20301-1100 REMOVAL OF GATE
Qayaq Construction LLC $900.00 $900.00 Bristol Prime Contractors, LLC $3,000.00 $3,000.00 Tutka, LLC $1,000.00 $1,000.00 Engineer's Estimate 1 EACH $1,250.00 $1,250.00
A0320 20301-1900 REMOVAL OF PIPE CULVERT
Qayaq Construction LLC $3,300.00 $13,200.00 Bristol Prime Contractors, LLC $600.00 $2,400.00 Tutka, LLC $3,200.00 $12,800.00 Engineer's Estimate 4 EACH $1,600.00 $6,400.00
A0340 20301-2400 REMOVAL OF SIGN
Qayaq Construction LLC $120.00 $1,080.00 Bristol Prime Contractors, LLC $220.00 $1,980.00 Tutka, LLC $300.00 $2,700.00 Engineer's Estimate 9 EACH $210.00 $1,890.00
A0360 20301-2700 REMOVAL OF STRUCTURE (TIMBER STAIRWAY)
Qayaq Construction LLC $6,000.00 $6,000.00 Bristol Prime Contractors, LLC $550.00 $550.00 Tutka, LLC $3,500.00 $3,500.00 Engineer's Estimate 1 EACH $1,000.00 $1,000.00
8 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0380 20301-3400 REMOVAL OF WHEELSTOP
Qayaq Construction LLC $380.00 $2,280.00 Bristol Prime Contractors, LLC $100.00 $600.00 Tutka, LLC $150.00 $900.00 Engineer's Estimate 6 EACH $200.00 $1,200.00
A0400 20302-1200 REMOVAL OF GUARDRAIL
Qayaq Construction LLC $2.50 $3,377.50 Bristol Prime Contractors, LLC $42.00 $56,742.00 Tutka, LLC $2.50 $3,377.50 Engineer's Estimate 1,351 LNFT $6.00 $8,106.00
A0420 20302-1300 REMOVAL OF GUARDRAIL, CONCRETE BARRIER
Qayaq Construction LLC $35.00 $4,375.00 Bristol Prime Contractors, LLC $20.00 $2,500.00 Tutka, LLC $50.00 $6,250.00 Engineer's Estimate 125 LNFT $25.00 $3,125.00
A0440 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (GABION WALL)
Qayaq Construction LLC Lump Sum $12,000.00 Bristol Prime Contractors, LLC Lump Sum $30,000.00 Tutka, LLC Lump Sum $24,000.00 Engineer's Estimate ALL LPSM Lump Sum $16,000.00
A0460 20401-0000 ROADWAY EXCAVATION
Qayaq Construction LLC $33.00 $469,095.00 Bristol Prime Contractors, LLC $13.00 $184,795.00 Tutka, LLC $36.00 $511,740.00 Engineer's Estimate 14,215 CUYD $22.00 $312,730.00
A0480 20411-0000 SELECT BORROW
Qayaq Construction LLC $32.00 $816,000.00 Bristol Prime Contractors, LLC $16.50 $420,750.00 Tutka, LLC $33.00 $841,500.00 Engineer's Estimate 25,500 TON $15.00 $382,500.00
9 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0500 20701-0100 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE A (WOVEN)
Qayaq Construction LLC $2.10 $31,668.00 Bristol Prime Contractors, LLC $8.00 $120,640.00 Tutka, LLC $3.80 $57,304.00 Engineer's Estimate 15,080 SQYD $3.25 $49,010.00
A0520 20702-0300 GEOTEXTILE FILTER, CLASS 1, TYPE C
Qayaq Construction LLC $7.00 $1,750.00 Bristol Prime Contractors, LLC $30.00 $7,500.00 Tutka, LLC $3.20 $800.00 Engineer's Estimate 250 SQYD $8.00 $2,000.00
A0540 20802-0000 FOUNDATION FILL
Qayaq Construction LLC $155.00 $71,300.00 Bristol Prime Contractors, LLC $100.00 $46,000.00 Tutka, LLC $120.00 $55,200.00 Engineer's Estimate 460 CUYD $150.00 $69,000.00
A0560 21101-1000 ROADWAY OBLITERATION, METHOD 1
Qayaq Construction LLC $35.00 $7,700.00 Bristol Prime Contractors, LLC $23.00 $5,060.00 Tutka, LLC $25.00 $5,500.00 Engineer's Estimate 220 SQYD $20.00 $4,400.00
A0580 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2 (PROTECTIVE APRON)
Qayaq Construction LLC $300.00 $21,000.00 Bristol Prime Contractors, LLC $330.00 $23,100.00 Tutka, LLC $265.00 $18,550.00 Engineer's Estimate 70 CUYD $170.00 $11,900.00
A0600 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3 (HEADWALL)
Qayaq Construction LLC $250.00 $33,250.00 Bristol Prime Contractors, LLC $300.00 $39,900.00 Tutka, LLC $275.00 $36,575.00 Engineer's Estimate 133 CUYD $80.00 $10,640.00
10 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0620 25101-0400 PLACED RIPRAP, METHOD A, CLASS 4 (RIPRAP END TREATMENT)
Qayaq Construction LLC $300.00 $33,000.00 Bristol Prime Contractors, LLC $275.00 $30,250.00 Tutka, LLC $280.00 $30,800.00 Engineer's Estimate 110 CUYD $140.00 $15,400.00
A0640 25120-0100 RIPRAP DITCH, METHOD A, CLASS 1
Qayaq Construction LLC $45.00 $27,900.00 Bristol Prime Contractors, LLC $75.00 $46,500.00 Tutka, LLC $45.00 $27,900.00 Engineer's Estimate 620 LNFT $32.00 $19,840.00
A0660 25201-1000 SPECIAL ROCK EMBANKMENT, MECHANICALLY-PLACED
Qayaq Construction LLC $190.00 $294,500.00 Bristol Prime Contractors, LLC $260.00 $403,000.00 Tutka, LLC $270.00 $418,500.00 Engineer's Estimate 1,550 CUYD $160.00 $248,000.00
A0680 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE
Qayaq Construction LLC $132.00 $1,939,080.00 Bristol Prime Contractors, LLC $60.00 $881,400.00 Tutka, LLC $175.00 $2,570,750.00 Engineer's Estimate 14,690 SQFT $72.00 $1,057,680.00
A0700 25601-0000 GROUND ANCHOR
Qayaq Construction LLC $8,600.00 $610,600.00 Bristol Prime Contractors, LLC $22,500.00 $1,597,500.00 Tutka, LLC $13,000.00 $923,000.00 Engineer's Estimate 71 EACH $5,000.00 $355,000.00
A0720 25605-0000 PERFORMANCE TEST
Qayaq Construction LLC $1,050.00 $5,250.00 Bristol Prime Contractors, LLC $2,000.00 $10,000.00 Tutka, LLC $1,300.00 $6,500.00 Engineer's Estimate 5 EACH $7,500.00 $37,500.00
11 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0740 26302-0000 TIMBER LAGGING
Qayaq Construction LLC $116.00 $971,964.00 Bristol Prime Contractors, LLC $90.00 $754,110.00 Tutka, LLC $130.00 $1,089,270.00 Engineer's Estimate 8,379 SQFT $100.00 $837,900.00
A0760 30202-2000 ROADWAY AGGREGATE, METHOD 2
Qayaq Construction LLC $43.00 $270,470.00 Bristol Prime Contractors, LLC $120.00 $754,800.00 Tutka, LLC $41.00 $257,890.00 Engineer's Estimate 6,290 TON $33.00 $207,570.00
A0780 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
Qayaq Construction LLC $225.00 $648,000.00 Bristol Prime Contractors, LLC $210.00 $604,800.00 Tutka, LLC $200.00 $576,000.00 Engineer's Estimate 2,880 TON $160.00 $460,800.00
A0800 41201-0000 TACK COAT
Qayaq Construction LLC $1,200.00 $7,080.00 Bristol Prime Contractors, LLC $1,200.00 $7,080.00 Tutka, LLC $950.00 $5,605.00 Engineer's Estimate 5.9 TON $1,450.00 $8,555.00
A0820 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
Qayaq Construction LLC $4,143.00 $389,442.00 Bristol Prime Contractors, LLC $5,851.00 $549,994.00 Tutka, LLC $4,865.00 $457,310.00 Engineer's Estimate 94 CUYD $3,000.00 $282,000.00
A0840 55505-0000 STRUCTURAL STEEL SOLDIER PILE
Qayaq Construction LLC $143.00 $391,820.00 Bristol Prime Contractors, LLC $317.00 $868,580.00 Tutka, LLC $205.00 $561,700.00 Engineer's Estimate 2,740 LNFT $200.00 $548,000.00
12 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0860 56501-0300 DRILLED SHAFT, 30-INCH DIAMETER
Qayaq Construction LLC $520.00 $743,600.00 Bristol Prime Contractors, LLC $954.00 $1,364,220.00 Tutka, LLC $1,005.00 $1,437,150.00 Engineer's Estimate 1,430 LNFT $550.00 $786,500.00
A0880 60201-0600 18-INCH PIPE CULVERT
Qayaq Construction LLC $248.00 $23,560.00 Bristol Prime Contractors, LLC $160.00 $15,200.00 Tutka, LLC $127.00 $12,065.00 Engineer's Estimate 95 LNFT $75.00 $7,125.00
A0900 60201-0800 24-INCH PIPE CULVERT
Qayaq Construction LLC $170.00 $129,200.00 Bristol Prime Contractors, LLC $162.00 $123,120.00 Tutka, LLC $230.00 $174,800.00 Engineer's Estimate 760 LNFT $160.00 $121,600.00
A0920 60201-1000 36-INCH PIPE CULVERT
Qayaq Construction LLC $350.00 $17,500.00 Bristol Prime Contractors, LLC $400.00 $20,000.00 Tutka, LLC $630.00 $31,500.00 Engineer's Estimate 50 LNFT $200.00 $10,000.00
A0940 60201-1400 60-INCH PIPE CULVERT
Qayaq Construction LLC $600.00 $66,000.00 Bristol Prime Contractors, LLC $580.00 $63,800.00 Tutka, LLC $815.00 $89,650.00 Engineer's Estimate 110 LNFT $700.00 $77,000.00
A0960 60501-0000 STANDARD UNDERDRAIN SYSTEM
Qayaq Construction LLC $64.00 $51,840.00 Bristol Prime Contractors, LLC $65.00 $52,650.00 Tutka, LLC $105.00 $85,050.00 Engineer's Estimate 810 LNFT $90.00 $72,900.00
13 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0980 60510-1000 8-INCH OUTLET PIPE
Qayaq Construction LLC $180.00 $30,600.00 Bristol Prime Contractors, LLC $35.00 $5,950.00 Tutka, LLC $135.00 $22,950.00 Engineer's Estimate 170 LNFT $32.00 $5,440.00
A1000 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
Qayaq Construction LLC $40.00 $66,000.00 Bristol Prime Contractors, LLC $65.00 $107,250.00 Tutka, LLC $38.00 $62,700.00 Engineer's Estimate 1,650.00 LNFT $36.00 $59,400.00
A1020 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
Qayaq Construction LLC $4,500.00 $9,000.00 Bristol Prime Contractors, LLC $6,000.00 $12,000.00 Tutka, LLC $4,500.00 $9,000.00 Engineer's Estimate 2 EACH $6,600.00 $13,200.00
A1040 61901-1300 FENCE, CHAIN LINK (PVC-COATED, BLACK)
Qayaq Construction LLC $48.00 $79,680.00 Bristol Prime Contractors, LLC $60.00 $99,600.00 Tutka, LLC $47.00 $78,020.00 Engineer's Estimate 1,660 LNFT $50.00 $83,000.00
A1060 61902-2000 GATE, METAL, 28 FEET WIDTH
Qayaq Construction LLC $9,000.00 $9,000.00 Bristol Prime Contractors, LLC $25,000.00 $25,000.00 Tutka, LLC $9,000.00 $9,000.00 Engineer's Estimate 1 EACH $9,400.00 $9,400.00
A1080 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $205.00 $8,200.00 Engineer's Estimate 40 HOUR $160.00 $6,400.00
14 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1100 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH
Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $180.00 $7,200.00 Engineer's Estimate 40 HOUR $150.00 $6,000.00
A1120 62201-1000 WHEEL LOADER, 4 CUBIC YARD MINIMUM RATED CAPACITY
Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $225.00 $9,000.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00
A1140 62201-2050 ROLLER
Qayaq Construction LLC $150.00 $6,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $200.00 $8,000.00 Engineer's Estimate 40 HOUR $170.00 $6,800.00
A1160 62201-2800 MOTOR GRADER, 8 FOOT MINIMUM BLADE
Qayaq Construction LLC $200.00 $8,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $210.00 $8,400.00 Engineer's Estimate 40 HOUR $210.00 $8,400.00
A1180 62201-3150 HYDRAULIC EXCAVATOR, CRAWLER MOUNTED, 1.0 CUBIC YARD MINIMUM CAPACITY WITH THUMB
ATTACHMENT
Qayaq Construction LLC $275.00 $11,000.00 Bristol Prime Contractors, LLC $200.00 $8,000.00 Tutka, LLC $270.00 $10,800.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00
A1200 62201-3750 CHAIN SAW
Qayaq Construction LLC $150.00 $3,000.00 Bristol Prime Contractors, LLC $100.00 $2,000.00 Tutka, LLC $165.00 $3,300.00 Engineer's Estimate 20 HOUR $70.00 $1,400.00
15 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1220 62301-0000 GENERAL LABOR
Qayaq Construction LLC $120.00 $4,800.00 Bristol Prime Contractors, LLC $100.00 $4,000.00 Tutka, LLC $115.00 $4,600.00 Engineer's Estimate 40 HOUR $96.00 $3,840.00
A1240 62406-0100 PLACING CONSERVED TOPSOIL, 2-INCH DEPTH
Qayaq Construction LLC $27,500.00 $60,500.00 Bristol Prime Contractors, LLC $24,500.00 $53,900.00 Tutka, LLC $15,000.00 $33,000.00 Engineer's Estimate 2.2 ACRE $8,500.00 $18,700.00
A1260 62501-0000 TURF ESTABLISHMENT (HYDRAULIC METHOD)
Qayaq Construction LLC $16,000.00 $35,200.00 Bristol Prime Contractors, LLC $12,300.00 $27,060.00 Tutka, LLC $24,000.00 $52,800.00 Engineer's Estimate 2.2 ACRE $8,300.00 $18,260.00
A1280 62901-0000 ROLLED EROSION CONTROL PRODUCT
Qayaq Construction LLC $10.00 $4,200.00 Bristol Prime Contractors, LLC $12.00 $5,040.00 Tutka, LLC $8.00 $3,360.00 Engineer's Estimate 420 SQYD $10.00 $4,200.00
A1300 63302-0000 SIGN SYSTEM
Qayaq Construction LLC $360.00 $6,300.00 Bristol Prime Contractors, LLC $65.00 $1,137.50 Tutka, LLC $175.00 $3,062.50 Engineer's Estimate 17.50 SQFT $300.00 $5,250.00
A1320 63316-1000 REMOVE AND RESET SIGN
Qayaq Construction LLC $480.00 $1,920.00 Bristol Prime Contractors, LLC $400.00 $1,600.00 Tutka, LLC $1,000.00 $4,000.00 Engineer's Estimate 4 EACH $475.00 $1,900.00
16 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1340 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE, 4-INCH)
Qayaq Construction LLC $0.75 $6,112.50 Bristol Prime Contractors, LLC $6.00 $48,900.00 Tutka, LLC $0.50 $4,075.00 Engineer's Estimate 8,150 LNFT $1.30 $10,595.00
A1360 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE, 6-INCH)
Qayaq Construction LLC $1.00 $12,790.00 Bristol Prime Contractors, LLC $12.00 $153,480.00 Tutka, LLC $0.50 $6,395.00 Engineer's Estimate 12,790 LNFT $1.30 $16,627.00
A1380 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
Qayaq Construction LLC $1,400.00 $8,400.00 Bristol Prime Contractors, LLC $340.00 $2,040.00 Tutka, LLC $350.00 $2,100.00 Engineer's Estimate 6 EACH $360.00 $2,160.00
A1400 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
Qayaq Construction LLC $50.00 $300.00 Bristol Prime Contractors, LLC $50.00 $300.00 Tutka, LLC $60.00 $360.00 Engineer's Estimate 6 EACH $120.00 $720.00
A1420 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Qayaq Construction LLC $250.00 $22,625.00 Bristol Prime Contractors, LLC $50.00 $4,525.00 Tutka, LLC $60.00 $5,430.00 Engineer's Estimate 90.5 SQFT $46.00 $4,163.00
A1440 63703-0000 RESIDENTIAL HOUSING
Qayaq Construction LLC $67,000.00 $134,000.00 Bristol Prime Contractors, LLC $158,400.00 $316,800.00 Tutka, LLC $35,000.00 $70,000.00 Engineer's Estimate 2 EACH $27,000.00 $54,000.00
17 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: AK FS CNF 1015(2)
Project Name: Russian River Campground Access Phase 2
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1460 63704-0000 VEHICLE
Qayaq Construction LLC $34,000.00 $68,000.00 Bristol Prime Contractors, LLC $52,500.00 $105,000.00 Tutka, LLC $55,000.00 $110,000.00 Engineer's Estimate 2 EACH $24,000.00 $48,000.00
Total Schedule - All Items
Qayaq Construction LLC $10,474,759.00 Bristol Prime Contractors, LLC $12,139,898.49 Tutka, LLC $15,465,034.00 Engineer's Estimate $7,731,881.00
| 2022-07-08T09:49:16-0700 | |
| DEAN ALAN UMATHUM |