Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

WPH1A

RFP- EQWPC-23-0001CISAHQ, Construction Services for CISA Headquarters Bldg, St Elizabeths W Campus, SE WASH DC Amendment 0009

THE FOLLOWING CHANGES, CORRECTIONS, AND ADDITIONS AS NOTED HEREIN ARE HEREBY INCORPORATED

INTO THE SOLICITATION.

WP1AA

GSA, OFC OF ACQUISITIONS

1800 F STREET, NW

WASHINGTON, DC 20405

TO ALL PROSPECTIVE OFFERORS

GSA, OFC OF DESIGN AND CONSTRUCTION

1800 F STREET, NW

WASHINGTON, DC 20405

RFP- EQWPC-23-0001CISAHQ

10/18/2023

04/05/2023

BONNIE ECHOLES Digitally signed by BONNIE ECHOLES

Date: 2023.10.18 23:52:30 -04'00'

10/18/2023

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

AMENDMENT 0009

IRA RFP-EQWPC-23-0001CISAHQ, Construction Services for the CISA Headquarters Building, St Elizabeths West Campus, SE WASH DC

Note: The Inflation Reduction Act of 2022 (IRA), Pub. L. No. 117-169, enacted in

August 2022, provided GSA with significant funding for (a) measures necessary to convert facilities to high-performance green buildings, (b) acquisition and installation of construction materials and products with substantially lower levels of embodied greenhouse gas emissions, and (c) emerging and sustainable technologies. The Contract resulting from this Solicitation will be funded in part by IRA appropriations, and it contains numerous IRA-specific requirements.

Requirements include, but are not limited to, requirements regarding pricing, invoicing, submittals, materials, and construction. In addition, please note that this Solicitation contains an evaluation factor favoring certain construction materials with the lowest possible levels of embodied carbon. Offerors shall carefully review this Solicitation, the Agreement, the Statement of Work, the

Specifications, and the Drawings. Offerors are responsible for accurately pricing and, if successful, fully performing all Contract requirements.

ITEM 1: Proposal receipt date and time is REMAINS UNCHANGED as follows.

OCOTBER 31, 2023, by 3:00PM EST BY EMAIL to the attention of the Contracting Officer, bonnie.echoles@gsa.gov

ITEM 2: DELETE the Pricing Sheet as issued previously and INSERT the attached REVISED PRICING SHEET in lieu thereof. This REVISED PRICING SHEET is to be used in proposal submission.

ITEM 3: Clarification to AMENDMENT 0008 IRA RFI LOG – Item 1

1. The IRA-Eligible Material table (included in Addendum #6) does not allow for analysis of materials supplied by different vendors.

a. For example different cement manufacturers will be utilized for the Structural Cast in Place Concrete and the Site Concrete Paving.

b. There is also potential for different steel manufacturers and miscellaneous metals, and glazing manufacturers for entrances, curtainwall, fire-rated glass wall systems, bullet resistant windows and sound control windows.

c. How would GSA like this information presented on the Contract Price for (Section II.B) and the IRA -Eligible material table included and Evaluation Factor 5.

A. GSA Answer [REVISED 10/4/2023]:

If an offeror is utilizing multiple manufacturers/suppliers within one LEC material subcategory, and those materials achieve different GSA GWP limits, they shall, for evaluation purposes, self-score based on the material/ product offered that has the highest GWP. (For example: within the 4,000 PSI concrete subcategory, if Offeror A's 4,000 PSI structural concrete meets GSA’s Top 40% GWP limit, and their 4,000 PSI site concrete meets GSA’s Top 20% limit, Offeror A shall use Top 40% in their scoring.)

ITEM 4: II.D. Technical Proposal DELETE FACTOR 1. Prior Experience on Similar Projects as issued in its entirety and INSERT the attached revised FACTOR 1. Prior Experience on Similar Projects, in lieu thereof.

ITEM 5: The attached ROUND 4 CISA Headquarters RFI Responses LOG is hereby incorporated under this solicitation.

ITEM 6: SPECIFICATIONS, DRAWINGS, AND SKETCHES (21 count) The following specifications, drawings, and sketches are hereby incorporated under this solicitation.

211300_A3 - Water Based Fire Suppression Systems.pdf 220529_A1- Hangers and Supports.pdf 220549_A2_Vibration and Seismic Controls.pdf 220800_A1- Commissioning.pdf 221110_A1 - Common Plumbing Piping.pdf 221123_A1 - Water Pumps.pdf 221124_A1- Water Packaged Booster Pumps.pdf 221329_A1 - Interior Sanitary Sewerage Pumps.pdf 223300_A1 - Electric Water Heaters.pdf 226780_A1 - Reclaim Water System Equipment.pdf Bid Addendum 3 Architecture 20231016.pdf DHS CISA - Plumbing - Bid Addendum 1 - 6.30.2023.pdf P-201 - PLUMBING LEVEL LL4 & LL5 PLANS.pdf P-204 - PLUMBING LEVEL LL1 PLAN.pdf P-205 - PLUMBING LEVEL 1 PLAN.pdf P-209 - PLUMBING LEVEL 5 PLAN.pdf P-401 - PLUMBING ENLARGED PLANS.pdf P-403 - PLUMBING ENLARGED PLANS.pdf P-700 - SANITARY SOIL - WASTE SYSTEM FLOR DIAGRAM.pdf P-703 - SANITARY SOIL - WASTE SYSTEM FLOW DIAGRAM.pdf P-712 - IRRIGATION WATER DIAGRAM.pdf

ITEM 7: Offeror must acknowledge receipt of this amendment by signature in block 15 and by inclusion of page 1 of the SF30 as an attachment to the proposal submission.

END OF AMENDMENT 0009

ATTACHMENTS:

REVISED PRICING SHEET

Revised FACTOR 1. Prior Experience on Similar Projects ROUND 4 CISA Headquarters RFI Responses LOG

211300_A3 - Water Based Fire Suppression Systems.pdf 220529_A1- Hangers and Supports.pdf 220549_A2_Vibration and Seismic Controls.pdf 220800_A1- Commissioning.pdf 221110_A1 - Common Plumbing Piping.pdf 221123_A1 - Water Pumps.pdf 221124_A1- Water Packaged Booster Pumps.pdf

221329_A1 - Interior Sanitary Sewerage Pumps.pdf 223300_A1 - Electric Water Heaters.pdf 226780_A1 - Reclaim Water System Equipment.pdf Bid Addendum 3_Architecture_20231016.pdf DHS CISA - Plumbing - Bid Addendum 1 - 6.30.2023.pdf P-201 - PLUMBING LEVEL LL4 & LL5 PLANS.pdf P-204 - PLUMBING LEVEL LL1 PLAN.pdf P-205 - PLUMBING LEVEL 1 PLAN.pdf P-209 - PLUMBING LEVEL 5 PLAN.pdf P-401 - PLUMBING ENLARGED PLANS.pdf P-403 - PLUMBING ENLARGED PLANS.pdf P-700 - SANITARY SOIL - WASTE SYSTEM FLOR DIAGRAM.pdf P-703 - SANITARY SOIL - WASTE SYSTEM FLOW DIAGRAM.pdf P-712 - IRRIGATION WATER DIAGRAM.pdf

ISSUED UNDER AMENDMENT 0009

ATTACHMENT TO SF 1442: PRICING SHEET

(To be submitted as an ATTACHMENT TO SF 1442)

CLIN & SubCLIN Price

CLIN 0001 Non IRA Project Expenditures $

CLIN 0002 IRA Acquisition and installation of low embodied carbon materials

SubCLIN 0002AA Acquisition and installation of low embodied carbon steel and associated expenses

SubCLIN 0002AB Acquisition and installation of low embodied carbon asphalt and associated expenses

SubCLIN 0002AC Acquisition and installation of low embodied carbon glass and associated expenses

SubCLIN 0002AD Acquisition and installation of low embodied carbon concrete and associated expenses

CLIN 0003 IRA emerging and sustainable Technologies

CLIN 0004 IRA high-performance green building measures

OPTIONS

OPTION 1: MASONRY REPOINTING at Bldgs 56/57 and Smokestacks

OPTION 2: PROTECTION BOARD INSTALLATION

AT EXISTING EXTERIOR OPENINGS AT BLDGS

56/57

OPTION 3: MASONRY SURFACE FINSIHES at smokestacks (only) at Bldgs 56/57

OPTION 4: SLAB ON GRADE (SOG) WORK AT

INTERIORS OF BLDGS 56/57

ISSUED UNDER AMENDMENT 0009

ALTERNATE

Alternate 01: CISA Temporary Parking Lot

OPTIONAL BID RATES

Contractor’s Overhead Rate for Adjustments

Contractor’s Profit Rate for Adjustments

Contractor’s Daily Rate for Compensable Project Delay (Work Day)

OFFEROR:

II.D. Technical Proposal FACTOR 1. Prior Experience on Similar Projects 10%

This factor considers the extent of the Firm’s past experience as a firm in providing similar construction services. The Firm must demonstrate successful experience as a General Contractor (GC) responsible for the construction of three (3) “similar”* projects substantially completed within the past twelve (12) years as defined below.

Two of the three (3) projects MUST contain ALL the following characteristics:

a. Project consisted of core and shell, tenant fit out: electrical, mechanical, plumbing, HVAC, sprinkler installation, fire and life safety systems, telecommunications, security infrastructure systems and utility connections.

b. The total project construction cost upon completion was not less than $200 million.

c. Project involved work on a historic site and/or campus. The terms “historic site” and “historic campus” refer to sites or campuses that are listed in or eligible for the National Register of Historic Places, or properties that otherwise have historic significance and required protection of historic elements.

d. Project included sustainable design (LEED ® certified) effort.

The one (1) remaining project MUST contain AT LEAST the following characteristics:

(No requirement for work on a historic site and/or campus.)

a. Project consisted of core and shell, tenant fit out: electrical, mechanical, plumbing, HVAC, sprinkler installation, fire and life safety systems, telecommunications, security infrastructure systems and utility connections.

b. The total project construction cost upon completion was not less than $200 million.

c. Project included sustainable design (LEED ® certified) effort.

For each project presented in relation to this factor, the Offeror must demonstrate that the project meets each of the above criteria. For each project presented the Firm shall submit the following data/information:

(a) Project Title

(b) Owner and/or Occupants(s)/Tenant(s)

(c) Location

(d) Project description including GSF

(e) Special Features i.e. Security System, Historical Consideration

(f) Contract Award Date

(g) Contract Type and Contractor's Responsibilities (Scope of Work)

(h) Date of Substantial Completion

(i) Contract Cost at Award

(j) Contractor’s key personnel assigned full time to the project

The more experience performing projects meeting the above criteria, the higher the Offeror will be rated.

Evaluation Criteria: This factor will evaluate the past experience of the firm to determine whether they have experience on three (3) “similar” construction projects that were substantially completed within the last twelve (12) years and meets the above similar characteristics as specified.

Acceptability Standard: This factor will be evaluated based upon the Offeror’s written response to the RFP. However, the Government reserves the right to contact references under this evaluation factor to verify the scope of the project offered. If the Offeror materially misrepresents information relating to its experience, the Contracting Officer may reject the proposal.

RFP-EQWPC-23-0001CISAHQ, Construction Services for the CISA Headquarters Building, St Elizabeths West Campus, SE WASH DC

RFI RESPONSE LOG (10/18/2023)

ITEM

Doc, Spec, or

Detail/ Sheet COMMENT Response

Schedule

Due to the large volume of information provided within

Amendment 6, many open questions regarding previously answered RFIs, and the new requirements for the Interim

IRA Low Embodied Carbon Material Requirements.

Please verify in accordance with Amendment 6, Round 3

RFI #93 the RFI deadline has been extended to October

6, 2023 to allow adequate time for new questions pertaining to the amendment, and coordination with the subcontracting market, with the Bid Proposal date to be

Proposal due date was extended. New proposal due date is now October 31st, 2023.

Amendment 6 issued several RFI's (#'s 16, 51, 82, 187, 224, 227, 251, 254, 164 and 303) that reference an IFC

Submission document set. Please provide timing for release of the IFC Submission document set and advise how we are to incorporate into our pricing at time of bid.

IFC set to be issued to the successful offeror before NTP

Per Amendment 6, with the anticipated Notice to Proceed of January 2024, please confirm if the bid validity (price hold) period can be reduced from 120 calendar days to a

Period of performance REMAINS as 807 days per Paragraph

1.C of the Agreement

Schedule

Please confirm the contract duration length. The documents and the RFI's are conflicting. Per the

Solicitation (pg. 14 of 40) section 4.B. Schedule, Notice to

Proceed: January 2024, Substantial Completion: June

2026, and Project Completion: January 2027 = NTP -to-

Substantial Completion = 29 months + an additional 7 months to Project Completion (TOTALs 36 months). Per the Agreement (pg. 4 of 42), section I.C. Period of

Performance, NTP -to- Substantial Completion = 807 calendar days (+/- 27 months) + an additional 60 calendar days (+/- 2 months) to Project Completion

(TOTALs 29 months). Please confirm the period of

Actual contract period of performance is 30 months

BLD 56/57

It is currently not possible to price the work on the smoke stacks and buildings 56/57 as the work is uncertain as a proper renovation and HAZMAT studies were never performed and are to be performed by the contractor after award. Please advise if GSA intends to perform and provide a comprehensive detailed HazMat study, crack surveys, and interior demolition studies to provide enough detail to promote better subcontractor competition and

Given that there is a lack of information identifying any possible hazmat conditions/materails, assume lead paint on all surfaces as well as asbestos on all existing mechanical equipment.

Amendment 6 issued a revised bid form 'ATTACHMENT

TO SF 1442: PRICING SHEET' (AMEND 0006 SF 1442

PRICING SHEET.pdf). The 'PRICING SHEET' which had

9 CLINs that was issued in Amendment 4 was not reissued. (1.) Please confirm if 'PRICING SHEET' from

Amendment 4 is still required? (2.) If the Amendment 4

PRICING SHEET is not required, please confirm where pricing for the Bid Alternate and Options are to be included. (3.) If the Amendment 4 PRICING SHEET is required, please reissue the Pricing Sheet to include ALL options as listed per specification section 012400 as the

REQUIRED SUBMISSION, AMEND 0009 ATTACHMENT

TO SF 1442: PRICING SHEET' (includes Options)

Amendment 6 reissued a revised 'DIVISIONAL PRICE

BREAKDOWN SUMMARY' (AMEND 0006 DIVISIONAL

PRICE BREAKDOWN SUMMARY.pdf). The footnote states that "Total amount shall match amount on OFFER

FORM." Please confirm what the total of the Divisional

Breakdown should match? (1.) CLIN 0001 Non IRA

PROJECT Expenditures (from Attachment to SF 1442:

Pricing Sheet); (2.) CLIN 0001, 0002, 0003 and 0004

(from Attachment to SF 1442: Pricing Sheet); (3.) CLIN 1

The requirement for submission of a DIVISIONAL

BREAKDOWN SHEET is hereby DELETED.

Issued under Amendment 0009

Amendment 6 revised the RFP submittal requirements and either added or removed sections/deliverables from the previous proposal submittal requirements. To ensure we are providing the GSA with all required deliverables, please confirm the contents of each volume are to be submitted as follows:

Price Volume:

1.) SF1442, Price form, divisional price breakdown form

2.) Qualifications, Exclusions and Conditions

3.) Project Labor Agreement

4.) Bid Bond

5.) GSA Form 527

6.) Representations and Certifications

Technical volume:

1.) Factor 1: Prior Experience on Similar Projects

2.) Factor 2: Past Performance of Offeror (PBS PPQ

Forms for Factor 1 projects)

3.) Factor 3: Designated Key Personnel Resumes

4.) Factor 4: Management Plan and Schedule

5.) Factor 5: Sustainability

6.) Factor 6: Small Business Participation Plan and Small

Business Subcontracting Plan

Confirmed with ONE EXCEPTION: The Project Labor

Agreement (PLA) should be included in response to FACTOR

7 in Technical Volume.

Per the Solicitation, pg. 7 of 40, section II.B Proposal

Format, attachment are limited to 25MB. Both a Price

Proposal and Technical Proposal are required for the submission. Please confirm both Price and Technical

Proposals are to be included in the same email for

"Emails, including message body, headers, and attachments are limited to 25MB. Zip files." One or two emails is acceptable. Email limitation is 25MB. Zip files per email.

message.

IRA low embodies carbon

The IRA-Eligible Material table (included in Addendum

#6) does not allow for analysis of materials supplied by different vendors. For example different cement manufacturers will be utilized for the Structural Cast in

Place Concrete and the Site Concrete Paving. There is also potential for different steel manufacturers and miscellaneous metals, and glazing manufactures for entrances, curtainwall, fire-rated glass wall systems, bullet resistant windows and sound control windows. How would GSA like the this information presented on the

If an offeror is utilizing multiple manufacturers/suppliers within one LEC material subcategory, and those materials achieve different GSA GWP limits, they shall, for evaluation purposes, self-score based on the material/ product offered that has the highest GWP.

(For example: within the 4,000 PSI concrete subcategory, if

Offeror A's 4,000 PSI structural concrete meets GSA’s Top

40% GWP limit, and their 4,000 PSI site concrete meets

GSA’s Top 20% limit, Offeror A shall use Top 40% in their scoring.)

IRA low embodies carbon

Amendment 6 issued a revised bid form 'ATTACHMENT

TO SF 1442: PRICING SHEET' (AMEND 0006 SF 1442

PRICING SHEET.pdf). The 'PRICING SHEET' includes

CLIN 0003 (IRA emerging and sustainable Technologies) and 0004 (IRA high-performance green building measures). (1.) Can the GSA provide a scope of work for

Clin 3 "IRA Emerging and Sustainable Technologies" and

Clin 4 "IRA High-performance green building measures".

(2.) Can the GSA please confirm the Total Evaluated

Scopes of Work relating to Emerging and Sustainable

Technologies and High Performance Green Building Measures are included in the revised Spec Sect 011000 – Summary. A revised SF1442 Pricing Sheet is issued under this amendment and is to be used in submitting the price proposal.

IRA low embodies carbon

Per the IRA-Eligible Material Table found in Evaluation

Factor 5 (Solicitation pg. 16 of 40), "*The weighted score for each material must be rounded to the nearest hundredth decimal". Please confirm the "LEC Materials

Evaluation Weight" listed are intended to be percentages

Correct

IRA low embodies carbon

Per the IRA-Eligible Material Table found in Evaluation

Factor 5 (Solicitation pg. 16 of 40), it is stated that "In addition, for each of the IRA-Eligible Material identified in the table above, offerors shall submit compliant EPDs listing that material's GWP." Per the Agreement (pg. 16 of 42), it is stated "Within 10 business days following contract award, the Contractor shall provide the

Contracting Officer with a current Market Report on IRA-

Eligible Materials referenced in the Solicitation's

Sustainability Factor self-scoring table." Please confirm this information shall be available for submission by the

EPDs are required to be submitted with proposal as stated in the Evaluation Factor.

IRA low embodies carbon

Amendment 6 issued a revised bid form 'ATTACHMENT

TO SF 1442: PRICING SHEET' (AMEND 0006 SF 1442

PRICING SHEET.pdf). The 'PRICING SHEET' includes

CLINs 0002AA through 0002AD for cost associated with

"Acquisition and Installation of low embodied carbon

(materials) and associated expenses". Please confirm if this cost is to be the 'Material PREMIUM Cost' or

The CLINs are for total price and associated expences for each low embodied carbon material.

IRA low embodies carbon

Amendment 6 issued a revised bid form 'ATTACHMENT

TO SF 1442: PRICING SHEET' (AMEND 0006 SF 1442

PRICING SHEET.pdf). The 'PRICING SHEET' includes

CLINs 0002AA through 0002AD for cost associated with

"Acquisition and Installation of low embodied carbon

(materials) and associated expenses". Please confirm what costs are to be included as defined by "associated expenses"? (i.e. for CLIN 0002AD) (1.) Product acquisition, (2.) Product fabrication, (3.) Product delivery, Examples of associated expenses are provided in Section

II.C(4) Additional Proposal Requirements of the Solicitation

Document (Page 13 of the Amendment 0006 PDF).

IRA low embodies carbon

Per The Agreement, page 15-16 of 42, section III.M.

Additional Terms and Conditions, Limited Notice to

Proceed with Post-award Low Embodied Carbon

Materials Research Report, please confirm that the project duration (period of performance) will commence following receipt of the "unrestricted notice to proceed"

The period of performance will commence one day after the

Awardee’s receipt of the Notice to Proceed.

IRA low embodies carbon

Per Specification Section 018113.13 - Embodied Carbon

Design Requirements issued in Amendment 6, section

1.2 states "Provide all requirements to achieve Embodied

Carbon thresholds established in this specification and related material specification sections." Further on in the same specification, paragraphs 2.1.A.1, Table 1, 2.2.A.1, Table 2, 2.3.A.1, Table 3, Table 4, Table 5 Table 6 all state to provide products that result in achieving the top

20% limit in Global Warming Potential (GWP) for the low embodied carbon steel. Please confirm if the top 20% limit is a requirement per specification section 018113.13, or is it the contractors discretion to include IRA limits per category on the Interim IRA Low Embodied Carbon

Refer to revised spec 018113.13 for limit options based on the industry best practice for that particular material.

IRA low embodies carbon

Per the Interim IRA Low Embodied Carbon Material

Requirements Form and within IRA Limit Commitment

Table found within the Solicitation (pg. . 15, 16 of 40) there are products listed under Steel as 'fabricated' and

'unfabricated'. Please provide definition as to what is classified as 'fabricated' and 'unfabricated' for these specified products.

GSA goes by which EPD is used for the material or product at issue. The raw material (e.g. from Nucor, Steel Dynamics, Cascade etc.) is typically formed into different shapes by smaller, more regionally-distributed fabricators. GSA included both fabricated and unfabricated steel GWP limits to provide additional flexibility in cases where, e.g., the unshaped steel had an EPD, but the finished product did not. EPDs identify whether they are for fabricated steel or not, and EPD databases such as EC3 (Building Transparency’s Embodied

IRA low embodies carbon

Per the Interim IRA Low Embodied Carbon Material

Requirements Form and within IRA Limit Commitment

Table found within the Solicitation (pg. . 15, 16 of 40) there are products listed under Steel as 'fabricated' and

'unfabricated'. i.e., Hollow Structural Sections. It is our assumption that 'unfabricated' will be (Step 1): steel mill casting steel plate, or does it also include (Step 2):

Shaping the steel plate into a tube? We would also assume that (Step 3): a 'fabricator' who would receive tube stock and add plates, caps, connects, etc. would be

These assumptions about what constitutes fabrication are correct. Please see additional insight in the following answer.

IRA low embodies carbon

Per the Interim IRA Low Embodied Carbon Material

Requirements Form and within IRA Limit Commitment

Table found within the Solicitation (pg. . 15, 16 of 40) there are products listed under Steel as 'fabricated' and

'unfabricated'. i.e., Hot-Rolled Sections. It is our assumption that 'unfabricated' would be inclusive of the hot-rolled sections directly from a steel mill. If this assumption is correct, please provide information on how the 'fabricated' IRA is to be calculated. As this project is primarily miscellaneous metals and not structural steel, we request definition on how the GWP Value for IRA limits are to be calculated for the 'fabrication' process as miscellanous steel fabrication shops are generally smaller with less ability to track and calculate the true

EPDs identify whether a product is fabricated or unfabricated, and are categorized in EPD databases such as EC3 accordingly. The EPD’s indication of whether a steel product is fabricated governs which GWP limit applies. GSA recognizes that unfabricated steel EPDs may be more prevalent, and has received input from the steel industry on fabrication being a geographically-distributed process at smaller firms -- and one which contributes less to GWP than the steel’s original

(unfabricated) manufacturing.

Elevator

Please clarify the finish for MT-01 and MT-10 specified for the elevator entrances and elevator returns/front cab wall. Section 057000 specified blackened steel for MT-01 at the elevator doors. Finish schedule AI-900 calls out MT-

01 as a coated metal by the GC to match control sample, 2 coat Permalac Finish. Arch drawings AI-612, AI-703, AI-

704 and AI-818 call out the following finishes: MT-01 (as

'Black Metal Look'), MT-1 (not identified) and MT-10 (not identified) Elevator specifications call for the cab fronts as

#4 stainless steel.

Per Bid RFI R2 #44: MT-10 to be revised to MT-01. MT-01 at elevator doors.

Demountable partitions

Will the Owner be issuing the General Contractor a Letter of Authorization to purchase the Demountable Partitions

(102219) off of the GSA Schedule pricing?

No. Refer to FAR Subpart 51.1 - Contractor Use of

Government Supply Sources. This solicitation will result in a firm fixed price, not a cost reimbursement, contract..

23 Doors Door 1341 is shown on drawings AE-105B but is not listed on the door schedule. Please provide details for

Doors are part of the operable partition assembly. Refer to

Spec Section 102226-2.3.H - Storage Pocket Doors

Bid form Per RFI Response, please reissue the bid form with all applicable options from Specification 012400 for pricing.

Revised form included.

Schedule

Please confirm the contract duration length. The documents and the RFI's are conflicting. Per the

Solicitation (pg. 14 of 40) section 4.B. Schedule, Notice to

Proceed: January 2024, Substantial Completion: June

2026, and Project Completion: January 2027 = NTP -to-

Substantial Completion = 29 months + an additional 7 months to Project Completion (TOTALs 36 months). Per the Agreement (pg. 4 of 42), section I.C. Period of

Performance, NTP -to- Substantial Completion = 807 calendar days (+/- 27 months) + an additional 60 calendar days (+/- 2 months) to Project Completion

(TOTALs 29 months). Please confirm the period of

The Contractor shall achieve Substantial Completion of the

Work, as that term is defined in this Agreement, no later than

_807_ calendar days from issuance of Notice to Proceed

(NTP). The Contractor shall achieve Contract Completion, as the term is defined in The Agreement, within 60 calendar days after Substantial Completion.

Bid form Per RFI Response, please reissue the bid form with all applicable options from Specification 012400 for pricing.

Revised form included.

Structure Per RFI Response, please reissue drawing SE-106A to clearly show all missing framing information.

Drawing SE-106A was provided with the Round 1 RFI responses. GSA can distribute.

Doors

Per Amendment 4, RFI Response 29, all doors within

STC rated partitions shall comply with the STC rating of the partition as a minimum. The current door schedule only has a small fraction of the STC doors that will be required. Upgrading all the doors (incorrectly labeled/not currently related) per the door schedule to comply with the STC rating of the partition will add substation costs.

As this is not a design/build project, please reissue updated/coordinated door schedule to incorporate all

STC rated doors and hardware sets.

Per previous response, door schedules will be updated and provided with IFC documents.

HM Doors (F, AA, and AU Panel types): Contractor to coordinate and provide adequate STC ratings at doors to comply with Art. 1.7.B of Section 081113.

Wood Doors (F Panel type): Contractor to coordinate and provide adequate STC ratings at doors to comply with Door

Schedule Note #4.

To assist in Contractor’s pricing exercise we offer the following review analysis: All interior doors are framed into the following STC rated walls:

- FA walls (STC 40): Storage, Work Rooms, Lockers, Food

Area, Copy Rooms;

- GA walls (STC 45): Huddle Rooms, Janitor, Restrooms, Misc Rooms;

- HA walls (STC 50 & 55): Comm, Elec, & Mech Rooms, Conf

Rms, Focus;

- X walls (STC 55): Doors into Open Offices at SCIF boundaries from Corridors.

Contractor to coordinate and price accordingly.

Structure

Addendum 4, RFI response #31 indicates that an AISC sophisticated paint endorsement will be required. Being that this is a cast-in-place concrete structure, not structural steel, this approach will severely limit the number of bidders for the steel (Miscellaneous metals) work on this project, and does not seem to be in the

Govts best interest. Please reconsider the response to this inquiry and confirm the sophisticated paint endorsement can be waived, or can a SSPC certification

Recommends still satisfying the AISC endorsement for the steel that is considered necessary for life safety which include the steel for the bridge, loading dock and courtyard steel structures. For other steel items, No objection to accepting just the certification pending acceptance from the GSA

Fall arrest system

Looking at the elevations of the building, there do not appear to be any sabilization anchors or the like identified on the elevations of the precast wall panels. Please confirm that they are not required, or provide elevations showing the required locations/layout.

By "stabilization anchors", it is assumed that refers to fall arrest/façade maintenance anchors. If so, all fall arrest and roof tie-offs will occur on the roof(s) and specified areas. Refer to sheet AE-206. Per specifications, fall arrest and façade maintence will be a delegated design. Drawings shown as

36 Turnstiles

Per Round 2, RFI #40, these devices, inclusive of the turnstiles are stated to be Government Furnished, Government Installed. Please confirm the turnstiles for the project are GFGI.

General Note 5 on Sheet AE-360 states that Magnetometer, Turnstiles, card reader, panic button, X-Ray, Server Racks are by others. Thus, these items are Government Furnished, Government Installed. Turnstiles are to be provided by the

DHS contractor.

Trailer

The Water AND Fire Services space on AE-360 seems to be a separate space from the mobile trailer. There aren't any details for this space. Please provide details.

"Water and Fire:

Per Spec Section 133433, Art. 2.3.O: Provide accessory building (water/fire service room) attached to the trailer.

Refer to 2.3.O.1 and 2.3.O.2 for systems and services."

Please provide design for this room as no design has been provided per the Contract Documents.

The trailer is a prefabricated unit to be constructed off-site and delivered by truck to the St. Elizabeth's campus. The performance requirements of the trailer unit, specified in Spec

Section 133433, and accessory building are by a single manufacturer and supplier. Dimensions for the accessory building should be followed and manufacturer's standard enclosure system will be reviewed as part of the shop drawing review process.

BLD 56/57

It is currently not possible to establish a cost estimate for this work due to Silman having limited access to perform a survey, and little to no access provided to contractors prior to pricing, please provide an allowance for this work until a proper survey of existing conditions can be

Given that there is a lack of information identifying any possible hazmat conditions/materails, assume lead paint on all surfaces as well as asbestos on all existing mechanical equipment.

BLD 56/57

The beam reinforcing detail W1 on SJ-501 indicates "if additional reinforcing is required, add plate to other side of web". We would need to know which members this would be required on in order to price this. Please clarify.

Per notes in the drawings, due to limited access, a comprehensive survey has not been performed to date, so the members requiring this additional reinforcement has not been verified in the field. Silman cannot confirm which members require this. This information will need to be verified by the

BLD 56/57

What happens at the connections for the beams that are reinforced. Do the connections need to be reinforced in any way? There do not appear to be details for that.

Please clarify and if needed, provide locations and details.

Per notes in the drawings, due to limited access, a comprehensive survey has not been performed to date, so the existing connections have not been evaluated. Existing connections will need to be evaluated once access is provided and, if required, reinforcement details will be developed based

BLD 56/57

Key note 41 on S-201 indicates that 50% of the steel girts need to be replaced. Its not clear what member sizes and types these are. Please clarify.

Per notes in the drawings, due to limited access, a comprehensive survey has not been performed to date, so the size of the existing steel girts has not been verified in field.

Base on limited site observations, it appears the girts are 12"

BLD 56/57

The crossover ladder between Bldgs 56/57, shown on AJ-

120 and AJ-140 (see key note 40) do not appear to have any details or parapet height to deterimine the ladder height. Please provide section cut and parapet height

Per Key Note #40: Ladder dimensions to be determined following field verifications & measurements of existing conditions by Contractor and reviewed by A/E through

Submittal process.

BLD 56/57

Key note 87 indicates the maintenance access ladder on

SJ-103 and SJ-104. It indicatets that there will be "local reinforcment to be required at existing floor framing below". We need details, layouts, extents of this work in

An existing building survey could not be performed during design and assumptions had to be made based on the original building drawings. The contractor will have to perform a field survey to determine existing conditions.

Div 5 Please reissue updated specification 055500 to reflect changes as stated in RFI Response.

The Government is unable to locate the reference to 055500 in any of the other Rounds of RFI's that indicated revisions would

Div 5 Please reissue updated Section 4/AE-503 correcting the horizontal railing drafting error as stated in RFI

Drafting error that will be corrected in IFC documentation.

Railing follows the same profile of the floors above and below.

Bid form Please reissue the bid form with all applicable options from Specification 012400 for pricing.Revised form included.

49 Schedule

Please confirm the contract duration length. The documents and the RFI's are conflicting. Per the

Solicitation (pg. 14 of 40) section 4.B. Schedule, Notice to

Proceed: January 2024, Substantial Completion: June

2026, and Project Completion: January 2027 = NTP -to-

Substantial Completion = 29 months + an additional 7 months to Project Completion (TOTALs 36 months). Per the Agreement (pg. 4 of 42), section I.C. Period of

Performance, NTP -to- Substantial Completion = 807 calendar days (+/- 27 months) + an additional 60 calendar days (+/- 2 months) to Project Completion

(TOTALs 29 months). Please confirm the period of

The Contractor shall achieve Substantial Completion of the

Work, as that term is defined in this Agreement, no later than

_807_ calendar days from issuance of Notice to Proceed

(NTP). The Contractor shall achieve Contract Completion, as the term is defined in The Agreement, within 60 calendar days after Substantial Completion.

BLD 56/57

011000-1.6G Hazardous Materials - calls for Contractor to perform its own survey to support its construction requirements. Provide government survey indicating amount and extent bid is to be based on.

Provide answer to RFI. 'It is currently not possible to establish a cost estimate for this work as there is no list of hazardous materials, locations, or quantities for pricing purposes. Please provide this information for purposes of pricing or provide an allowance to be

Given that there is a lack of information identifying any possible hazmat conditions/materails, assume lead paint on all surfaces as well as asbestos on all existing mechanical equipment.

BLD 56/57

Provide a survey / photos of all existing holes and openings in existing floors, walls and ceilings that are to be closed and patched. If this information is not available, provide an allowance to include for this work.

'It is currently not possible to establish a cost estimate for this work due to lack of information within the Contract

Documents. Please provide an allowance for this work until a proper survey of existing conditions can be

Given that there is a lack of information identifying any possible hazmat conditions/materails, assume lead paint on all surfaces as well as asbestos on all existing mechanical equipment.

Spec Provide the missing specification section referenced in section 018123-2.1-C3 and D2

Blast Loads analysis is provided in the Narrative Section 21.

GSA may choose to share this information with the bidders or

Narratives

This RFI response is in conflict with response to Round 2, RFI #212. Please confirm the four volumes of Design

Narratives are FOR INFORMATION ONLY.

The Design Narratives provide information specific to the basis of design, but should be used as a resource For Information

Only. Contractors are responsible to follow the Project Manual

QC

1. Factor 3 Designated Key Personnel requires that the

QC/QC Manager hold a “Registered Professional

Architect (R.A.) and/or Professional Engineer (P.E.) and

C.Q.M. for Contractors Course Certification; Note:

Appropriate experience may be substituted for education and credentials.” Please clarify what GSA considers

“appropriate experience” that can be substituted for

The language for "appropriate experience" as a substitute has been removed under this factor.

Notes - VIII.1. - there are reference to coordination with other ongoing construction projects. Please provide a listing, timeline and current documents for those other projects (to the extent that they may impact this project.

GSA is not aware, at this time, of any other projects that will have an impact on the CISA HQ Project.

Notes VIII.4 - please provide a copy of the Phase I

Assessment document referenced in this note that details the extent of asbestos and lead paint hazardous

This document is not available.

Master plan

Notes VIII.5 - Please confirm that the bid documents, as provided, have incorporated ALL of the requirements of the documents referenced in this note (St Elizabeth

Master Plan Amendment#2 Environmental Impact Study and Record of Decision (signed 29, September, 2020, etc.). If not, Please provide a Bid Amendment that does incorporate these requirements. Simply referencing these documents and requiring that "All activities related to site preparation for construction...must adhere to the

Reference website for GSA Development of St. Elizabeths

Campus: http://www.stelizabethsdevelopment.com/

Utility locator Notes IX.2 - please provide contact information for the

"Preferred Campus Utility Locator"(s).

POC information will be provided to the successfol offeror.

BLD 56/57

Please confirm that the referenced repair/reinstallation of the existing metal clad link to smokestack (Note 10) pending Assessment by the Owner's engineering / preservation consultants is NOT to be included in this proposal. If it is to be included, please advise on an

Allowance to carry for this unknown scope. (which is not further defined by Note 10/AJ110 or the structural drawings)

This metal clad link should be protected throughout the stabilization of smokestack 2 and Building 57. There is no intent to remove this link, though if damaged, should be repaired or replaced in kind. Contractor to include this protection and/or repair in their scope of services.

This Response is in conflict with Round 2, RFI #260 and

RFI #372. Please confirm bidders are to replace 3 bands and provide a unit price for replacement of additional

The bidder is confused with the terms "link" and "band". The metal "bands" are the metal straps around the smokestack that help provide structural stability to the outward pressure of the masonry. The metal clad "link" is the small bridge connection between Building 57 and the Smokestack. This

"link" should be protected throughout the stabilization. The response to RFI #260 is accurate to the "bands".

61 BLD 56/57

The existing floor live load capacity at the ground floor of

Building 57 could not be determined due to limited access to the basement; could not determine sizes or configuration of structural members at the ground floor.

Until the existing floor framing can be observed and live load analyis can be performed, recommends all shoring or scaffolding, be supported at grade at the basement level.

'It is currently not possible to establish a cost estimate for this work due to the lack of information provided within

All shoring and scaffolding shall be submitted to the

Goverment for review and stamped by a structural licensed engineer. The Government recommends all shoring or scaffolding, be supported at grade at the basement level.

New Work Key Notes" #25 and #27 at Arch. Sheets AJ-

130 (plans) and AJ-210 (elevations). These notes indicate existing walls to be exposed (down to footings) during demolition for structural work. These walls are to be repaired per Structural requirements before installing new waterproofing. Waterproofing specifications (Div. 07

) call for proper preparation of substrates, which is part of wall repair scope. The extensive remedial work stated in the question is still unknown at the time.

It is currently not possible to establish a cost estimate for this work due to unknown conditions of existing walls, please provide an allowance for this work until a proper

Given that the extent of remedial work is unknown at this time, assume worst case for bidding purposes.

Bid form

Consistent with Response #1 above, the A/E Team recommends the PRICING SHEET be revised to address all appropriate options listed at Spec. 01 2400, 3.1.

(Options for Slab on Grade at Bldg. 56/57 are noted are

3.1.A.4.)

Per RFI Response, please reissue the bid form with all

Revised form included.

Bid form

Note 1 on 2/SJ-101 indicates an assumed requirement for replacement of 10% of the structural steel at the ground floor. To properly price this, we will need the sizing/weights of the existing steel. If this information is not available, please consider adding a Bid Allowance for this work in order to properly level the bid scope.

This information is not available due to limited access at the basement level for observation.

It is currently not possible to establish a cost estimate for this work due to Silman having limited access to perform a survey, and little to no access provided to contractors prior to pricing, please provide an allowance for this work until a proper survey of existing conditions can be

Given that "this information is not available due to limited access at the basement level for observation", assume worst case for bidding purposes.

67 Waterproofing

Planter and seat wall sections do not indicate damp proofing or waterproofing at the back of these walls. We recommend that damp proofing be applied to the back of these walls. Please advise.

Damproofing is desired at the back of the planter and seat walls where they will come in contact with soil. Refer to the Civil engineer's grading plan for locations where this condition occurs. Revision to the wall sections to include it.

Provide dampproofing to the backside of planter and seat walls where they come in contact with the soil.

Schedule

"General note 5 on S 001 indicates ""All smokestacks stabilization work to precede all other site, demolition, and construction work for the larger CISA headquarters project."" Please advise if this is applicable as it appears the ""early"" demolition of buildings 60 and 66 occurred before the stabilization.