Ex C Form D (Rev. 1, 9/22/08) Exhibit C Form D – Subcontract Schedule May 31, 2019
EXHIBIT “C”
FORM D
SUBCONTRACT SCHEDULE
PN: Edit the Clause titles identified below to fit the Subcontract pro forma being used. For example, Services and Architect/Engineer proformas incorporate schedule requirements in the milestone clause.
Bidder to submit a Preliminary Subcontract Schedule addressing the Subcontract Target and Milestone dates listed in the Task Order Schedule and the Target/Milestone dates in the table below.
Bidder is to identify at least three potential problem areas that may affect successful subcontract completion and Bidder’s proposed resolution of each problem should it occur.
Based on the successful Bidder’s Preliminary Subcontract Schedule and CONTRACTOR requirements, an agreed schedule shall be developed after award, in accordance with RFP-0000300 Section 15.0, Schedule.
| Pre-bid Meeting & Site Visit |
| 04/10/2019 & 04/11/2019 |
| Notice of Award (NOA) |
| 08/30/2019 |
| Preparedness Review Complete |
| 10/25/2019 |
| Notice to Proceed (NTP) |
| 10/31/2019 |
| Begin Mobilization |
| 11/4/2019 |
| Final Closeout Report Due |
| 12/27/2020 |
| Pre-bid Meeting & Site Visit |
| 04/10/2019 & 04/11/2019 & 06/19/2019 |
| Offer/Proposal Due Date |
| 07/08/2019 |
| Notice of Award (NOA) |
| 08/30/2019 |
| Submittals, Preparedness Review, SAP, PEP, Training Complete |
| 10/25/2019 |
| Investigation and Remediation of SWMU 21-022(i) and AOC C-21-006 Complete |
| 12/19/2019 |
| DP West Tunnels Characterization Complete |
| 05/22/2020 |
| D&D, Size Reduction, Soil Sampling & Remediation, Waste Loading & Weighing & Staging of Western 1/3 DP West Slabs, Tunnels & Foundations Compete |
| 07/10/2020 |
| D&D, Size Reduction, Soil Sampling & Remediation, Waste Loading & Weighing & Staging of Middle 1/3 DP West Slabs, Tunnels & Foundations Compete |
| 08/14/2020 |
| D&D, Size Reduction, Soil Sampling & Remediation, Waste Loading & Weighing & Staging of Eastern 1/3 DP West Slabs, Tunnels & Foundations Compete |
| 10/18/2020 |
| Backfilling and Site Restoration Complete |
| 11/20/2020 |
| Demobilization and Site Cleanup Complete |
| 12/08/2020 |
| Final Closeout Report Due |
| 12/27/2020 |
PR# RFP-0000300