Exhibit_C_Form_D_Subcontract_Schedule_-_5.30.19__-_Amendment_3_FINAL.doc

DOC document 64 KB Posted

Attached to
TA-21 DP West Slabs D&D and Remediation Project
Solicitation number
RFP-0000300
Issued by

About this file

Exhibit C Form D, Subcontract Schedule

View the file

Other files

File Type Posted
Exhibit_A_General_Conditions_Rev_0.doc DOC document
IMG_0015_TA21_150_basement.jpg JPG image
Exhibit_B_Special_Conditions_Rev_0_Draft.docx DOCX document
RFP-0000300_questions_log_-_6.12.19_-_Amendment_4.docx DOCX document
IMG_0018_TA21_150_basement.jpg JPG image
IMG_0016_TA21_150_basement.jpg JPG image
IMG_0014_TA21_150_basement.jpg JPG image
DB_NM190022_04-05-2019_NM22.pdf PDF
IMG_0008_TA21_150_basement.jpg JPG image
IMG_0017_TA21_150_basement.jpg JPG image
Exhibit_C_Form_A_-_DP_West_Slabs_Schedule_Activities_-_Amendment_4_-_6.13.19.docx DOCX document
IMG_0019_TA21_150_basement.jpg JPG image
Exhibit_H_TA_21_DP_West_Slabs_Final_with_signatures_-_Amendment_4_-_6.12.19.pdf PDF
EXHIBIT_L_Prime_Contract_Flow_Downs.docx DOCX document
IMG_0013_TA21_150_basement.jpg JPG image
RFP-0000300_questions_log_-_5.28.19_-_Amendment_3_FINAL.docx DOCX document
Exhibit_F_Attachments,_F7.0_revised_5.30.19.pdf PDF
N3B_Waste_Acceptance_Criteria,_N3B-P409-1,_Rev._0.pdf PDF
Appendix_D-7_Training_matrix_TA-21_DP_West_Slabs_-_Exhibit_F_-_Amendment_3_-_5.30.19.pdf PDF
Exhibit_C_Form_A_-_DP_West_Slabs_Schedule_Activities_-_Amendment_3_-_5.30.19_FINAL.docx DOCX document
Exhibit_D_TA-21_DP_West_Slabs_(FINAL_5-30-19)_for_amendment_3.docx DOCX document
RFP-0000300_questions_log_-_5.20.19.docx DOCX document
18-0031_TA21_DPWest_Contour_Map.pdf PDF
Attachment_D-18_map_point_202_pipe_stub_photo_5.8.19.pdf PDF
Form_9072_-_RFP-0000300_TA-21_DP_West_Slabs_-_revised_for_amendment_2_-_5.20.19.docx DOCX document
RFP-0000300_Amendment__1_Reissue_5_01_19.docx DOCX document
Exhibit_C_Form_F_Project_Organization_and_Workplan_-_4.30.19.doc DOC document
Exhibit_C_Form_H_Resumes_of_Key_Personnel_-_05.01.19.doc DOC document
Exhibit_D_TA-21_DP_West_Slabs_(FINAL_4-30-19).docx DOCX document
Exhibit_C_Form_C-1_Lower_Tier_Experience_Statement_-_4.30.19.doc DOC document
Exhibit_C_Form_A_-_DP_West_Slabs_Schedule_Activities_-_FINAL_-_4.30.19.docx DOCX document
Exhibit_C_Form_N_Experience_Statement_-_FINAL_4.30.19.doc DOC document
Exhibit_C_Form_D_Subcontract_Schedule_-_5.01.19.doc DOC document
D-_10_(17_of_18)_N3B-SOP-ER-2005,_r.0_-_Background_Comparisons_for_Radionuclides.pdf PDF
Exhibit_G_TA-21_Delta_Prime_West_Slabs_Project.pdf PDF
N3B_Form_9060_Insurance_Requirements.pdf PDF
Appendix_D-7_Training_matrix_TA-21_DP_West_Slabs.pdf PDF
Attachment_D-13_N3B_Request_for_Information_Form.pdf PDF
D-_10_(4_of_18)_N3B_P101-17_R3_Excavation_Fill_Soil_Disturbance.pdf PDF
D-_10_(12_of_18)_N3B_LA-UR-11-10371_R0_N3B_Storm_Water_BMP_Manual.pdf PDF
D-12_Threemile_SIR_R1_July18.pdf PDF
D-16_(2_of_3)_NMED_SSG_VOL-I_-March_2017_revised.pdf PDF
D-14_N3B_CoE_SDDR.pdf PDF
D-_10_(14_of_18)_N3B-AP-ER-0001,_r.0_Document_Development_for_Environmental_Deliverables.pdf PDF
D-_10_(5_of_18)_N3B_P151-1_R5_Packaging_and_Transportation_Program_Procedure.pdf PDF
Attachment_D-18_TA-21_Site_Cleanup_Items.pdf PDF
D-_10_(9_of_18)_N3B_ER-SOP-10093_R1_Sample_Control_and_Field_Documentation.pdf PDF
Form_9072_-_RFP-0000300_TA-21_DP_West_Slabs_-Final.pdf PDF
Exhibit_C_Form_B_Construction_Plant_Equipment_List_(new)_-_FINAL.doc DOC document
D-_10_(7_of_18)_N3B_ER-SOP-20145_R0_REQUESTING_AND_MANAGING_DATA_SETS.pdf PDF
Show 40 more

Latest 50 of 98 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ex C Form D (Rev. 1, 9/22/08) Exhibit C Form D – Subcontract Schedule May 31, 2019

EXHIBIT “C”

FORM D

SUBCONTRACT SCHEDULE

PN: Edit the Clause titles identified below to fit the Subcontract pro forma being used. For example, Services and Architect/Engineer proformas incorporate schedule requirements in the milestone clause.

Bidder to submit a Preliminary Subcontract Schedule addressing the Subcontract Target and Milestone dates listed in the Task Order Schedule and the Target/Milestone dates in the table below.

Bidder is to identify at least three potential problem areas that may affect successful subcontract completion and Bidder’s proposed resolution of each problem should it occur.

Based on the successful Bidder’s Preliminary Subcontract Schedule and CONTRACTOR requirements, an agreed schedule shall be developed after award, in accordance with RFP-0000300 Section 15.0, Schedule.

Milestones
Due Date
Issue RFP
04/08/2019
Pre-bid Meeting & Site Visit
04/10/2019 & 04/11/2019
Notice of Award (NOA)
08/30/2019
Preparedness Review Complete
10/25/2019
Notice to Proceed (NTP)
10/31/2019
Begin Mobilization
11/4/2019
Final Closeout Report Due
12/27/2020
Targets
Due Date
Issue RFP
04/08/2019
Pre-bid Meeting & Site Visit
04/10/2019 & 04/11/2019 & 06/19/2019
Questions Due
06/24/2019
Offer/Proposal Due Date
07/08/2019
Notice of Award (NOA)
08/30/2019
Submittals, Preparedness Review, SAP, PEP, Training Complete
10/25/2019
Investigation and Remediation of SWMU 21-022(i) and AOC C-21-006 Complete
12/19/2019
DP West Tunnels Characterization Complete
05/22/2020
D&D, Size Reduction, Soil Sampling & Remediation, Waste Loading & Weighing & Staging of Western 1/3 DP West Slabs, Tunnels & Foundations Compete
07/10/2020
D&D, Size Reduction, Soil Sampling & Remediation, Waste Loading & Weighing & Staging of Middle 1/3 DP West Slabs, Tunnels & Foundations Compete
08/14/2020
D&D, Size Reduction, Soil Sampling & Remediation, Waste Loading & Weighing & Staging of Eastern 1/3 DP West Slabs, Tunnels & Foundations Compete
10/18/2020
Backfilling and Site Restoration Complete
11/20/2020
Demobilization and Site Cleanup Complete
12/08/2020
Final Closeout Report Due
12/27/2020