Reference Only - Basis of Design BOD Part 2 of 7.pdf

PDF 5 MB Posted

Attached to
Y1DZ--437-21-205 EHRM Infrastructure Upgrades Construction Fargo, ND
Solicitation number
36C77622B0030
Issued by

About this file

This architectural basis of design document outlines plans to upgrade the IT infrastructure at the Fargo VA Health Care System campus. The project will modify existing rooms and combine spaces to expand telecommunication rooms and meet new size standards. Where full rooms are not feasible, existing racks will be replaced with new cabinets or racks. One new building addition is planned to house an additional telecommunication room. The design provides target criteria for telecommunication rooms and identifies each space by labeling planned modifications on building floor plans. Related solicitation 36C77622B0030 seeks construction services including demolition, new construction, mechanical, electrical and other work to complete the Fargo VA Health Care System project 437-21-205 to upgrade the entire campus IT infrastructure to current VA and industry standards while minimizing downtimes through coordination and phasing of the work.

View the file

Other files

File Type Posted
Wage Rates - Cass County - 6.17.22.pdf PDF
36C77622B0030 0005.docx DOCX document
Addendum Fiber Duct Bank.pdf PDF
36C77622B0030 0004.docx DOCX document
Technical Question Tracking Sheet - Infra Upgrades - Fargo.docx DOCX document
PCRA 437-21-205 Zone 2.pdf PDF
ICRA Zones.pdf PDF
PCRA 437-21-205 Zone 4.pdf PDF
36C77622B0030 0003.pdf PDF
PCRA 437-21-205 Zone 5.pdf PDF
PCRA 437-21-205 Zone 3.pdf PDF
36C77622B0030 0002.pdf PDF
Site Visit Sign-in Sheet - Fargo.pdf PDF
36C77622B0030 0001.pdf PDF
Wage Rates - Cass County - 4.15.22.pdf PDF
36C77622B0030 0001.pdf PDF
Wage Rates - Cass County - 4.25.22.pdf PDF
Reference Only - Basis of Design BOD Part 3 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 7 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 6 of 7.pdf PDF
BOD Appendix A ACM Survey Report.pdf PDF
Specifications Vol 01 Rev.pdf PDF
36C77622B0030_1.pdf PDF
Drawings Part 7 of 9.pdf PDF
Reference Only - EHRM Design Alerts 1-8.pdf PDF
COVID-19 Safety Protocols 12-14-21.pdf PDF
Contractor Safety - Environmental Form.docx DOCX document
Reference Only - Basis of Design BOD Part 5 of 7.pdf PDF
Specifications Vol 02 Rev.pdf PDF
Reference Only - Basis of Design BOD Part 1 of 7.pdf PDF
Drawings Part 2 of 9.pdf PDF
Drawings Part 6 of 9.pdf PDF
Drawings Part 8 of 9.pdf PDF
Reference Only - Basis of Design BOD Part 4 of 7.pdf PDF
Drawings Part 9 of 9.pdf PDF
Drawings Part 4 of 9.pdf PDF
Drawings Part 1 of 9.pdf PDF
Drawings Part 5 of 9.pdf PDF
Reference Only - Infra Stdrd for Telecomm Spaces 3.1 - ISTS.pdf PDF
Drawings Part 3 of 9.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Architectural Basis of Design

• Summary

• Architectural Design

• Program Analysis

• Building Plan Analysis

• Floor Plans

BASIS OF DESIGN: ARCHITECTURAL

Fargo VA Health Care System | EHRM Infrastructure Upgrades | March 18, 2022

2-1

2 ARCHITECTURAL BASIS OF DESIGN

SUMMARY

The primary focus of this project is to prepare a coordinated design for upgrading the fiber optic system throughout the campus buildings to each telecommunication room

(TR), new fiber to each TR, run new upgraded ethernet cabling from TRs to data drops, install additional IT outlets, install new electrical outlets throughout the campus, provide additional normal, critical and UPS outlets in TRs, upgrade campus power distribution as required, and increase twenty six TR footprints to meet new standards.

Upgrades to the existing Main Computer Room (MCR) will be included in the design as required to properly serve the upgrades the TRs. This will include at a minimum

UPS to support the TRs, 3-phase power to the TRs and source A fiber to the TRs.

ARCHITECTURAL DESIGN

The baseline architectural portion of the work is providing for demolition of existing walls and doors as necessary to accommodate expanded TR footprints, new walls and new or relocated doors as required. The existing finishes in the designated TR rooms are to be removed to bare walls, which will be prepped for paint and installation of fire-rated backboards. Any existing ceiling assemblies are to be removed. Any existing floor finishes are to be removed and the concrete substrate prepped for installation of static-dissipative tile. Rooms are to be finished out as described in the

Room Finish Schedule as part of the contract drawings.

Walls surrounding each TR will be extended as required to the underside of deck above. Walls will be upgraded to be 1-hour rated - including fire-rated sealant at the tops and bottoms of each wall. All existing and new penetrations will receive re-enterable fire stop assemblies.

Target Design Criteria for each TR is as follows:

• In Healthcare/Mission Critical Areas

• Minimum 100 SF for legacy space TRs to accommodate two (2) racks.

• Minimum 170 SF for new TRs built as building additions to accommodate four (4) racks.

• All enclosure walls to be one hour rated construction.

• Code– plus feature requested by the Station.

• All TR doors to be three-quarter hour rated construction.

• Code– plus feature requested by the Station.

• TR doors to be minimum 3’-0” wide by 8-0” high.

• Doors to be knock-down type frames per Station standard.

• Floors to be Static –dissipative tile.

• No finished ceilings, unless needed to meet fire separation requirements.

Where these criteria cannot be met due to existing construction limitations, BAE is working with the Station to develop a list of variance requests to submit to the EHRM

National group. For example, it has been determined that an 8’-0” high door cannot be accommodated in the majority of locations. A variance will need to be requested for these locations.

Due to existing conditions constraints several buildings will not receive full TR enclosures. At those buildings existing telecommunication racks will be replaced with new cabinets or racks (as identified in the Program Analysis later in this report). These include Buildings 10, 11, 12, 13, 30 and 56. This approach has been vetted and approved by the Station and DCIE.

Building 51 was designated by the VA Station to receive a building addition to house a

TR. The design developed to date has been vetted and approved by the Station and

DCIE.

2-2

2 ARCHITECTURAL BASIS OF DESIGN

PROGRAM ANALYSIS

The following spreadsheet was provided to BAE by the Station and has been adopted by the design team to track the required modifications of existing rooms in order to design the new TRs. This spreadsheet was initially verified during the September 13 through 14, 2021 site investigation and has been amended and updated following the

35% and 50% submittal review meetings as required to track development of the baseline design.

2-3

PROGRAM ANALYSIS

2 ARCHITECTURAL BASIS OF DESIGN

Yes Expansion/relocation is required - in scope

No No expansion/relocation is required - out of scope

No No expansion/relocation is feasible - out of scope

2-4

2 ARCHITECTURAL BASIS OF DESIGN

BUILDING PLAN ANALYSIS

Following the Program Analysis spreadsheet are building floor plans for all buildings to be provided new TRs as part of this Scope of Work. The plans illustrate the locations of all new TRs and free standing server cabinets as part of the baseline design.

2-5

KEY

Modify existing room to meet

EHRM TR requirements.

Combine rooms to create

EHRM TR

Modify existing room: will not meet EHRM TR requirements.

Replace existing rack with new cabinet or rack as identified in

Program Analysis

Building addition for new

EHRM TR

IT Equipment to be Replaced

2-6

Combine rooms to create

EHRM TR

2-7

Combine rooms to create

EHRM TR

2-8

Combine rooms to create

EHRM TR

2-9

Combine rooms to create

EHRM TR

2-10

Combine rooms to create

EHRM TR

2-11

Combine rooms to create

EHRM TR

New room for EHRM TR

2-12

Combine rooms to create

EHRM TR

2-13

Combine rooms to create

EHRM TR

2-14

Combine rooms to create

EHRM TR

2-15

Combine rooms to create

EHRM TR

2-16

Combine rooms to create

EHRM TR

2-17

Combine rooms to create

EHRM TR

2-18

Combine rooms to create

EHRM TR

2-19

Combine rooms to create

EHRM TR

2-20

Combine rooms to create

EHRM TR

2-21

Combine rooms to create

EHRM TR

File details come from the government source that posted it. Updated .