Y1DZ--437-21-205 EHRM Infrastructure Upgrades Construction Fargo, ND
Solicitation number
36C77622B0030
Issued by

About this file

This amendment to solicitation 36C77622B0030 provides technical questions and answers and attachments related to infrastructure upgrades at the Fargo VA Health Care System. The construction work includes upgrades to the IT infrastructure across the entire Fargo campus to the latest VA and industry standards, including demolition, new construction, various trades, asbestos abatement, and other work. Phasing and coordination must keep downtimes to a minimum. Relevant attachments include technical question tracking, ICRA and PCRA zone maps outlining the scope of work areas. The response due date is not impacted by this amendment.

View the file

Other files

File Type Posted
Wage Rates - Cass County - 6.17.22.pdf PDF
36C77622B0030 0005.docx DOCX document
Addendum Fiber Duct Bank.pdf PDF
36C77622B0030 0004.docx DOCX document
Technical Question Tracking Sheet - Infra Upgrades - Fargo.docx DOCX document
PCRA 437-21-205 Zone 2.pdf PDF
ICRA Zones.pdf PDF
PCRA 437-21-205 Zone 4.pdf PDF
PCRA 437-21-205 Zone 5.pdf PDF
PCRA 437-21-205 Zone 3.pdf PDF
36C77622B0030 0002.pdf PDF
Site Visit Sign-in Sheet - Fargo.pdf PDF
36C77622B0030 0001.pdf PDF
Wage Rates - Cass County - 4.15.22.pdf PDF
36C77622B0030 0001.pdf PDF
Wage Rates - Cass County - 4.25.22.pdf PDF
Reference Only - Basis of Design BOD Part 3 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 2 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 7 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 6 of 7.pdf PDF
BOD Appendix A ACM Survey Report.pdf PDF
Specifications Vol 01 Rev.pdf PDF
36C77622B0030_1.pdf PDF
Drawings Part 7 of 9.pdf PDF
Reference Only - EHRM Design Alerts 1-8.pdf PDF
COVID-19 Safety Protocols 12-14-21.pdf PDF
Contractor Safety - Environmental Form.docx DOCX document
Reference Only - Basis of Design BOD Part 5 of 7.pdf PDF
Specifications Vol 02 Rev.pdf PDF
Reference Only - Basis of Design BOD Part 1 of 7.pdf PDF
Drawings Part 2 of 9.pdf PDF
Drawings Part 6 of 9.pdf PDF
Drawings Part 8 of 9.pdf PDF
Reference Only - Basis of Design BOD Part 4 of 7.pdf PDF
Drawings Part 9 of 9.pdf PDF
Drawings Part 4 of 9.pdf PDF
Drawings Part 1 of 9.pdf PDF
Drawings Part 5 of 9.pdf PDF
Reference Only - Infra Stdrd for Telecomm Spaces 3.1 - ISTS.pdf PDF
Drawings Part 3 of 9.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

06-29-22

437-21-205

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

00076

Department of Veterans Affairs Department of Veterans Affairs

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

To all Offerors/Bidders

36C77622B0030

06-29-2022

X

X X

NA

X 1 (ONE)

The purpose of this amendment is to provide the following:

1. A copy of the Fargo EHRM Technical Questions and answers.

2. Attachments that were discussed within question #24

Donald A. Marsh III Contracting Officer

PCAC15L3-1697

See attached document: Technical Question Tracking Sheet - Infra Upgrades - Fargo.

See attached document: ICRA Zones.

See attached document: PCRA 437-21-205 Zone 2.

See attached document: PCRA 437-21-205 Zone 3.

See attached document: PCRA 437-21-205 Zone 5.

See attached document: PCRA 437-21-205 Zone 4.

End of Document