36C77622B0030 0002.pdf

PDF 292 KB Posted

Attached to
Y1DZ--437-21-205 EHRM Infrastructure Upgrades Construction Fargo, ND
Solicitation number
36C77622B0030
Issued by

About this file

This document includes a federal solicitation and related contract amendment. The solicitation is for construction work at the Fargo VA Health Care System to complete project 437-21-205 for EHRM Infrastructure Upgrades. The scope of work includes demolition, new construction, plumbing, mechanical HVAC, fire protection sprinklers, electrical lighting, power and systems, asbestos abatement, masonry, structural work, and other efforts required by the contract documents to upgrade the entire Fargo campus IT infrastructure to the latest VA and industry standards while keeping downtimes to a minimum. The solicitation was issued by the Department of Veterans Affairs Technology Acquisition Center Austin. The contract amendment provides an updated contract clause for payments under fixed-price construction contracts and does not include any additional scope requirements.

View the file

Other files

File Type Posted
Wage Rates - Cass County - 6.17.22.pdf PDF
36C77622B0030 0005.docx DOCX document
Addendum Fiber Duct Bank.pdf PDF
36C77622B0030 0004.docx DOCX document
Technical Question Tracking Sheet - Infra Upgrades - Fargo.docx DOCX document
PCRA 437-21-205 Zone 2.pdf PDF
ICRA Zones.pdf PDF
PCRA 437-21-205 Zone 4.pdf PDF
36C77622B0030 0003.pdf PDF
PCRA 437-21-205 Zone 5.pdf PDF
PCRA 437-21-205 Zone 3.pdf PDF
Site Visit Sign-in Sheet - Fargo.pdf PDF
36C77622B0030 0001.pdf PDF
Wage Rates - Cass County - 4.15.22.pdf PDF
36C77622B0030 0001.pdf PDF
Wage Rates - Cass County - 4.25.22.pdf PDF
Reference Only - Basis of Design BOD Part 3 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 2 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 7 of 7.pdf PDF
Reference Only - Basis of Design BOD Part 6 of 7.pdf PDF
BOD Appendix A ACM Survey Report.pdf PDF
Specifications Vol 01 Rev.pdf PDF
36C77622B0030_1.pdf PDF
Drawings Part 7 of 9.pdf PDF
Reference Only - EHRM Design Alerts 1-8.pdf PDF
COVID-19 Safety Protocols 12-14-21.pdf PDF
Contractor Safety - Environmental Form.docx DOCX document
Reference Only - Basis of Design BOD Part 5 of 7.pdf PDF
Specifications Vol 02 Rev.pdf PDF
Reference Only - Basis of Design BOD Part 1 of 7.pdf PDF
Drawings Part 2 of 9.pdf PDF
Drawings Part 6 of 9.pdf PDF
Drawings Part 8 of 9.pdf PDF
Reference Only - Basis of Design BOD Part 4 of 7.pdf PDF
Drawings Part 9 of 9.pdf PDF
Drawings Part 4 of 9.pdf PDF
Drawings Part 1 of 9.pdf PDF
Drawings Part 5 of 9.pdf PDF
Reference Only - Infra Stdrd for Telecomm Spaces 3.1 - ISTS.pdf PDF
Drawings Part 3 of 9.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

05-25-2022

437-21-205

36C776

Department of Veterans Affairs Program Contracting Activity Central

6150 Oak Tree Blvd, Suite 300 Independence OH 44131

00076

Department of Veterans Affairs Department of Veterans Affairs

6150 Oak Tree Blvd, Suite 300 Independence OH 44131

To all Offerors/Bidders 36C77622B0030

06-16-2022 X

X X

NA

X 1 (ONE)

The purpose of this amendment is to provide the following

1. A copy of the site visit sign in sheet.

2. VAAR 852.232-70 has now been updated to reflect 852.232-71 and has been attached with this amendment.

Donald A. Marsh III Contracting Officer

PCAC15L3-1697

A.1 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)

The clause FAR 52.232–5, Payments Under Fixed-Price Construction Contracts, is implemented as follows:

(a) Retainage.

(1) The Contracting Officer may retain funds—

(i) Where performance under the contract has been determined to be deficient or the Contractor has performed in an unsatisfactory manner in the past; or

(ii) As the contract nears completion, to ensure that deficiencies will be corrected and that completion is timely.

(2) Examples of deficient performance justifying a retention of funds include, but are not restricted to, the following—

(i) Unsatisfactory progress as determined by the Contracting Officer;

(ii) Failure to meet schedule in Schedule of Work Progress;

(iii) Failure to present submittals in a timely manner; or

(iv) Failure to comply in good faith with approved subcontracting plans, certifications, or contract requirements.

(3) Any level of retention shall not exceed 10 percent either where there is determined to be unsatisfactory performance, or when the retainage is to ensure satisfactory completion.

Retained amounts shall be paid promptly upon completion of all contract requirements, but nothing contained in this paragraph (a)(3) shall be construed as limiting the Contracting Officer’s right to withhold funds under other provisions of the contract or in accordance with the general law and regulations regarding the administration of Government contracts.

(b) The Contractor shall submit a schedule of costs in accordance with the requirements of section ‘‘Network Analysis System—Critical Path Method (NAS–CPM)’’ to the Contracting Officer for approval within 90 calendar days after date of receipt of notice to proceed. The approved cost schedule will be one of the bases for determining progress payments to the Contractor for work completed.

(1) Costs as shown on this schedule must be true costs and the resident engineer may require the Contractor to submit its original estimate sheets or other information to substantiate the detailed makeup of the cost schedule.

(2) The total costs of all work activities/events shall equal the contract price.

(3) Insurance and similar items shall be prorated and included in each work activity/event cost of the critical path method (CPM).

(4) The CPM shall include a separate cost loaded activity for adjusting and testing of the systems listed in the table in paragraph (b)(5) of this clause. The percentages listed in paragraph (b)(5) will be used to determine the cost of adjust and test work activities/events and identify, for payment purposes, the value of the work to adjust, correct and test systems after the material has been installed.

(5) Payment for adjust and test activities will be made only after the Contractor has demonstrated that each of the systems is substantially complete and operates as required by the contract.

VALUE OF ADJUSTING, CORRECTING, AND TESTING SYSTEM

System Percen t

Pneumatic tube system………………………………………………………………………………. 10

Incinerators (medical waste and trash)……………………………………………………….. 5

Sewage treatment plant equipment……………………………………………………………. 5

Water treatment plant equipment……………………………………………………………… 5

Washers (dish, cage, glass, etc.)………………………………………………………………….. 5

Sterilizing equipment……………………………………………………………………………….…. 5

Water distilling equipment…………………………………………………………………………. 5

Prefab temperature rooms (cold, constant temperature)………………………….. 5

Entire air-conditioning system (Specified under 600 Sections)…………………… 5

Entire boiler plant system (Specified under 700 Sections)………………………….. 5

General supply conveyors…………………………………………………………………………… 10

Food service conveyors………………………………………………………………………….…… 10

Pneumatic soiled linen and trash system…………………………………………………… 10

Elevators and dumbwaiters………………………………………………………………………… 10

Materials transport system…………………………………………………………………………. 10

Engine-generator system……………………………………………………………………………. 5

Primary switchgear…………………………………………………………………………………… … 5

Secondary switchgear………………………………………………………………………………….. 5

Fire alarm system………………………………………………………………………………………… 5

Nurse call system………………………………………………………………………………………… 5

Intercom system………………………………………………………………………………………… .. 5

Radio system………………………………………………………………………………………… …….. 5

TV (entertainment) system………………………………………………………………………… 5

(c) In addition to this cost schedule, the Contractor shall submit such unit costs as may be specifically requested. The unit costs shall be those used by the Contractor in preparing its bid and will not be binding as pertaining to any contract changes.

(d) The Contracting Officer will consider for monthly progress payments material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site, under such terms and conditions as the Contracting Officer approves, including but not limited to the following—

(1) The materials or equipment are in accordance with the contract requirements and/or approved samples and shop drawings;

(2) The materials and/or equipment are approved by the resident engineer;

(3) The materials and/or equipment are stored separately and are readily available for inspection and inventory by the resident engineer;

(4) The materials and/or equipment are protected against weather, theft and other hazards and are not subjected to deterioration; and

(5) The Contractor obtains the concurrence of its surety for off-site storage.

(e) The Government reserves the right to withhold payment until samples, shop drawings, engineer’s certificates, additional bonds, payrolls, weekly statements of compliance, proof of title, nondiscrimination compliance reports, or any other requirements of this contract, have been submitted to the satisfaction of the Contracting Officer.

(f) The Contracting Officer will notify the Contractor in writing within 10 calendar-days of exercising retainage against any payment in accordance with FAR clause 52.232–5(e). The notice shall disclose the amount of the retainage in value and percent retained from the payment, and provide explanation for the retainage.

(End of Clause)

End of Document

A.1 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)

File details come from the government source that posted it. Updated .