Attachment_1_F.1_52.211-10.pdf
FAR Clause PDF 12 KB Posted
- Attached to
- NGWSP Block 9 through 11
- Solicitation number
- R17PS00812
About this file
Attachment 1
View the file
Other versions and copies of FAR 52.211-10
| File | Revision | Posted | Attached to |
|---|---|---|---|
| Amendment 1_SEC F_FAR 52.211-10_Page 14 of 48.doc | Amendment 1 | RECOVERY - CUSTER NATIONAL FOREST, FY09 West Fork Rock Creek Road Reconstruction | |
| B.08_W9127N21B00180002-Bids Due 12May21 & 52.211-10 Revision.pdf | May 12, 2021 | Rogue River Mechanical Dredging 2021 | |
| Revised Clause F.1 52.211-10.doc | Revision not stated | Mitchelson Wetlands Restoration |
Who attaches FAR 52.211-10
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK
APR 1984
The Contractor shall be required to
(a) commence work under this contract within 10 calendar days after the date the Contractor receives:
1) Notice to Proceed for non-site work under this contract,
2) Notice to Proceed for site work on Reach 10 (Station 10003+58.44 to Station 10050+57 and the
Temporary 6-Inch Construction Water Line), and Reach 11 (Station 11058+00 to Station 11279+80), which is anticipated to be issued no later than January 29, 2018, and
3) Notice to Proceed for site work on Reach 9 (Station 90000+00 to Station 91220+00), which is anticipated to be issued no later than June 25, 2018.
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 910 calendar days after the contractor receives the initial non-site work Notice to Proceed issued in accordance with (a)(1) above. The time stated for completion shall include final cleanup of the premises.