About this file
Revised Clause F.1 52.211-10
View the file
Other versions and copies of FAR 52.211-10
| File | Revision | Posted | Attached to |
|---|---|---|---|
| Amendment 1_SEC F_FAR 52.211-10_Page 14 of 48.doc | Amendment 1 | RECOVERY - CUSTER NATIONAL FOREST, FY09 West Fork Rock Creek Road Reconstruction | |
| B.08_W9127N21B00180002-Bids Due 12May21 & 52.211-10 Revision.pdf | May 12, 2021 | Rogue River Mechanical Dredging 2021 | |
| Attachment_1_F.1_52.211-10.pdf | Revision not stated | NGWSP Block 9 through 11 |
Who attaches FAR 52.211-10
Other files
| File | Type | Posted |
|---|---|---|
| Signed Abstract of Offers.pdf | ||
| Amend No. 1 SF30 for Site Showing.pdf | ||
| Construction Plan revised page 19 of 21.pdf | ||
| Site Showing Minutes.docx | DOCX document | |
| Construction Plan revised page 2 of 21.pdf | ||
| Construction Plan revised page 18 of 21.pdf | ||
| Construction Plans.pdf | ||
| Construction Specifications.pdf | ||
| SF1442.doc | DOC document | |
| Wage Rates.mht | MHT file | |
| Solicitation packet.doc | DOC document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE
AG-6215-S-12-0014 Page 8 of 43
TABLE OF CONTENTS
SECTION F - DELIVERIES OR PERFORMANCE
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 105 calendar days after receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.