Attachment_2_I.26_WBR_1452.232-81_AltIII.pdf

PDF 19 KB Posted

Attached to
NGWSP Block 9 through 11 Federal contract opportunity
Solicitation number
R17PS00812
Issued by
Department of the Interior Bureau of Reclamation

About this file

Attachment 2

View the file

Other files for this federal contract opportunity

Other files attached to NGWSP Block 9 through 11, newest first.
File Type Posted
Attachment_5_Test_Pit_Photos.pdf PDF
Attachment_6_Block_9-11_Q&A's.docx DOCX document
Attachment_4_Drill_Hole_Photos.pdf PDF
SF-30_R17PS00812_Amendment_5.pdf PDF
Attachment_3_REVISED_Drawings.pdf PDF
Attachment_2_REVISED_Specifications.pdf PDF
Attachment_1_REVISED_Schedule_B.docx DOCX document
Attachment_3_REVISED_Specifications.pdf PDF
Attachment_1_REVISED_R17PS00812_Schedule_B.pdf PDF
Attachment_2_REVISED_Continuation_of_Section_B_in_excel.xlsx XLSX spreadsheet
Attachment_5_Block_9-11_Q&A's_7-28-2017.docx DOCX document
Attachment_4_REVISED_Drawings.pdf PDF
SF_30.pdf PDF
Attachment_3_REVISED_Specifications.pdf PDF
Attachment_4_REVISED_Drawings.pdf PDF
SF-30_Amendment_000003.pdf PDF
Attachment_1_REVISED_R17PS00812_Schedule_B.docx DOCX document
Attachment_2_REVISED_Continuation_of_Section_B_in_excel.xlsx XLSX spreadsheet
SF-30_Amendment_2.pdf PDF
Attachment_6_Block_9-11_Site_Tour_Q&A's.docx DOCX document
Attachment_3_L.15_WBR_1452.236-86.pdf PDF
Attachment_1_F.1_52.211-10.pdf PDF
Attachment_5_Block_9_-_11_SITE_TOUR_AGENDA.pdf PDF
Attachment_4_Sign-in_sheet.pdf PDF
Tab_13_SF-30_AMD_000001.pdf PDF
Attachment_6_Past_Performance_Questionnaire.pdf PDF
Attachment_5_Wage_Rate_Requirements_(Construction)_Wage_Determinations.pdf PDF
Attachment_3_Geology_Drawings_And_Logs.pdf PDF
Attachment_4_Continuation_of_Section_B_in_excel.xlsx XLSX spreadsheet
Attachment_1_Specifications.pdf PDF
Attachment_2_Drawings.pdf PDF
Attachment_7_Site_Visit_Location_Maps.pdf PDF
R17PS00812.pdf PDF
Tab_09_Synopsis_(1).docx DOCX document
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

I.26 WBR

1452.232-81

ALT III

PAYMENT FOR MOBILIZATION AND PREPARATORY

WORK– BUREAU OF RECLAMATION ALT III(JUN 2002)

MAY 2000

(a) General. Payment for the Mobilization and Preparatory Work line items of the schedules will be made as reflected herein. To the extent that this line item exceeds the percentages of total schedule pricing as estimated by the Contracting Officer in WBR 1452.236-86, Instruction for Mobilization and Preparatory Work Schedule Line Item, payment will be made as reflected in Section (d)(3), (4) and (5) below. Reclamation will make payment to the Contractor in accordance with this clause for operations including, but not limited to, those necessary for --

(1) Movement of personnel, equipment, supplies, and incidentals to the project site;

(2) The establishment of offices, buildings, plants and other facilities, at the site (excludes temporary buildings (e.g. storage sheds, shops, offices) and utilities listed in the Operations and Storage Areas clause of this contract;

(3) Payment of premiums for project bonds and insurance; and

(4) Other work and operations which must be performed or costs incurred incident to the initiation of meaningful work at the site and for which the contract does not otherwise provide for payment.

(5) Approved detailed logic diagram(s) and the baseline schedule.

(b) Facilities and equipment covered by mobilization work.

(1) All facilities, plant, and equipment which are established at, or brought to, the site shall be deemed to be subject to the provisions of this paragraph unless the Contracting Officer specifically provides other written authorization for a particular item or items.

(2) The Contractor shall be solely responsible for the adequacy, efficiency, use, protection, maintenance, repair, and preservation of all facilities, plant, and equipment on site.

(3) The facilities, plant, and equipment covered by this paragraph shall not be dismantled or removed from the site prior to completion of the work under the contract without the written authorization of the Contracting Officer.

(c) Termination for default. Should the Contractor be terminated for default as provided by the Default clause of this contract --

(1) All facilities, plant, and equipment on the site shall be subject to the Government's right to take possession of and utilize such items for the purpose of completing the work;

(2) The Contractor shall provide evidence of encumbrances, liens, or other security interests, to the Contracting Officer; and

(3) Any encumbrance, lien, or other security interest on such facilities, plant, or equipment shall be subordinated to the Government's rights under the Default clause of this contract to utilize all facilities, plant, and equipment to complete the work under the contract.

(d) Payment. Payment for mobilization and preparatory work under paragraph (a) of this clause shall be made at the contractor lump-sum price for this item as contained in the Schedule. Progress payments for mobilization and preparatory work shall be made as follows --

(1) In accordance with paragraph (g) of the Payments under Fixed Price Construction Contracts clause of this contract and upon submission of a proper invoice, the Government will reimburse the Contractor for the total amount of premiums paid for performance and payment bonds as required by the Performance and Payment Bond Requirements clause of this contract and for any insurance which is specified as payable by the Government under this contract.

(2) Except as provided in (d)(1)above, progress payments for mobilization and preparatory work shall not be considered a separate division of work for the purposes of progress payments and shall be subject to retainage before payment of the total amount for this contract line item.

(3) When progress payments totaling five percent (5%) of the total original schedule amount on a schedule have been made by the Government for all other work accomplished under that schedule, the Government shall pay the Contractor 50 percent (50%) of the mobilization and preparatory work schedule line item amount or 2.5 percent (2.5%) of the total original schedule amount (whichever is the lower) exclusive of any payment already made to the Contractor for performance and payment bond premiums and specified insurance under subparagraph (d)(1) of this clause.

(4) When progress payments totaling 10 percent (10%) of the total original schedule amount on a schedule have been made by the Government for all other work accomplished under the schedule and upon approval of the detailed logic diagram(s) and baseline schedule, the balance of the amount for the mobilization and preparatory work schedule line item or 2.5 percent (2.5%) of the total original schedule amount (whichever is the lower) shall be paid to the contractor.

(5) If the schedule amount for mobilization and preparatory work on a schedule exceeds the total of the payments allowed under (3) and (4) above, the balance shall be paid when the schedule work is substantially complete as determined by the Contracting Officer.