PS132603(2) - UPS Battery Replacement Location 64.pdf
PDF 1 MB Posted
- Attached to
- UPS Battery Replacement Location 64
- Solicitation number
- PS132603(2)
- Issued by
- California
About this file
This is an Invitation for Bid (IFB) document issued by the Los Angeles County Metropolitan Transportation Authority (LACMTA) for the replacement of a UPS battery module assembly at Location 64. The project requires the supply and installation of 216 VRLA batteries, consisting of 144 Deka Unigy HR5500 units and 72 Deka Unigy 31H5000 units or approved equals. All work, including installation and acceptance, must be completed within 45 days of contract execution. The contractor shall provide a one-year manufacturer warranty from the date of product receipt and acceptance. The pre-bid conference is scheduled for Wednesday, August 5, 2026, at 10:00 AM via Microsoft Teams, and a mandatory worksite visit is set for Thursday, August 6, 2026, at 10:00 AM (attendance must be confirmed by August 5, 2026, at 4:00 PM). Questions and requests for approved equals are due by Friday, August 14, 2026, at 2:00 PM, with responses provided by August 21, 2026. Sealed bids must be submitted electronically to bids@metro.net no later than 10:00 AM on Thursday, September 3, 2026, with bid opening occurring at 12:00 PM on the same date via Microsoft Teams.
The contract is awarded on a firm fixed unit rate basis to the lowest-priced responsive and responsible bidder. This contract is federally funded and subject to fiscal year funding availability. The contractor must be pre-qualified with LACMTA prior to award if the contract exceeds $500,000 for non-construction contracts. All contractors and first-tier subcontractors must be registered with the California Department of Industrial Relations pursuant to Labor Code 1725.5. Bidders must submit all required forms including bid letters, certification forms, pricing sheets, ethics declarations, general certifications, federal compliance certificates, and DEOD forms. A DBE goal was not established for this procurement due to insufficient DBE availability. The contract documents include special provisions addressing organizational conflicts of interest, worksite access and restoration, insurance requirements (including Commercial General Liability and Automobile Liability coverage), hazardous material identification, and contractor equipment specifications. Payment will be made electronically via Electronic Funds Transfer within thirty days of receipt of a properly submitted invoice, with ten percent retention until fifty percent of services are completed.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
No.
Issued:
UPS Battery Replacement Location 64
IFB PS132603(2)
July 27, 2026
LACMTA ISSUE DATE: July 27, 2026 UPS Battery Replacement Location 64 IFB No. PS132603(2)
TABLE OF CONTENTS
I. LETTER OF INVITATION
LOI-01 NOTICE AND INVITATION
LOI-02 DEFINITIONS
LOI-03 AVAILABILITY OF SOLICITATION DOCUMENTS
LOI-04 COMMUNICATION WITH LACMTA
LOI-05 PRE-BID CONFERENCE
LOI-06 WORKSITE VISIT
LOI-07 BASIS OF AWARD
LOI-08 APPROVED EQUALS (GOODS)
LOI-09 EXHIBITS
LOI-10 CONTRACT DOCUMENTS
LOI-11 INDEMNITY
LOI-12 LIQUIDATED DAMAGES (RESERVED)
LOI-13 SOLICITATION LINKS
LOI-14 CRITICAL DATES
LOI-15 DBE PROGRAM (RESERVED)
LOI-16 SBE/DVBE PROGRAM (RESERVED)
LOI-17 SBE SET-ASIDE PROGRAM (RESERVED)
LOI-18 MSZ PROGRAM (RESERVED)
LOI-19 LSBE PREFERENCE (RESERVED)
LOI-20 LOI SIGNATURES
II. BID INSTRUCTIONS
INSTRUCTIONS TO BIDDERS
IB-01 PRE-QUALIFICATION REQUIREMENTS
IB-02 CONTRACTOR REGISTRATION LAW
IB-03 EXAMINATION OF IFB DOCUMENTS
IB-04 INTERPRETATION OF IFB DOCUMENTS
IB-05 COMMUNICATION WITH LACMTA OTHER THAN THE CONTRACT ADMINISTRATOR
IB-06 AMENDMENTS
IB-07 PREPARATION OF SUBMITTAL
IB-08 MODIFIED AND ALTERNATIVE BIDS
IB-09 SIGNING OF BIDS
IB-10 SUBMISSION AND OPENING OF SEALED BID
IB-11 BID EVALUATION PROCESS
IB-12 DISCREPANCIES IN BID ITEMS
IB-13 WITHDRAWAL OF BID
IB-14 BID MISTAKES
IB-15 LACMTA RIGHTS
IB-16 PUBLIC RECORDS ACT
IB-17 DISQUALIFICATION OF BIDDERS
IB-18 FILING OF PROTESTS
IB-19 BUY BACK (RESERVED)
IB-20 BONDS (RESERVED)
IB-21 BIDDERS LIST FORM
DEOD INSTRUCTIONS
DI-01 - INSTRUCTIONS TO BIDDERS/PROPOSERS
III. BID REQUIREMENTS/FORMS
SUBMITTAL REQUIREMENTS
1.1 GENERAL FORMAT
1.2 BID CONTENT
1.3 BID FORMS
1.4 CERTIFICATION FORMS
1.5 DBE FORMS
UPS Battery Replacement Location 64 IFB No. PS132603(2)
EXHIBITS (SOLICITATION)
EXHIBIT 1 DBE GOOD FAITH EFFORTS AND COMMITMENT FORMS
EXHIBIT 2 SCHEDULE OF QUANTITIES AND PRICES (BID PRICING SHEET)
EXHIBIT 3 LIST OF CERTIFIED FIRMS (RESERVED)
EXHIBIT 4 BIDDERS LIST FORM
EXHIBIT 5 BID LETTER
EXHIBIT 6 LIST OF CURRENT CONTRACTS - BACKLOG
EXHIBIT 7 LIST OF COMPLETED CONTRACTS - LAST FIVE YEARS
EXHIBIT 8 ETHICS DECLARATION
EXHIBIT 9 GENERAL CERTIFICATIONS
EXHIBIT 10 CERTIFICATE OF COMPLIANCE WITH 49 CFR PART 655, PREVENTION OF ALCOHOL
MISUSE AND PROHIBITED DRUG USE IN TRANSIT OPERATIONS
EXHIBIT 11 CERTIFICATION OF COMPLIANCE WITH FEDERAL LOBBYING REQUIREMENTS (49 CFR
PART 20)
EXHIBIT 12 CERTIFICATION OF PROSPECTIVE CONTRACTOR AND LOWER TIER PARTICIPANT
REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY AND VOLUNTARY EXCLUSION
EXHIBIT 13 NONCOLLUSION AFFIDAVIT TO BE EXECUTED BY BIDDER
EXHIBIT 14 MISCELLANEOUS (RESERVED)
EXHIBIT 15 BID BOND (RESERVED)
EXHIBIT 16 QUALITY ASSURANCE / QUALITY CONTROL (RESERVED)
EXHIBIT 17 SAFETY (RESERVED)
EXHIBIT 18 BIDDERS INDUSTRIAL SAFETY RECORD (RESERVED)
IV. CONTRACT DOCUMENTS (SAMPLE)
FORM OF CONTRACT
ARTICLE 0 SIGNATURES
ARTICLE I CONTRACT DOCUMENTS ORDER OF PRECEDENCE
ARTICLE II DEFINITIONS
ARTICLE III SERVICES TO BE PERFORMED/ GOODS TO BE DELIVERED
ARTICLE IV COMPENSATION AND PAYMENT
ARTICLE V CONTRACT TERM AND PERIOD OF PERFORMANCE
ARTICLE VI OPTIONS (RESERVED)
ARTICLE VII AVAILABILITY OF FUNDS
ARTICLE VIII INSURANCE
ARTICLE IX NOTICES AND SERVICE THEREOF*
ARTICLE X ADDITIONAL PROVISIONS
ARTICLE XI ENTIRE AGREEMENT
SPECIAL PROVISIONS
SP-01 DBE PARTICIPATION
SP-02 ORGANIZATIONAL CONFLICTS OF INTEREST*
SP-03 RELEASE OF INFORMATION*
SP-04 WORKSITE ACCESS/RESTORATION
SP-05 INSURANCE REQUIREMENTS
SP-06 LOSS PREVENTION
SP-07 CONTRACTOR EQUIPMENT*
SP-08 HAZARDOUS MATERIAL IDENTIFICATION AND SAFETY DATA
SP-09 CLEAN UP
SP-10 PROTECTION OF STRUCTURES, EQUIPMENT, AND VEGETATION
SP-11 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS*
SP-12 LIQUIDATED DAMAGES* (RESERVED)
SP-13 THE CONTRACTOR'S LICENSE
SP-14 LACMTA MANAGEMENT OF CONTRACTOR'S PERSONNEL*
SP-15 SUBCONTRACT ADMINISTRATION*
SP-16 PAYMENT OF PREVAILING AND LIVING WAGES/REPORTING*
SP-17 LIVING WAGE/SERVICE CONTRACT WORKER RETENTION POLICY * (RESERVED)
GENERAL CONDITIONS
UPS Battery Replacement Location 64 IFB No. PS132603(2)
GC-01 GLOSSARY OF TERMS*
GC-02 GOVERNING LAW*
GC-03 CONTRACT DOCUMENTS
GC-04 INTERPRETATION*
GC-05 AUTHORITY OF THE CONTRACTING OFFICER
GC-06 LACMTA'S TECHNICAL REPRESENTATIVE (PROJECT MANAGER)
GC-07 ORGANIZATIONAL AND KEY PERSONNEL
GC-08 WHISTLEBLOWER REQUIREMENTS*
GC-09 AGENT TO ACCEPT SERVICE
GC-10 ETHICS AUTHORITIES*
GC-11 CONFIDENTIALITY*
GC-12 COVENANT AGAINST CONTINGENT FEES*
GC-13 ENGLISH REQUIREMENTS*
GC-14 LICENSES AND PERMITS
GC-15 GOODS*
GC-16 RIGHTS IN PROPERTY*
GC-17 INDEPENDENT CONTRACTOR
GC-18 SUBCONTRACTORS AND SUPPLIERS*
GC-19 STANDARDS OF PERFORMANCE*
GC-20 INSPECTION OF WORK*
GC-21 FINAL ACCEPTANCE*
GC-22 SAFETY*
GC-23 WARRANTY*
GC-24 SAFETY AND LOSS PREVENTION*
GC-25 UNAUTHORIZED ACTIONS*
GC-26 LIABILITY AND INDEMNIFICATION*
GC-27 PERIOD OF PERFORMANCE
GC-28 EXTENSION OF TIME
GC-29 SUSPENSION*
GC-30 HISTORICAL, ARCHAEOLOGICAL, PALEONTOLOGICAL, AND SCIENTIFIC DISCOVERIES*
GC-31 CHANGES
GC-32 NOTICE OF INTENT TO CLAIM AND CLAIMS
GC-33 RESOLUTION OF DISPUTES
GC-34 SOFTWARE LICENSING AGREEMENT AND PROVISIONS FOR USE*
GC-35 RIGHTS IN TECHNICAL DATA, PATENTS AND COPYRIGHTS*
GC-36 RIGHTS IN TECHNICAL DATA, PATENTS AND COPYRIGHTS*
GC-37 ENVIRONMENTAL COMPLIANCE
GC-38 THE CONTRACTOR'S INTERACTION WITH THE MEDIA AND THE PUBLIC*
GC-39 TERMINATION FOR CONVENIENCE OF LACMTA*
GC-40 TERMINATION FOR DEFAULT*
GC-41 ASSIGNMENT*
GC-42 NO WAIVER
GC-43 SEVERABILITY*
GC-44 AUDIT REQUIREMENTS*
GC-45 CONTRACTOR'S OBLIGATIONS*
REGULATORY REQUIREMENTS
RR-01 ADMINISTRATIVE CODE*
RR-02 DISCRIMINATION*
RR-03 PUBLIC RECORDS ACT*
RR-04 CIVIL RIGHTS REQUIREMENTS*
RR-05 CLEAN WATER AND CLEAN AIR REQUIREMENTS*
RR-06 CONTRACTOR REGISTRATION LAW*
RR-07 COMPLIANCE WITH CALIFORNIA HEALTH AND SAFETY CODE (HSC) §25250.51
RR-08 ALCOHOL AND DRUG-FREE WORKPLACE PROGRAM* (SERVICES & GOODS)
RR-09 ACCESS TO RECORDS
RR-10 FEDERAL FUNDING, INCORPORATION OF FEDERAL TRANSIT ADMINISTRATION (FTA) TERMS, UPS Battery Replacement Location 64 IFB No. PS132603(2)
AND FEDERAL CHANGES*
RR-11 ENERGY CONSERVATION REQUIREMENTS
RR-12 NO GOVERNMENT OBLIGATION TO THIRD PARTIES*
RR-13 PROGRAM FRAUD AND FALSE OR FRAUDULENT STATEMENTS OR RELATED ACTS*
RR-14 SUSPENSION AND DEBARMENT*
RR-15 RECYCLED PRODUCTS
RR-16 COMPLIANCE WITH FEDERAL LOBBYING POLICY*
RR-17 BUY AMERICA*
RR-18 CARGO PREFERENCE*
RR-19 FLY AMERICA
RR-20 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT*
RR-21 SEISMIC SAFETY
RR-22 ADA ACCESS
RR-23 TRANSIT EMPLOYEE PROTECTIVE ARRANGEMENTS*
RR-24 CHARTER SERVICE OPERATIONS
RR-25 SCHOOL BUS REQUIREMENTS
RR-26 FEDERAL PATENT AND DATA RIGHTS*
RR-27 SAFE OPERATION OF MOTOR VEHICLES - SEAT BELT USE*
RR-28 SAFE OPERATION OF MOTOR VEHICLES - DISTRACTED DRIVING*
RR-29 FTA NOTIFICATION FOR FTA CONCERNS*
EXHIBITS (CONTRACT)
EXHIBIT A STATEMENT OF WORK
EXHIBIT B SPECIFICATIONS (RESERVED)
EXHIBIT C PRICING AGREEMENT
EXHIBIT D WORK-COMPLETION/DELIVERABLE SCHEDULE (RESERVED)
EXHIBIT E DIVERSITY & ECONOMIC OPPORTUNITY DEPARTMENT CONTRACT COMPLIANCE MANUAL
(RC-FTA)
EXHIBIT F-1 PAYMENT CERTIFICATION (CONTINUOUS)
EXHIBIT F-2 PAYMENT CERTIFICATION (FINAL)
EXHIBIT G APPROVED SUBCONTRACTORS AND SUPPLIERS
EXHIBIT H MISCELLANEOUS (RESERVED)
EXHIBIT I 49 CRF PART 20 (RESERVED)
EXHIBIT J 29 CFR 5.5 AND APPLICABLE FEDERAL PREVAILING WAGE CLASSIFICATIONS
UPS Battery Replacement Location 64 IFB No. PS132603(2)
I. LETTER OF INVITATION
UPS Battery Replacement Location 64 IFB No. PS132603(2)
LOI-01 NOTICE AND INVITATION
DATE: Monday, July 27, 2026
ATTENTION: PROSPECTIVE BIDDER
SUBJECT: INVITATION FOR BID No. PS132603(2)
SOLICITATION TITLE: UPS BATTERY REPLACEMENT LOCATION 64
The Los Angeles County Metropolitan Transportation Authority (LACMTA) has established a contracting opportunity to provide the following: There is a need to replace the UPS battery module assembly at Location 64 due to the age and condition of the existing batteries. This project is detailed in the Scope of Services, Exhibit A. The resultant contract, if awarded, will be federally funded and is subject to fiscal year funding.
You are hereby invited to submit to LACMTA a Bid to furnish all Services, including, but not limited to, all management, labor, equipment, delivery, removal, disposal, or materials and other related items required for the supply and installation of 216 VRLA batteries (144 Deka Unigy HR5500 and 72 Deka Unigy 31H5000 or approved equals) at Location 64, resulting from this Invitation for Bid (IFB) on a firm fixed unit rate basis.
Requested delivery: All work, including installation and acceptance, needs to be completed within 45 days of contract execution. Per Exhibit A, Contractor shall provide a 1-year manufacture warranty from date of receive and acceptance of product.
Bids in response to this solicitation shall be submitted electronically via email to bids@metro.net. Bids must be received no later than 10:00 a.m. on Thursday, September 3, 2026. Time of receipt is determined by the date/time stamp imprinted upon the email system. It is recommended that bidders send their email(s) allowing for sufficient time to ensure that the bidder can meet the bid due date. Additionally, it is recommended that bidder's email(s) are sent with a Delivery and Read receipt for their records. Lastly, bidders should send a verification email to the named Contract Administrator of the IFB after the email submission(s) of proposal to bids@metro.net. The verification email should indicate that a bid has been submitted by Vendor Name for IFB# on X number of emails.
BIDDERS MUST SUBMIT ALL FORMS LISTED IN PAGES 26-27. FAILURE TO SUBMIT ALL
FORMS/EXHIBITS MAY RESULT IN BID DEEMED NON-RESPONSIVE AND INELIGIBLE FOR AWARD.
LOI-02 DEFINITIONS
Refer to the Contract Documents, including, but not limited to, the Section titled GLOSSARY OF TERMS in the General Conditions for the meaning of various abbreviations, acronyms and terms used in this IFB but not defined herein.
LOI-03 AVAILABILITY OF SOLICITATION DOCUMENTS
The IFB documents are available for download through LACMTA's Vendor Portal (Open Solicitations).
Additional reference documents, if requested, are available through the Contract Administrator.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
LOI-04 COMMUNICATION WITH LACMTA
All communications in connection with this IFB shall be provided as follows:
Contract Administrator:
• By electronic mail at naranjov@metro.net
Diversity & Equal Opportunity: via email at DEODS@metro.net.
Request for information on lobbyist registration are to be directed to the Ethics Department at ethics@metro.net.
Pre-Qualification Department: (213) 922-4130 or via email at Pre-Qual@metro.net.
LOI-05 PRE-BID CONFERENCE
LACMTA will hold a Virtual Pre-Bid Conference. Bidders are invited to attend the Pre-Bid Conference.
Attendance is not mandatory to be considered for award of a contract; however, when a Pre-Bid Conference is held, attendance is an essential part of Good Faith Efforts.
Virtual Pre-Bid Conference
Time and Date: Wednesday, 8/5/2026 at 10:00 AM
Location: Microsoft Team Meeting
Link and Phone number: Join:
https://teams.microsoft.com/meet/216255248972 761?p=oZx4dSsZj4iNP6Q0XZ
Meeting ID: 216 255 248 972 761 Passcode: Po6FF3mq
Need help? | System reference
Dial in by phone +1 213-279-1001,,522682674# United States, Los Angeles Find a local number
Phone conference ID: 522 682 674#
LOI-06 WORKSITE VISIT
A worksite walk-through has been arranged at the time and location below. Transportation to the worksite will not be provided unless specified below under "Additional Instructions". Prior approval for this worksite walk-through is not required.
Worksite Visit
UPS Battery Replacement Location 64 IFB No. PS132603(2)
Time and Date: 10:00 a.m. on Thursday, August 6, 2026
Location:
RSVP for Location Details
Additional Instructions: Interested bidders must confirm their attendance to this work site visit by sending an e-mail to NaranjoV@metro.net no later than Wednesday August 5, 2026 at 4:00 PM . Location details will be shared with those that RSVP firms are limited to a maximum of two attendees.
LACMTA does not pay for parking or validate tickets.
LOI-07 BASIS OF AWARD
A. The award, if made, will be made to the lowest-priced responsive and responsible Bidder. LACMTA reserves its rights, including, but not limited to, those identified in the Instructions to Bidders, LACMTA RIGHTS, and to be the sole judge of the merits of the respective Bids received.
B. If Option pricing is requested, the evaluation for Contract Award will be based upon the Base Contract plus Option(s), in any possible combination of Options, as determined by LACMTA. Bidders MUST bid on the base and options to be considered for award. LACMTA will evaluate the option pricing at the time it considers Bids. LACMTA's inclusion of an option in an invitation for bid or any contract awarded shall not obligate LACMTA to exercise the option, or to preclude LACMTA from initiating a new solicitation for the services to which the option applies.
LOI-08 APPROVED EQUALS (GOODS)
Unless otherwise provided in the Specifications, reference to Goods or patented processes by brand, trade name, make, manufacturer, or catalog number shall be regarded only as a means of establishing a standard of quality. Such references shall not be construed as limiting competition. The Contractor may, at its option, use any Goods or process that is equivalent to that named subject to the prior written acceptance by LACMTA.
Bidders seeking LACMTA's authorization for substitution of Goods or processes are required to submit a written request for an "Or Equal" substitution together with data substantiating the bidder's representation that the non-specified item is of equal quality to the item specified. Bidders are required to submit the request and substantiating data to the contract administrator at NaranjoV@metro.net. Please refer to the critical dates section LOI-14 regarding due date. Authorization of a substitution is solely within the discretion of LACMTA.
LACMTA shall be the sole judge of the quality and suitability of proposed alternative Goods or processes subject to the right of LACMTA to accept or reject such alternative.
LOI-09 EXHIBITS
This solicitation incorporates all Exhibit documents, including, but not limited to, those identified as Exhibits (Solicitation) and Exhibits (Contract), with the same force and effect as if they were provided in this solicitation in full text.
LOI-10 CONTRACT DOCUMENTS
A sample copy of all Contract Documents is included as part of this solicitation.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
LOI-11 INDEMNITY
Any contract awarded pursuant to this IFB will contain the indemnity provisions included in the Section titled LIABILITY AND INDEMNIFICATION in the General Conditions, which will require the Bidder to indemnify LACMTA as provided therein.
LOI-12 LIQUIDATED DAMAGES (RESERVED)
LOI-13 SOLICITATION LINKS
This solicitation may reference the followingelectronic webpages/links. The following listing is provided for the convenience of the Bidders or Proposers and LACMTA does not warrant it to be an all-inclusive listing. Other links may be identified in other solicitation documents or Contract Documents.
• Vendor Portal (Open Solicitations)
• California's Online Marketplace
• Office of Civil Rights
• BLS North American Industry Classification System (NAICS)
• US Census North American Industry Classification System
• Metro Contractor Pre-Qualification Program
• LACMTA Administrative Code
• LACMTA Lobby Ordinance (Applicable Law)
• LACMTA Contractor's Code of Conduct
• Protest Instructions (protest procedures)
• Labor Compliance Manual
• Living Wage and Service Contractor Worker Retention Policy Manual
• Environmental Policy
• Federal Transit Administration (Drug and Alcohol)
UPS Battery Replacement Location 64 IFB No. PS132603(2)
LOI-14 CRITICAL DATES
The following dates are critical for this solicitation:
Bid Issue Date Monday, 7/27/2026
Pre-Bid Conference Wednesday, 8/5/2026 at 10:00 AM
Work Site-Visit Thursday, 8/6/2026 at 10:00 AM Please visit LOI-06 for more information.
QuestionsDue Date Friday, 8/14/2026 at 2:00 PM
Approved Equals Due Date Friday, 8/14/2026 at 2:00 PM
Response to Questions and Request for Approved Equals
Friday, 8/21/2026
Bid Due Date Thursday, 9/03/2026 at 10:00 AM
Bid Opening Thursday, 9/03/2026 at 12:00 PM
Microsoft Teams meeting Join:
https://teams.microsoft.com/meet/210363727285 742?p=QL8pnAfapqTij6o60G
Meeting ID: 210 363 727 285 742 Passcode: SF2Bq9p9
Need help? | System reference
Dial in by phone +1 213-279-1001,,22440869# United States, Los Angeles Find a local number
Phone conference ID: 224 408 69#
BIDDERS MUST SUBMIT ALL FORMS LISTED IN PAGES 26-27. FAILURE TO SUBMIT ALL
FORMS/EXHIBITS MAY RESULT IN BID BEING DEEMED NON-RESPONSIVE AND INELIGIBLE FOR
AWARD.
LOI-15 DBE PROGRAM (RESERVED)
UPS Battery Replacement Location 64 IFB No. PS132603(2)
LOI-16 SBE/DVBE PROGRAM (RESERVED)
LOI-17 SBE SET-ASIDE PROGRAM (RESERVED)
LOI-18 MSZ PROGRAM (RESERVED)
LOI-19 LSBE PREFERENCE (RESERVED)
LOI-20 LOI SIGNATURES
For this solicitation, the resulting Contract is set up to be conducted electronically, including the use of electronic signatures. If you wish to opt out of electronic transactions for the Contract, you must notify the Contract Administrator in writing.
Issued by:
LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY
Veralie Naranjo Assistant Contract Administrator
UPS Battery Replacement Location 64
II. BID INSTRUCTIONS
UPS Battery Replacement Location 64 IFB No. PS132603(2)
INSTRUCTIONS TO BIDDERS
IB-01 PRE-QUALIFICATION REQUIREMENTS
A. Pre-Qualification applies to primes, first tier subcontractors and direct suppliers to LACMTA. Pre- Qualification is required for all firms not exempted from the process if their bid or proposal will exceed $500,000 for non-Construction contracts. Pre-Qualification is required of all firms not exempted from the process regardless of amount for public works construction contracts. Failure to do so may cause your Bid to be rejected as non-responsive.
B. Contractor Pre-Qualification Applications must be emailed to Pre-Qual@metro.net, the LACMTA Pre- Qualification Office, no later than the Bid due date and time. DO NOT insert copies of pre-qualification documents in your Bid. All first-tier subcontractors must be pre-qualified prior to performing any Work.
Contractor is responsible for ensuring a timely submittal of all Contractor Pre-Qualification Applications.
C. For contact information, please refer to the Letter of Invitation (LOI). For detailed instructions, refer to the Contractor Pre-Qualification Application which can be downloaded from LACMTA's Pre-Qualification website, or provided by the Pre-Qualification Office.
IB-02 CONTRACTOR REGISTRATION LAW
To be considered for this contract, Bidders and their subcontractors must be registered with Department of Industrial Relations to be eligible to bid and work on public works projects in accordance with California Labor Code §1725.5.
Pursuant to California Labor Code §1725.5, no contractor or subcontractor may (1) be listed on a bid for a public works project unless registered with the Department of Industrial Relations, or (2) be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations.
A list of all registered firms may be found on the California Department of Industrial Relations (DIR) website so that awarding bodies and contractors will be able to comply with requirements to only use registered contractors and subcontractors.
LACMTA shall not accept any bid nor award any contract without proof of the contractor's and subcontractor's current registration.
IB-03 EXAMINATION OF IFB DOCUMENTS
A. All Bids shall be submitted in strict accordance with the IFB documents.
B. Copies of the solicitation and LACMTA responses to all written questions, requests for interpretation, and requests for clarification will be available as provided in this IFB. The Bidder is solely responsible for the examination of solicitation documents, reviewing all amendments, and comprehending all conditions that may impact the Bid and the performance of the Work should the Bidder be selected. Failure of the Bidder to examine and inform itself is at its sole risk.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
IB-04 INTERPRETATION OF IFB DOCUMENTS
A. Requests for interpretation or clarification of the solicitation documents shall be submitted in writing. All written requests shall be submitted to the Contract Administrator identified in the LOI. Written responses to requests for interpretation or clarification will be provided to all prospective Bidders.
B. To ensure that responses are provided to all prospective Bidders, inquiries shall be received at least ten
(10) working days prior to the submittal due date. Where such interpretation or clarification requires a change in the solicitation documents, LACMTA will issue an amendment.
C. LACMTA shall not be bound by, and the Bidders shall not rely on for any purpose, any oral interpretation or oral clarification of the solicitation documents.
IB-05 COMMUNICATION WITH LACMTA OTHER THAN THE CONTRACT ADMINISTRATOR
Any written correspondence with the following support groups should include a copy to the attention of the Contract Administrator identified in the LOI.
A. Pre-Qualification addressed in PRE-QUALIFICATION REQUIREMENTS, which should be directed to the Pre-Qualification Department as indicated in the LOI, and
B. Diversity and Economic Opportunity, which should be directed to the Diversity and Economic Opportunity Department (DEOD), as indicated in the LOI.
IB-06 AMENDMENTS
A. LACMTA reserves the right to revise the solicitation documents prior to the Bid opening. Such revisions, if any, will be made by amendment to this IFB.
B. Bidders shall acknowledge receipt of all amendments to the solicitation documents in the Bid Letter. Failure to acknowledge receipt of all amendments and to include all the requirements of the amendments in the Bid may render the Bid non-responsive.
C. Prior to submitting the Bid to LACMTA for consideration, each Bidder is responsible for checking the LACMTA website to ensure that it has received all applicable amendments.
IB-07 PREPARATION OF SUBMITTAL
A. Bidders shall complete and submit all required Bid forms and submittal requirements in accordance with the directions specified in this IFB and on the forms provided herein. All required explanatory narratives and the supplementary data are to be included with the Bid forms as indicated.
B. Bids shall contain concise written materials that enable the reviewer to make an assessment regarding Bidder's responsibility.
C. Bids shall specifically describe the Bidder's role and relationship to its proposed subcontractors and suppliers, and describe the work allocation and organizational controls interfaces with said proposed subcontractors and suppliers, where required.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
D. Pencil or erasable ink shall not be accepted. Initial all modifications made to the Bidder's entries and identify the Bidder's name on the top right of each page, or subcontractor's name when applicable. Liquid or dry correction materials shall not be used.
E. Failure to comply with the requirements outlined in these solicitation documents may result in a Bid being incomplete and rejected as non-responsive.
IB-08 MODIFIED AND ALTERNATIVE BIDS
A Bid shall be rejected if the Bid modifies any requirement of the solicitation documents or is determined to be a conditional or an alternative Bid.
IB-09 SIGNING OF BIDS
A. An Authorized Representative with the full legal authority to commit the Bidder shall execute the Bid Letter and all required Bid forms and other solicitation documents. An unsigned Bid Letter will be considered non-responsive, and the bid will not be considered for award.
B. If the Bidder is a joint venture or partnership, it shall submit with its Bid a duly notarized Venturer or Partner-executed Irrevocable Power of Attorney that designates the Bidder's Authorized Representative and a copy of the properly executed Joint Venture or Partnership Agreement. The Bidder's Authorized Representative shall be empowered to execute the Bid on behalf of the Bidder and to act for and bind the Bidder in all matters relating to the Bid. The Irrevocable Power of Attorney and the Joint Venture or Partnership Agreement shall specifically state that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of the Bidder that are assumed under any contract arising from the Bid. The Bidder's Authorized Representative shall execute the Bid on behalf of the joint venture or partnership in its legal name.
C. Bidders shall submit sufficient documentation to (1) establish the legal authority of the identified Authorized Representative(s) to act on behalf of the Bidder, and (2) define the scope of the Authorized Representative's authority.
IB-10 SUBMISSION AND OPENING OF SEALED BID
A. Bids shall be submitted via email at bids@metro.net Bids shall be submitted electronically via email to bids@metro.net. Please refer to LOI-14 regarding the due date. Bids received after that time will not be considered. Time of receipt is the date/time the email is sent. It is recommended that bidders send their email(s) allowing for sufficient time to ensure that the bidder can meet the bid due date. Additionally, it is recommended that bidder's email(s) are sent with a Delivery and Read receipt for their records. Lastly, bidders should send a verification email to the named Contract Administrator of the IFB after the email submission(s) of bid to bids@metro.net. The verification email should indicate that a bid has been submitted by Vendor Name for IFB# on X number of emails.
B. It is each Bidder's sole responsibility to ensure that its Bid is received as required. The Bid opening is a public process and all bidders may attend.
IB-11 BID EVALUATION PROCESS
A. The Bid evaluation period shall close upon LACMTA's completion of its review and evaluation of Bids, UPS Battery Replacement Location 64 IFB No. PS132603(2) including any Good Faith Efforts submittals. A recommendation for award will be sent to all bidders and bid results will be available on LACMTA's website.
B. During the Bid evaluation period, staff shall determine if Bids are responsive and Bidders are responsible.
Bids submitted in strict accordance with the solicitation documents will be deemed responsive.
Responsiveness is defined to mean the Bid must comply in all material respects with the IFB, as determined by LACMTA, including, but not limited to, filling out all forms and following all instructions in the Bid forms in order to meet the minimum qualifications of a Responsive Bidder. Responsibility is defined as the apparent ability of the Bidder to meet and successfully complete the requirements of the Contract. Responsibility determinationincludes, but is not limited to, consideration of a Bidder's trustworthiness, the quality of past performance, financial ability, and fitness and capacity to provide the proposed Services and Goods in a satisfactory manner. Bidders may be required by LACMTA to present further evidence that they have successfully performed and provided similar Services and Goods of comparable magnitude or provide other proof satisfactory to LACMTA that they are competent to successfully complete the Contract.
C. A debriefing is available to Bidders after award. Bidders must request the debriefing in writing within five
(5) days of receipt of the Notice of Intent to Award. Any request for a debriefing should be addressed to the Contract Administrator identified in the LOI.
IB-12 DISCREPANCIES IN BID ITEMS
A. The Bidder shall furnish a price for each individual Bid item, unless otherwise stated in the Schedule of Quantities and Prices. Failure to do so may render the Bid(s) incomplete and non-responsive and may cause its rejection. The Bid shall state the unit prices, the total amount of each Bid item, and the "Total Bid Price" as indicated on the Schedule of Quantities and Prices for which the Bidder proposes to supply the Services and completely perform the Contract. If the unit price and the extended amount expressed by the Bidder for any item are not in agreement, the unit price alone will be considered as representing the Bidder's intention. LACMTA will correct the extended unit price and the Total Bid Price.
B. Any unit price left blank in the Bid will be considered non-responsive.
C. Any total price left blank in the Bid will be considered non-responsive unless the blank item can be calculated from the information available (i.e., total price can be determined by multiplying the unit price by the estimated quantity).
IB-13 WITHDRAWAL OF BID
The Bidder may withdraw its Bid before the bid opening by means of a written request signed by the Bidder or its properly Authorized Representative. The written request must be clearly identified as a "withdrawal of Bid" (on the outside of the envelope and on the request) and delivered to the address identified in the LOI.
IB-14 BID MISTAKES
A Bidder, who seeks to rescind its Bid due to a mistake or error in preparation of its Bid, shall notify LACMTA in writing within five (5) business days of public bid opening.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
IB-15 LACMTA RIGHTS
LACMTA may investigate the qualifications and responsibility of any Bidder under consideration, inclusive of, but not limited to, the information provided in the Contractor Pre-Qualification Application, Bid, or any other information available to LACMTA. LACMTA may require confirmation of information furnished by the Bidder, and require additional evidence of qualifications and responsibility to perform the Services described in this
IFB.
LACMTA reserves the right to take any of the actions below:
A. Award on an item by item basis, aggregate of items or the total bid, whichever is in the best interest of
LACMTA;
B. Reject any or all of the Bids;
C. Reject any Bid that, in the opinion of LACMTA, is so unbalanced in comparison to other Bids received and/or to LACMTA's internal estimates that it does not accurately reflect the cost of the Services to be provided;
D. Cancel the entire IFB;
E. Issue subsequent IFB;
F. Amend the IFB before Bid closing;
G. Exercise its sole discretion to determine matters of responsiveness and request further or additional information from any or all Bidders;
H. Appoint evaluation committees to review Bids;
I. Seek the assistance of outside technical experts to review Bids;
J. Request clarification from any or all Bidders of any information contained in Bids;
K. Approve or disapprove the use of particular subcontractors and suppliers;
L. Exercise its discretion in reviewing Bids according to the requirements of the solicitation documents;
M. Disqualify the Bid(s) upon evidence of an organizational conflict of interest, false or misleading certifications or representations in its Bid, or collusion with intent to defraud or other illegal practices on the part of the Bidder(s);
N. Waive any informalities or irregularities in any Bid, to the extent permitted by law;
O. Require, as a condition to the award of any contract, security from Bidders for the full and faithful performance and completion of the contract in a form determined by LACMTA in its sole discretion, including without limitation payment bonds, performance bonds, letters of credit and guarantees from shareholders of the Bidder or otherwise;
P. Examine any books, records, accounts and other documents of any Bidder as it relates to the Bid; and Q. Reject any conditional or alternate Bid.
IB-16 PUBLIC RECORDS ACT
A. Responses to this IFB are subject to the provisions of the California Public Records Act (Government Code §7920.000 et. seq.).
B. Any documents, including financial records, provided by the Bidder/Contractor to LACMTA marked "Trade Secret," "Confidential," or "Proprietary" provided by the Bidder/Contractor to LACMTA shall be handled in accordance with the Section titled PUBLIC RECORDS ACT in the Regulatory Requirements.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
IB-17 DISQUALIFICATION OF BIDDERS
A. Organizational conflict of interest restrictions apply to this IFB Process. Organizational conflicts of interest are fact dependent and may arise in various situations or circumstances, including but not limited to, as referenced in the SPECIAL PROVISION entitled
ORGANIZATIONAL CONFLICTS OF INTEREST.
B. As noted above, organizational conflicts of interest are fact dependent, and the party with the greatest access to the relevant facts as to whether a Proposer has an organizational conflict of interest will always be the Proposer itself. LACMTA is the ultimate arbiter of whether a Proposer has an organizational conflict of interest. LACMTA has determined that it is not appropriate for LACMTA to:
1. Evaluate a particular Bidder's circumstances before receiving all the facts that would be included in a bid;
2. Give legal advice; or
3. Make a business decision for a Bidder concerning participation in a procurement.
C. Bidders are prohibited from:
1. Directly or indirectly obtaining any advice or engaging in discussions relating to the Project or the IFB Process from or with; or
2. Including on its Bidder team, any person or entity with an organizational conflict of interest.
Bidders are responsible for identifying any potential or actual organizational conflict of interests before obtaining any advice or engaging in any discussions relating to the Project or the IFB Process and when determining who to include within the Bidder team.
D. By submitting a Proposal, each Bidder agrees that if any perceived, potential, or actual organizational conflict of interest is discovered after the Bidder has submitted its Bid, the Bidder will make an immediate and full written disclosure to LACMTA that includes:
1. The names and contact information of the persons or entities to which the perceived, potential, or actual organizational conflict of interest relates;
2. A description of the perceived, potential, or actual organizational conflict of interest; and
3. A description of the action that the Bidder has taken, or bidders to take, to avoid or mitigate such perceived, potential, or actual organizational conflict of interest.
E. The process for responding to any LACMTA organizational conflict of interest finding shall be governed by LACMTA's organizational conflict of interest policy and Administrative Code.
IB-18 FILING OF PROTESTS
A. All protests must be filed and resolved in accordance with LACMTA's Protest Procedures.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
B. Appeals from the denial of Pre-Qualification must be filed and resolved in accordance with LACMTA's procedures for denial of Pre-Qualification (available for download at LACMTA's Pre-Qualification website).
IB-19 BUY BACK (RESERVED)
IB-20 BONDS (RESERVED)
IB-21 BIDDERS LIST FORM
A. In accordance with 49 C.F.R. 26.11(c), LACMTA is required to maintain a Bidders List, consisting of all firms bidding/proposing on prime contracts and bidding/proposing or quoting subcontracts, who seek an award or participation on LACMTA contracts funded in whole or in part with federal funds. Each Bidders List is a compilation of bidders, proposers, quoters, subcontractors, manufacturers, and suppliers of materials who have submitted bids/proposals during the advertising period of a specific contract.
B. If the LOI identifies this IFB as federally funded, all businesses are required to complete and submit a Bidders List Form (Exhibit 4) when submitting a bid, proposal, or quote directly to LACMTA.
C. All businesses that submit a bid, proposal, or quote directly to LACMTA must also ensure that all of its quoting subcontractors, suppliers, manufacturers and suppliers that the bidder/proposer included in its response to LACMTA, are required to complete and submit a Bidders List Form (Exhibit 4).
D. Bidders List Forms (Exhibit 4) are due with the bid/proposal. Failure to submit the Bidders List Form(s) may deem the bid/proposal non-responsive.
E. LACMTA will use the Bidders List to identify the universe of DBE and non-DBE contractors and subcontractors who seek to work on LACMTA contracts for use in establishing LACMTA's overall DBE goals.
END OF INSTRUCTIONS TO BIDDERS
UPS Battery Replacement Location 64 IFB No. PS132603(2)
DEOD INSTRUCTIONS
DI-01 - INSTRUCTIONS TO BIDDERS/PROPOSERS
SECTION 100 - DBE PROGRAM
100 FEDERAL OBLIGATION: This contract is subject to the requirements of Title 49, Code of Federal Regulations, Part 26, Participation by Disadvantaged Business Enterprises in Department of Transportation Financial Assistance Programs.
101 LACMTA POLICY STATEMENT: It is LACMTA's policy to provide equal opportunity for Disadvantaged Business Enterprises (DBE), as defined in 49 C.F.R. Part 26, to receive and participate on DOT-assisted contracts. It is also our policy to:
A. Ensure nondiscrimination in the award and administration of DOT-assisted contracts;
B. Create a level playing field on which DBEs can compete fairly for DOT-assisted contracts;
C. Ensure that LACMTA's DBE program operates in a nondiscriminatory manner and without regard to race or sex, while maximizing efficiency of service;
D. Ensure that only firms that meet 49 C.F.R. Part 26 eligibility standards are permitted to participate as DBEs;
E. Help remove barriers to the participation of DBEs in DOT-assisted contracts; and
F. Assist the development of firms that can compete successfully in the market place outside the DBE program.
102 INTERPRETATION: Any conflict, error, omission or ambiguity which may arise between these instructions and the federal regulations or the above mentioned DBE Program obligation, shall be resolved first in favor of the federal regulations and second the DBE Program. Failure of a Bidder/Proposer, its subcontractors, consultants, suppliers or other entities to carry out these requirements may be grounds for LACMTA to implement administrative penalties or other remedies imposed by LACMTA.
103 SUSPENSION OR DEBARMENT: Suspension or debarment proceedings may be initiated by LACMTA against any firm that:
A. Attempts to participate in a DOT-assisted program as a DBE and does not meet the eligibility criteria stated in the certification standards for DBE programs; or on the basis of false, fraudulent or deceitful statements;
or under circumstances indicating a serious lack of business integrity or honesty.
B. Attempts to use false, fraudulent or deceitful statements or representations in order to meet its DBE administrative requirements, or uses another firm that does not meet the DBE eligibility criteria stated in the certification standards.
In accordance with 49 C.F.R. Part 26.107 DOT may take action itself through its Fraud and Civil Remedies Program or refer the matter to the Department of Justice for prosecution under appropriate criminal statutes.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
LACMTA may refer any false, fraudulent, or dishonest conduct to the attention of the Department of Transportation in connection with the DBE program, so that DOT can take the steps (e.g., referral to the Department of Justice for criminal prosecution, and/or referral to the DOT Inspector General, action under suspension and debarment or Program Fraud and Civil Penalties rules).
104 LACMTA OVERALL DBE GOAL: LACMTA has established a triennial overall DBE goal for DBE participation. LACMTA will use both DBE-Conscious and DBE-Neutral measures to achieve its overall goal.
SECTION 200 -SUBCONTRACTOR PARTICIPATION
200 DBE CONTRACT GOAL: DBE goals are established based on the analysis of the scope of work, and the availability of DBE firms that are ready, willing, and able to perform. If established, the contract goal is listed in the LOI.
If a contract goal is not established, Bidders/Proposers are encouraged to utilize DBE firms when opportunities are available during the performance of the contract.
201 RESPONSIVENESS TO CONTRACT GOAL: If a DBE contract goal is established for this contract, obtaining the contract goal is a matter of responsiveness.
202 DBE ADMINISTRATIVE REQUIREMENTS: DBE administrative requirements for this contract are provided in the Contract Compliance Manual (Federal), incorporated as part of the conformed contract.
203 CONTRACTOR ASSURANCE: The Bidders/Proposers shall make the following assurance and shall, after contract award, include this assurance verbatim in each subcontract and/or purchase agreement awarded to subcontractors, suppliers, truckers, and brokers:
Contractors, subrecipients, nor subcontractors shall discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 C.F.R. Part 26 in the award and administration of federally-assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the recipient deems appropriate, which may include, but is not limited to:
1. Withholding monthly progress payments;
2. Assessing sanctions;
3. Liquidated damages; and/or
4. Disqualifying the contractor from future bidding/proposing as non-responsible.
204DEOD FORMS: The Bidder/Proposer shall provide, as part of its Bid/Proposal, a complete listing of subcontractors that will perform any portion of the work/services, together with a description of their statement of work/scope of services and dollar value of their participation.
Bidder/Proposer shall submit with its Bid/Proposal completed DEOD Forms 1, 3 and 5 listed below and found in Exhibit 1 (even if DBE goals were not established).
Form No. Form Name
To Be Completed By Applicability Required
Bidder/Proposer All Subcontrac
IFB RFP
UPS Battery Replacement Location 64 IFB No. PS132603(2) tors / Suppliers
Subcontractor Listing Form (For IFB Only)
X X X
Form 1 NOT USED
Attachment A to Form 1
NOT USED
Form 1B Proposed Subcontractors & Suppliers (For non- Construction IFBs and RFPs Only)
X X X X
Attachment B to Form 1B
Proposed Lower Tier Subcontractors and Suppliers
X X X X X
Form 2 NOT USED
Form 3 Business Data Sheet X X X X X
Form 4 NOT USED
Form 5 Bidder's List Form X X X X
Form 6 NOT USED
• All Bidders are required to complete and submit the Subcontractor Listing Form for IFB solicitations only.
• All Bidders/Proposers are required to complete DEOD Forms 1B, 3 and 5.
• All Bidders/Proposers are required to complete and submit Attachment B to Form 1B
• All Subcontractors/Suppliers are required to complete and submit Form 3.
• All Bidders and Proposers who submit a bid or proposal as a prime are required to complete and submit Form 5
Metro will achieve its overall DBE goal using DBE-conscious and DBE-neutral measures in accordance with the US Department of Transportation DBE Program Rule 49 Code of Federal Regulations, Part 26.
205INFORMATION MUST BE CURRENT, ACCURATE, AND COMPLETE: Bidders/Proposers shall ensure that all information provided in their response to the requirements is current, accurate, and complete.
206 NOT USED
207NOT USED
SECTION 300 -NOT USED
300 NOT USED
301NOT USED
UPS Battery Replacement Location 64 IFB No. PS132603(2)
SECTION 400 -NOT USED
400 NOT USED
401 NOT USED
402 NOT USED
403 NOT USED
404NOT USED
SECTION 500 - DBE CERTIFICATION
500 NOT USED
501 DBE CERTIFICATION ELIGIBILITY:
A. Each applicant for DBE certification must demonstrate that he/she meets the criteria of social and economic disadvantage (SED) affirmatively based on their own experiences and circumstances within American society, and without regard to race or sex in accordance with 49 C.F.R. § 26.67.
502 NOT USED
SECTION 600- CONTRACT COMPLIANCE
600 COMPLIANCE MONITORING: LACMTA will monitor the Contractor's compliance with the DBE Program and administrative requirements for this contract as provided in the Diversity & Economic Opportunity Department Contract Compliance Manual (_________) incorporated into the executed contract.
END OF DEOD INSTRUCTIONS
UPS Battery Replacement Location 64
III. BID REQUIREMENTS/FORMS
UPS Battery Replacement Location 64 IFB No. PS132603(2)
SUBMITTAL REQUIREMENTS
1.1 GENERAL FORMAT
Bids submitted via email shall be sent to bids@metro.net.This email address is exclusively reserved for the submission of bids. Any other communications must be submitted directly to the Contract Administrator, Buyer, DEOD, Ethics, Risk Management, and or Pre-Qualification Office accordingly. Submittals must adhere to the following requirements:
A. Be prepared based on the documents provided in this IFB and, when applicable, on 8.5" x 11" page size with 1" left, top, bottom and right margins. Typing shall be single spaced with a minimum font size of ten.
Use of 11" x 17" (fold out sheets) for large tables, charts or diagrams is permissible, but should be limited.
Elaborate format is not necessary.
Do not provide promotional, marketing or advertising information;
B. When requested by the IFB, contain concise written materials (and drawings if applicable) that enable the reviewer to clearly understand the Bidder's capabilities;
C. When requested by the IFB, specifically describe the Bidder's role and relationship to its proposed subcontractors and suppliers, and describe the work allocation and organizational controls interfaces with said proposed subcontractors and suppliers; and
D. Contractor Pre-Qualification Application documents shall not be included with the Bid documents.
Contractor Pre-Qualification Application documents shall be delivered directly to the Pre-Qualification Office no later than the Bid due date and time.
E. Subject line must contain the LACMTA Contract Administrator First and Last name, and the IFB Number. If more than one email is required for bid submittal, indicate in the subject line, submittal 1 of 5, 2 of 5, etc.
F. Bids shall be submitted no later than the bid due date and time.
G. Individual email submittals should be no larger than 20MB.
H. It is recommended that bidders send their email(s) allowing for sufficient time to ensure that the bidder can meet the bid due date. Additionally, it is recommended that bidder's email(s) are sent with a Delivery and Read receipt for their records. Lastly, bidders should send a verification email to the named Contract Administrator of the IFB after the email submission of bid to bids@metro.net. The verification email should indicate that a bid has been submitted for IFB# on X number of emails.
1.2 BID CONTENT
The Bid shall have the following components and shall be presented in the format exactly as shown here:
VOLUME I - Bid Forms
1. EXHIBIT 5 - BID LETTER This letter shall be completed and executed by the Bidder's Authorized Representative in the form provided in Exhibit 5. Any changes, alterations, interlineations, comments or other modifications to the Bid Letter may result in the Bid being rejected as nonresponsive.
2. EXHIBIT 6 - LIST OF CURRENT CONTRACTS - BACKLOG
3. EXHIBIT 7 - LIST OF COMPTETED CONTRACTS - LAST 5 YEARS
UPS Battery Replacement Location 64 IFB No. PS132603(2)
VOLUME II - Certification Forms
1. EXHIBIT 8 - ETHICS DECLERATION Provide for Prime and any Subcontractors
2. EXHIBIT 9 - GENERAL CERTIFICATIONS Provide for Prime and any Subcontractors
3. EXHIBIT 10 - CERTIFICATE OF COMPLIANCE WITH 49 CRF PART 665, PREVENTION OF
ALCOHOL MISUSE AND PROHIBITED DRUG USE TRANSIT OPERATIONS Provide for Prime and Subcontractors
4. EXHIBIT 11 - CERTIFICATE OF COMPLIANCE WITH FEDERAL LOBBYING REQUIREMENTS (49
CFR PART 20) Provide for Prime and Subcontractors
5. EXHIBIT 12 - CERTIFICATION OF PROSPECTIVE CONTRACTOR AND LOWER TIER
PARTICIPANT REGARDING DEBARTNENT, SUSPENSIOINELIGIBILITY AND VOLUNTARY
EXCLUSION
VOLUME III - Price Proposal
The Price Proposal shall identify the Firm Fixed Unit Rate offer for the performance of the Work identified herein, along with a proposed complete Schedule of Quantities and Prices with Instructions, Exhibit 2. Bids shall be in accordance with the format prescribed by LACMTA and as attached hereto.
The Bidder's Price Proposal must include a price covering the entire Scope of Services, including information for the Bidder and members of its team (e.g., joint venturers or partners, subcontractors, etc.). The Bidder's price shall include all applicable direct labor, all applicable labor surcharges such as taxes, insurance and fringe benefits, as well as indirect costs, overhead, general and administrative expense, other direct costs, and profit.
VOLUME IV - DEOD Forms and Required Documents
This solicitation requires the following completed DEOD forms, Exhibit 1, as instructed in the Instructions to Bidders/Proposers Section:
• Exhibit A Pre-Assessment Form
• Exhibit B Post-Assessment Form
• Form 1- SBE Proposed Subcontractors and Suppliers
• Form 2 - SBE Affidavit
• Form 3 - Business Data Sheet
• Form 4 -SBE Affirmation (if applicable)
• Form 5- SBE BIDDERS LIST FORM (If applicable)
1.3 BID FORMS
This solicitation requires the following completed documents in the Bid:
• Price Form(s) titled Schedule of Quantities and Prices (Bid Pricing Sheet) - Please see Exhibit 2.
UPS Battery Replacement Location 64 IFB No. PS132603(2)
• Bidders List Form - Please see Exhibit 4.
• Bid Letter - Please see Exhibit 5.
• List of Current Contracts (Backlog) - Please see Exhibit 6.
• List of Completed Contracts - Last Five Years - Please see Exhibit 7.
1.4 CERTIFICATION FORMS
This solicitation requires the following completed certifications in the Bid:
• Ethics Declaration (Bidder must submit its completed Ethics Declaration, as well as a completed Ethics Declaration from each of Bidder's prospective subcontractors, in the Bid) - Please see Exhibit 8.
• General Certifications - Please see Exhibit 9.
• Certificate of Compliance with 49 C.F.R. Part 655, Prevention of Alcohol Misuse and Prohibited
Drug Use in Transit Operations - Please see Exhibit 10.
• Buy America Certificate (Steel, Iron, or Manufactured Products)
• Certification of Compliance with Federal Lobbying Requirements (49 C.F.R. Part 20) - Please see
Exhibit 11.
• Certification of Prospective Contractor and Lower Tier Participant Regarding Debarment, Suspension,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .