Project_Manual.pdf

PDF 4 MB Posted

Attached to
Daytona Beach Ocean Center Electrical Switchgear Replacement
Solicitation number
26-P-04LL
Issued by
Volusia County, Florida

About this file

This document is a comprehensive project manual for the Volusia County Ocean Center Electrical Switchgear Replacement project, prepared by Matern Professional Engineering, Inc., serving as the 100% construction documents package for the replacement of the facility's main electrical switchboard and bus duct systems. The project, located at 101 North Atlantic Avenue, Daytona Beach, Florida 32118, involves the removal and installation of a new 480Y/277V, 3-phase, 4-wire service-entrance-rated switchboard (Square D QED-2 model, 2000A capacity) with associated copper busway distribution, grounding system upgrades, feeder replacements, comprehensive testing protocols, and complete operations and maintenance documentation. Contractors must submit detailed shop drawings within 30 days of contract award, with substantial completion required within 30 days of Notice to Proceed and final completion within 35 days total. The contract requires attendance at a mandatory pre-solicitation conference on March 10, 2026, submission of written questions by March 26, 2026, and electronic proposal submission by April 9, 2026, at 3:00 PM EST. The specifications mandate adherence to the Florida Building Code (8th Edition 2023), NFPA 70-2020 National Electrical Code, NFPA 72 Fire Alarm Code, IEEE 1584-2018 arc flash analysis standards, and all other applicable federal, state, and local electrical codes and regulations.

The contract price is listed as to be determined (TBD) with liquidated damages assessed at $1,000 per day for failure to achieve the 35-day completion deadline. Qualified contractors must hold an active Florida-licensed building or general contractor license, engage a Florida Certified Electrical Contractor (EC) as subcontractor, employ a superintendent with an active Florida Journeyman's Electrical License and minimum four years' experience, demonstrate at least five years of established business history, and provide a minimum of three references for similar switchgear replacement projects completed within the past three years. Required insurance includes Workers' Compensation, Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Auto Liability ($1,000,000 combined single limit), Excess Liability ($2,000,000), and Installation Floater coverage, with the County named as additional insured and all policies issued by Florida-licensed insurers with A.M. Best ratings of A- or better. A performance and payment bond equal to 100 percent of the contract value must be provided prior to work commencement. Evaluation criteria are weighted on a 100-point scale: Technical Qualifications and Experience (35 percent), Project Approach and Schedule (35 percent), Price and Total Cost (20 percent), and Safety, Quality Control and Resources (10 percent). The project imposes specific operational conditions requiring four weeks' advance notice for building entrance or exit closures, one week's notice for project extensions, site security with six-foot chain link fencing with black liners, portable restrooms, and potential generator support depending on dark days required. No set-aside designations for disadvantaged or minority-owned businesses are indicated, and no incumbent vendors or current contractors are identified in the available documentation.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VOLUSIA COUNTY

OCEAN CENTER

ELECTRICAL SWITCHGEAR REPLACEMENT

PROJECT MANUAL

100% CONSTRUCTION DOCUMENTS

Matern Professional Engineering, Inc.

130 Candace Drive Maitland, Florida 32751

Mechanical • Electrical • Plumbing • Fire Protection Technology • Energy • Commissioning Engineers

CONSULTANTS

ELECTRICAL

Matern Professional Engineering, Inc.

130 Candace Drive Maitland, Florida 32751-3331

MAY 13, 2025 Volume No. 1 of 1

CONSULTANTS

ELECTRICAL /

ENGINEER

Bradley J. Pascarella, P.E.

FL LICENSE #74529

(Div 26)

Division 00

PROCUREMENT AND CONTRACTING

REQUIREMENTS GROUP

THIS PAGE INTENTIONALLY LEFT BLANK

OCEAN CENTER – ELECTRICAL SWITCHGEAR REPLACEMENT

TABLE OF CONTENTS 00 01 10 - 1

00 01 10 - TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 10 TABLE OF CONTENTS

00 04 00 STATEMENT OF COMPLIANCE

00 05 00 NON-ASBESTOS CERTIFICATION

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 SUMMARY

01 25 00 SUBSTITUTION PROCEDURES

01 26 00 CONTRACT MODIFICATION PROCEDURES

01 29 00 PAYMENT PROCEDURES

01 31 00 PROJECT MANAGEMENT AND COORDINATION

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

01 32 16 CONSTRUCTION PROGRESS SCHEDULE

01 32 33 PHOTOGRAPHIC DOCUMENTATION

01 33 00 SUBMITTAL PROCEDURES

01 40 00 QUALITY REQUIREMENTS

01 42 00 REFERENCES

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 50 10 PROJECT CONSTRUCTION SIGN

01 60 00 PRODUCT REQUIREMENTS

01 60 20 FLORIDA PRODUCT APPROVAL FORM

01 73 00 EXECUTION REQUIREMENTS

01 73 10 CUTTING AND PATCHING

01 74 13 FINAL CLEANING

01 77 00 CLOSEOUT PROCEDURES

01 78 30 WARRANTIES

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 03 – CONCRETE (NOT USED)

DIVIISON 04 – MASONRY (NOT USED)

DIVISION 05 – METALS (NOT USED)

DIVISION 06 - WOOD, PLASTICS AND COMPOSITES (NOT USED)

DIVISION 07 - THERMAL & MOISTURE PROTECTION (NOT USED)

DIVISION 08 - OPENINGS (NOT USED)

DIVISION 09 – FINISHES (NOT USED)

DIVISION 10 – SPECIALTIES (NOT USED)

DIVISION 11 THRU 20 (NOT USED)

TABLE OF CONTENTS 00 01 10 - 2

DIVISION 21 - (NOT USED)

DIVISION 22 - (NOT USED)

DIVISION 23 - (NOT USED)

DIVISION 26

26 01 00 Operation and Maintenance Manuals 26 01 03 Minor Electrical Demolition for Remodeling 26 01 05 Investigation of Existing Electrical Systems 26 05 00 Common Work Results for Electrical 26 05 06 Demonstration of Completed Electrical Systems 26 05 07 Submittals 26 05 08 Substitutions 26 05 09 Reference Standards and Regulatory Requirements 26 05 10 Electrical Symbols and Abbreviations 26 05 19 Building Wire and Cable 26 05 26 Grounding and Bonding 26 05 35 Pull and Junction Boxes 26 05 53 Identification for Electrical Systems 26 05 73 Power System Study With Arc Flash Analysis 26 24 13 Distribution Switchboards 26 27 13 Electrical Metering 26 43 00 Surge Protective Devices

DIVISIONS 27 THRU 33 (NOT USED)

END

STATEMENT OF COMPLIANCE 00 04 00 - 1

SECTION 00 04 00 - STATEMENT OF COMPLIANCE

To the best of my knowledge the Plans and Specifications comply with the applicable minimum building codes and the applicable fire-safety standards as determined by the local authority in accordance with FBC Section 107 and 633 Florida Statutes.

END OF SECTION 00 04 00

STATEMENT OF COMPLIANCE 00 04 00 - 2

NON-ASBESTOS CERTIFICATION 00 05 00 - 1

SECTION 00 05 00 - NON-ASBESTOS CERTIFICATION

To the best of the Engineer’s knowledge these Contract Documents do not contain any asbestos containing materials intended for use in construction.

END OF SECTION 00 05 00

NON-ASBESTOS CERTIFICATION 00 05 00 - 2

Division 01

GENERAL REQUIREMENTS

THIS PAGE IS INTENTIONALLY LEFT BLANK

SUMMARY 01 10 00 - 1

SECTION 01 10 00 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work by Owner.

5. Work under separate contracts.

6. Future work.

7. Purchase contracts.

8. Owner-furnished products.

9. Contractor-furnished, Owner-installed products.

10. Access to site.

11. Work restrictions.

12. Specification and drawing conventions.

13. Miscellaneous provisions.

1.3 PROJECT INFORMATION

A. The existing Ocean Center Convention Center, located at 101 N Atlantic Ave, Daytona Beach, FL 32118, contains a main switchboard on the first level that is outdated and requires replacement. The current gear is a Main-Tie-Main type, double-ended switchboard.

Additionally, the existing bus duct running from the transformer vault to the facility’s main electrical distribution switchgear is also scheduled for replacement.

B. Mechanical, Plumbing, Fire Protection, and Architectural scope is excluded from this proposal.

1.5 WORK BY OWNER

A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this Contract with any other work performed by Owner.

1.6 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

C. Use of Site: Limit use of Project site to areas within the Contract limits indicated by the scope of work shown on the documents. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to locations shown on the documents.

2. Driveways, Walkways and Entrances: Keep driveways, parking lots, loading areas, and

SUMMARY 01 10 00 - 2

entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

c. Maintain fence/gate separation between construction operations and occupied spaces at all times, with additional monitoring before/after deliveries.

D. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.

E. Contractor shall request master key and security code from maintenance.

1.7 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and adjacent building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day- to-day operations. Owner shall be provided a safe work environment. Maintain existing exits unless otherwise indicated.

B. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Owner shall be provided a safe work environment. Maintain existing exits unless otherwise indicated.

C. Owner Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1.8 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1.9 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications.

The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

SUMMARY 01 10 00 - 3

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 10 00

SUMMARY 01 10 00 - 4

SUBSTITUTION PROCEDURES 01 25 00 - 1

SECTION 01 25 00 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

1.4 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and Title and Drawing Numbers and Titles.

1. Substitution Request Form: Use “Contractor’s Request for Substitution” form (3 pages) provided at end of the Section (“Contractor’s Request for Substitution” form completed and signed by CM/General Contractor only.)

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of Engineer’s and Owner’s.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research/evaluation reports evidencing compliance with building code in effect for Project, from a model code organization acceptable to authorities having

SUBSTITUTION PROCEDURES 01 25 00 - 2

jurisdiction.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Engineer's Action: If necessary, Engineer will request additional information or documentation for evaluation within 7 days of receipt of a request for substitution.

Engineer will notify Contractor through Construction Manager of acceptance or rejection of proposed substitution within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Engineer’s Supplemental Instructions for minor changes in the Work.

b. Use product specified if Engineer cannot make a decision on use of a proposed substitution within time allocated.

4. Owner/Volusia County Action: Volusia County shall review “Contractor’s Request for Substitution” and supporting documentation received from Volusia County Project Manager. Volusia County has the right to: (1) approve the substitution request if the Engineer has approved the request or (2) disapprove the request agreeing with the Engineer’s disapproval or (3) not approve the substitution request, even if the Engineer has approved the request.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

1.6 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but no later than 45 days after the Notice to Proceed. Request received after that time may be considered or rejected at discretion of Engineer, subject to final approval/rejection by Owner.

B. Conditions: Engineer and Owner will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer

SUBSTITUTION PROCEDURES 01 25 00 - 3

including Owner, when applicable, will return requests without action, except to record noncompliance with these requirements:

1. Requested substitution is consistent with the Contract Documents and will produce indicated results.

2. Requested substitution provides sustainable design characteristics that specified product provided for achieving LEED, Green Globes or the Florida Green Building Coalition prerequisites and credits.

3. Substitution request is fully documented and properly submitted.

4. Requested substitution will not adversely affect Contractor's construction schedule.

5. Requested substitution has received necessary approvals of authorities having jurisdiction.

6. Requested substitution is compatible with other portions of the Work.

7. Requested substitution has been coordinated with other portions of the Work.

8. Requested substitution provides specified warranty.

9. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

C. Substitutions for Convenience: Not allowed.

END OF SECTION 01 25 00

SUBSTITUTION PROCEDURES 01 25 00 - 4

Exhibit A

CONTRACTOR’S REQUEST FOR SUBSTITUTION FORM

The undersigned hereby submits for consideration the following request for substitution in lieu of the specified item noted:

Section/Page Paragraph/Detail Specified Item/Model No.

Proposed Substitution:

It is the Contractor’s responsibility to provide all information necessary to determine the proposed substitution is equal or better than the specified item. Complete product description, drawings, photographs, performance and test data, samples and other information necessary for evaluation of requested substitution is to be attached and marked for comparison purposes. Fill in ALL BLANKS below.

1. Identify specific reason why this Substitution Request is being made.

2. Identify the recycled materials or components, or the features which support its status as “Environmentally Friendly”:

3. Will approval of the requested substitution affect dimensions, locations, or configurations shown on the drawings in any way? Yes No . If “Yes”, explain:

4. Will changes be required to the building or other construction in order to properly install or accommodate the requested substitution? Yes No__. If “Yes”, explain:

5. Will the Contractor pay for any changes to the building design, including re-design, engineering and detailing caused by acceptance of the substitution request? Yes No__. If “No”, explain:__

SUBSTITUTION PROCEDURES 01 25 00 - 5

6. Does the requested substitution meet all applicable Codes, Ordinances, and regulations for this specific application? Yes__ No__. If “No”, explain:

7. Does the requested substitution meet the same applicable standards (ASTM, ANSI, UL, FS, etc.)?

Yes__ No__. If “No”, explain:

8. Will approval of the requested substitution affect the work of other trades? Yes No__. If “Yes”, explain:

9. Will the requested substitution affect the construction progress schedule? Yes No__. If “Yes”, explain:

10. Has the requested substitution been used locally in similar applications? Yes (identify) No__.

(explain):

11. Does the manufacturer’s warranty on the requested substitution differ from that specified?

Yes No__. If “Yes”, explain:

12. Identify monetary credit and reduction of contract time the Owner will realize if this Substitution Request is accepted._

The Engineer and Owner will not be required to prove any product is not equal or suitable for the Project.

SUBSTITUTION PROCEDURES 01 25 00 - 6

CONTRACTOR’S CERTIFICATION OF EQUAL PERFORMANCE AND ASSUMPTION OF LIABILITY FOR

EQUAL PERFORMANCE

The undersigned Contractor states that the performance, function, quality and durability are equivalent or superior to the specified item. If Contractor is a corporation, the legal name of the corporation shall be set forth below, together with signature(s) of the officer or officers authorized to sign contracts on behalf of the corporation and corporate seal; if Contractor is a partnership, the true name of the firm and the name(s) of the general partner(s) shall be set forth below with the signature(s) of the partner or partners authorized to sign contracts on behalf of the partnership.; and if the Contractor is an individual, his signature shall be placed below. Failure to provide legally binding signature(s) will result in non-consideration of Substitution Request.

Submitted By: (Corporate Seal) Attest (if Corporation)

Signature, Date

Name (Print)

Title

Firm (Print)

Street Address

City, State, Zip Witnesses:

(if partnership or individual)

ENGINEER’S ACTION

Approved By: Date:

(Signature Required)

(Print Firm Name) Not Approved: By: Date:

(Signature Required)

(Print Firm Name)

VOLUSIA COUNTY/DESIGN ACTION

Approved: By:

(Signature Required) – Volusia County/Design Not Approved: By:

(Signature Required) – Volusia County/Design

Date:

Date:

Date:

Date:

CONTRACT MODIFICATION PROCEDURES 01 26 00 - 1

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

B. Related Sections include:

1. Division 01, Section 01 25 00 "SUBSTITUTION PROCEDURES" for administrative procedures for handling requests for substitutions made after Contract award.

1.3 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Engineer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time.

If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by Engineer are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request, 20 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

d. Include costs of labor and supervision directly attributable to the change.

B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to Engineer.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule in Primavera P6 format that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

CONTRACT MODIFICATION PROCEDURES 01 26 00 - 2

6. Comply with requirements in Section 01 25 00 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Volusia County approved Proposal Requests are incorporated into Contract Documents through Bulletins.

8. Allowances are Not-To-Exceed and are incorporated through Volusia County -approved Change

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for signatures of Owner and Contractor on Volusia County Change Order form with supporting attachments.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Engineer may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work.

It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1 Within fourteen (14) days of the change condition being defined, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

2 Construction Change Directives shall be closed out in a timely manner thru the Change Order process.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 26 00

PAYMENT PROCEDURES 01 29 00 - 1

SECTION 01 29 00 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Sections include the following:

1. Division 01, Section 01 26 00, "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

2. Division 01, Section 01 32 00 "Construction Progress Documentation" for administrative requirements governing preparation and submittal of Contractor's Construction Schedule and Submittals Schedule.

1.3 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.

1.4 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with Continuation Sheets.

b. Submittals Schedule.

c. Contractor's Construction Schedule.

2. Submit the Schedule of Values to Engineer through the Construction Manager at earliest possible date but no later than fourteen (14) days before the date scheduled for submittal of initial Applications for Payment.

3. Subschedules: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values correlated with each phase of payment.

4. Subschedules for Phased Work: Where the Work is separated into phases requiring separately phased payments; provide sub schedules showing values coordinated with each phase of payment.

5. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work; provide sub schedules showing values coordinated with each element.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name, Volusia County Project Number and location.

PAYMENT PROCEDURES 01 29 00 - 2

b. Name of Engineer.

c. Engineer's Project number.

d. Contractor's name and address.

e. Date of submittal.

2. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed:

a. Related Specification Section or Division.

b. Description of the Work.

c. Name of subcontractor.

d. Name of manufacturer or fabricator.

e. Name of supplier.

f. Change Orders (numbers) that affect value.

g. Dollar value: Percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.

1) Labor.

2) Materials.

3) Equipment.

4) Buyout Savings

3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate. Include separate line items under required principal subcontracts for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training in the amount of 5 percent of the Contract Sum.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

5. Include General Requirements Schedule of Values. Distribute costs into forecasted billings, and notify Owner if/why a forecasted amount is exceeded by actual amounts.

If actuals exceed forecasted amounts, request approval from Owner to shift funds amongst General Requirement line items to accommodate overages.

6. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.

7. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

8. Allowances: Provide a separate line item in the Schedule of Values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.

9. Purchase Contracts: Provide a separate line item in the schedule of values for each purchase contract. Show line-item value of purchase contract. Indicate owner

PAYMENT PROCEDURES 01 29 00 - 3

payments or deposits, if any, and balance to be paid by Contractor.

10. Each item in the Schedule of Values and Applications for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

11. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

12. At no time during the Project shall the Engineer-approved schedule of values line items change without submitting prior written notification with substantiating cause to Engineer and Owner.

1.5 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Engineer and Construction Manager and paid for by Owner. Schedule of Values line items shall not be modified without submitting prior written notification with substantiating cause to Engineer and Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: Submit Application for Payment to Engineer by the 10th of the month. The period covered by each Application for Payment is one month, ending on the last day of the previous month.

1. Submit draft copy of Application for Payment 7 days prior to due date for review by Engineer.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 Continuation Sheets as form for Applications for Payment.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Engineer will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment, for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.

3. Provide summary documentation for stored materials indicating the following:

PAYMENT PROCEDURES 01 29 00 - 4

a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.

b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.

c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.

F. Transmittal: Submit four (4) signed and notarized original copies of each Application for Payment to Engineer by a method ensuring receipt within 24 hours. Packet shall include waivers of lien and similar attachments if required. Engineer may require additional copies.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Submit final Application for Payment with or preceded by final waivers from every entity involved with performance of the Work covered by the application that is lawfully entitled to a lien.

5. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to Owner.

H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of Values.

3. Contractor's Construction Schedule (preliminary if not final).

4. Products list.

5. Schedule of unit prices.

6. Submittals Schedule (preliminary if not final).

7. List of Contractor's staff assignments.

8. List of Contractor's principal consultants.

9. Copies of building permits.

10. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

11. Initial progress report.

12. Report of preconstruction conference.

13. Certificates of insurance and insurance policies.

14. Performance and payment bonds.

PAYMENT PROCEDURES 01 29 00 - 5

15. Data needed to acquire Owner's insurance.

16. Initial settlement survey and damage report if required.

17. Itemized list and not to exceed dollar amounts for all self-perform work.

I. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."

5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."

6. AIA Document G707, "Consent of Surety to Final Payment."

7. Evidence that claims have been settled.

8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

9. Final, liquidated damages settlement statement.

10. Itemized list of all self-perform work with actual cost of each line item and original SOV cost for each line item. Owner approval required in order to exceed itemized list.

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

END OF SECTION 01 29 00

PAYMENT PROCEDURES 01 29 00 - 6

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 1

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. Requests for Information (RFIs).

4. Project meetings.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

C. Related Requirements:

1. Section 01 32 00 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.

2. Section 01 73 00 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.3 DEFINITIONS

A. RFI: Request from Owner, Engineer, or Contractor seeking information required by or clarifications of the Contract Documents.

1.4 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Use CSI Form 1.5A or form as approved by the Owner. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

1. Post copies of list in project meeting room, in temporary field office, and by each temporary telephone. Provide electronic copy to Flagler Schools during Pre-

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 2

Construction Conference. Keep list current at all times.

1.5 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.

1.6 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity, or as requested by Owner.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 3

a. Use applicable Drawings as a basis for preparation of coordination drawings.

Prepare sections, elevations, and details as needed to describe relationship of various systems and components.

b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.

c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

f. Indicate required installation sequences.

g. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Engineer indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate sub-framing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Mechanical and Plumbing Work: Show the following:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

c. Fire-rated enclosures around ductwork.

7. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes dimensioned from column center lines.

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 4

8. Fire-Protection System: Show the following:

a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.

9. Review: Engineer will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Engineer determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Engineer will so inform Contractor, who shall make changes as directed and resubmit.

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using Portable Data File (PDF) format.

3. BIM File Incorporation: When applicable, Construction Manager will incorporate Contractor's coordination drawing files into Building Information Model established for Project.

a. Construction Manager will perform three-dimensional component conflict analysis as part of preparation of coordination drawings. Resolve component conflicts prior to submittal. Indicate where conflict resolution requires modification of design requirements by Engineer.

4. Engineer will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files.

a. Engineer makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in Latest Edition Revit.

c. Contractor shall execute a data licensing agreement in the form of Agreement form acceptable to Engineer.

1.7 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Engineer will return RFIs submitted to Engineer by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Engineer.

6. RFI number, numbered sequentially.

7. RFI subject.

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 5

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature or stamp.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Engineer.

1. Attachments shall be electronic files in Adobe Acrobat PDF format.

D. Engineer's Action: Engineer will review each RFI, determine action required, and respond. Allow seven working days for Engineer's response for each RFI. RFIs received by Engineer after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of…

This is the start of the file's text. The full file is on GovTribe.