Evaluation_Criteria_for_Ocean_Center_Switchgear_Replacement_Project.docx

DOCX document 19 KB Posted

Attached to
Daytona Beach Ocean Center Electrical Switchgear Replacement
Solicitation number
26-P-04LL
Issued by
Volusia County, Florida

About this file

This is an evaluation criteria document for the Daytona Beach Ocean Center Electrical Switchgear Replacement Project in Florida, a state and local contract opportunity focused on replacing aging high voltage switchgear equipment at a premier event venue. The project encompasses the replacement of main-tie-main switchboards, bus duct systems, grounding infrastructure, and related electrical distribution components to enhance system reliability, safety, and code compliance for a 480V/208V distribution system serving an occupied convention center facility. The scope requires coordination with utility providers, advance shutdown notifications, phasing to maintain facility operations, and adherence to event calendar blackout dates, with equipment lead times for switchgear, transformers, and bus duct components identified as critical schedule considerations.

Evaluation of proposals will be scored on a 100-point basis distributed across four weighted categories: Price and Total Cost (30 percent), Technical Qualifications and Experience (25 percent), Project Approach and Schedule (25 percent), and Safety, Quality Control and Resources (20 percent). Contractors must possess active Florida Electrical Contractor licenses, employ superintendents with Florida Journeyman licenses and minimum four years of experience, maintain five years of business history, and demonstrate completion of at least three similar switchgear replacement projects. Technical submissions must include arc flash studies compliant with IEEE 1584-2018 standards, shop drawings within 30 days, as-built AutoCAD documentation, and comprehensive testing protocols. The evaluation criteria emphasize cost-effective solutions with reasonable unit pricing, lifecycle cost considerations, warranty extensions beyond the one-year minimum, dedicated project management resources, manufacturer-certified technicians, and demonstrated 24/7 emergency response capability for occupied facility operations.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Evaluation Criteria for Ocean Center Switchgear Replacement Project Scoring Matrix (100 %Total)

1. PRICE/TOTAL COST (30 %)

Base Bid Price

· Competitive total project cost

· Complete scope inclusion (no major qualifications/exclusions)

· Reasonable unit pricing breakdown

· Payment schedule alignment with project milestones Value & Cost Structure

· Allowances appropriately estimated

· Cost-effective alternatives proposed

· Warranty terms (1-year minimum, extensions valued)

· Lifecycle cost considerations

2. TECHNICAL QUALIFICATIONS & EXPERIENCE (25 %)

Contractor Qualifications

· Active Florida Certified Electrical Contractor (EC) License

· Superintendent with active FL Journeyman License + 4 years experience minimum

· Company minimum 5 years in business Relevant Project Experience

· Similar switchgear replacement projects completed (minimum 3 references)

· 480V/208V distribution system experience

· Occupied facility/convention center work

· Projects completed

· Arc flash studies and power system analysis experience

3. PROJECT APPROACH & SCHEDULE (25%)

Schedule & Coordination

· Realistic timeline with event calendar blackout dates acknowledged

· Phasing plan to maintain facility operations

· 4-week advance notice protocol for closures

· Utility coordination and 60-day shutdown notification plan

· Equipment lead times identified (switchgear, transformers, bus duct) Technical Approach

· Understanding of main-tie-main switchboard replacement sequence

· Bus duct and grounding system installation methodology

· Testing protocols (short circuit, coordination, arc flash analysis per IEEE 1584-2018)

· Submittal schedule (shop drawings within 30 days, O&M manuals)

· As-built documentation plan (AutoCAD format, record drawings)

· Special conditions compliance (staging, security fencing, parking)

4. SAFETY, QUALITY CONTROL & RESOURCES (20%)

Safety Program

· OSHA compliance record

· Arc flash PPE program

· Energized work training documentation

· Site-specific safety plan for occupied facilities

· Recent safety record/incident-free hours Quality Assurance & Resources

· QA/QC procedures and inspection plan

· Testing equipment availability (ground resistance, insulation, torque tools)

· Dedicated project team (PM, full-time superintendent)

· Manufacturer-certified technicians

· 24/7 emergency response capability

· Material procurement and local supplier relationships

· Warranty management procedures