DBOC_Special_Conditions.docx
DOCX document 21 KB Posted
- Solicitation number
- 26-P-04LL
- Issued by
- Volusia County, Florida
About this file
This Special Conditions document outlines operational requirements for contractors performing work at the Daytona Beach Ocean Center, a premier event venue in Florida. The contractor must coordinate all work activities around the Ocean Center's scheduled events calendar, which identifies blackout dates when construction is prohibited. The Ocean Center will designate staging areas in close proximity to the project site, though these areas may be relocated as needed to accommodate ongoing events and operational requirements. Contractors are required to provide four weeks' advance notice for any closures affecting building entrances, exits, or direct building access, and one week's notice for any extensions beyond the approved project timeline.
All contractors must comply with strict site management and security requirements at the Ocean Center. Contractors are restricted to designated parking areas only, with parking on sidewalks or outside dedicated workspace strictly prohibited. The contractor must secure the work site and all staging areas with six-foot chain link fencing featuring black liner and appropriate signage. All equipment, tools, and supplies must be secured in designated staging areas at the end of each workday. These conditions apply to the Daytona Beach Ocean Center Electrical Switchgear Replacement project, which involves replacing aging high voltage switchgear equipment with modern systems to improve electrical reliability, enhance safety infrastructure, ensure compliance with current electrical codes, and support future facility expansion.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL CONDITIONS
Contractors will work around the Ocean Center scheduled events. The events Calender will be provided for the project timeframe identifying blackout dates with no construction permitted. The Calander is subject to change.
The Ocean Center will set up the location of staging areas and will make the best efforts to be close to the project area. Staging area may be relocated for the ongoing events and client’s needs.
Contractors must park in designated areas only. Parking on sidewalks or outside dedicated workspace is prohibited.
Contractors are responsible for securing their work site and staging areas with 6-foot chain link fence with black liner and proper signage. All equipment, tools and supplies must be secured at the end of day is agreed staging areas.
The Ocean Center will need 4-week advanced notice for any closures of building entrances/ exits or work affecting direct building access. Extensions beyond approved time will need 1 week notice.