This document is a Past and Present Performance Questionnaire for a Department of Veterans Affairs contract opportunity (Solicitation No. 36C24826Q0188). The solicitation is for a design-build project at James A. Haley VA Hospital in Tampa, Florida, involving the replacement of two fire barrier doors connecting Buildings 32 and 38. The project (Project #673-26-112) requires furnishing professional services, equipment, labor, materials, and specialty services to replace existing drop-down fire doors with fire-rated swing double doors that will automatically close when smoke detectors are activated.

The questionnaire is designed to collect detailed performance references from previous contractors, with ratings on 22 specific performance criteria including project management, personnel capabilities, problem-solving, schedule adherence, and overall performance. The solicitation requires work potentially during non-standard hours (weekends, holidays, evenings, nights) and mandates that the design-build team include professional service subcontractors with appropriate licensing and certifications. The Phase I quote is due on 02/16/2026 at 10:00 AM EST, with the contracting officer being David Hernandez from the VA Network Contracting Office 8.

View the file

Other files

File Type Posted
WD-FL20260208 01-02-26.pdf PDF
013526 Safety Requirements Tampa Specific - Copy.docx DOCX document
015719 Temporary Environmental Controls - Copy.docx DOCX document
081400 Interior Wood Doors - Copy.docx DOCX document
090600 Schedule for Finishes - Copy.docx DOCX document
260511 Requirements for Electrical Installations - Copy.docx DOCX document
280500 Common Results Electronics Safety Security - Copy.docx DOCX document
014535 Special Inspections - Copy.docx DOCX document
015816 Temporary Interior Signage - Copy.docx DOCX document
096519 Resilient Tile Flooring - Copy.docx DOCX document
Experience information Sheet.pdf PDF
092900 Gypsum - Copy.docx DOCX document
260526 Grounding and Bonding - Copy.docx DOCX document
283100 Fire Detection and Alarm - Copy.doc DOC document
38 LS - Copy.pdf PDF
Building 38 - As Built_Drawings - Copy.pdf PDF
013323 Shop Drawings - Copy.docx DOCX document
022113 Site Surveys - Copy.docx DOCX document
081710 Integrated Door Assemblies - Copy.docx DOCX document
092216 Non Structural Metal Framing - Copy.docx DOCX document
260533 Raceways and Boxes - Copy.docx DOCX document
38 32 Main Opening - Copy.pdf PDF
Bldg 32 Arch As Builts - Copy.pdf PDF
01321616 Network Analysis Schedule DB - Copy.docx DOCX document
014500 Quality Control - Copy.docx DOCX document
017419 Construction Waste Management - Copy.docx DOCX document
024100 Demolition - Copy.docx DOCX document
fire-38gfloor-Floor - Ansi C - Copy.pdf PDF
014219 Reference Standards - Copy.docx DOCX document
081113 Hollow Metal Doors and Frames - Copy.docx DOCX document
fire-32gfloor-Ansi C - Copy.pdf PDF
Schematic Design - Copy.pdf PDF
Base Offer Price Breakdown - 1 page.xlsx XLSX spreadsheet
096513 Resilient Base - Copy.docx DOCX document
260513 Medium Voltage - Copy.docx DOCX document
262726 Wiring Devices - Copy.docx DOCX document
010000 TIL General Specification - Tampa Specific - Copy.docx DOCX document
095100 Acoustical Ceiling - Copy.docx DOCX document
099100 Painting - Copy.docx DOCX document
260519 Low Voltage - Copy.docx DOCX document
262921 Enclosed Switches and Circuit Breakers - Copy.docx DOCX document
280513 Conductors and Cables for Electronic Safety Security - Copy.docx DOCX document
EMR 1 page.pdf PDF
36C24826Q0188_1.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST AND PRESENT PERFORMANCE QUESTIONNAIRE

INSTRUCTIONS TO CONTRACTOR

Complete the CONTRACTOR INFORMATION section below in light blue shaded boxes. Send to the point of contact listed requesting they please complete the form and submit it according to the instructions below.

INSTRUCTIONS TO REFERENCE CONTACT

The contractor named below is submitting an offer for a United States Department of Veterans Affairs contract requirement, and has sent this form to you, in your role as a past performance reference contact. Please complete this form in full (all areas shaded in light yellow, below). Once completed, please send the form to the Contracting Officer only by email:

Department of Veterans Affairs NCO 8 Contracting Office TO: David Hernandez Contracting Officer, Email: david.hernandez1@va.gov

REF SOLICITATION NUMBER: 36C24826Q0188

Please return before required due date of at 10:00 AM EST.

If you are unable to provide this information, please inform the Contractor listed below.

CONTRACTOR INFORMATION [completed by Contractor] Contractor Company Name

Street Address

Contractor Point of Contact Name

City

Point of Contact Phone Number

State

Reference Project Title

Zip Code

Contract POP (start to finish):

Email

Contract Number

Contract Dollar Value

Description of Work

Role of Contractor on This Project (check appropriate box)

· Prime Contractor ☐ Sub-contractor ☐ Key Personnel

RESPONDENT INFORMATION [completed by Reference Contact] Company Name

Street Address

POC Name

City

Phone Number

State

Fax Number

Zip Code

Email

PERFORMANCE INFORMATION: Choose the number on the scale of 1 to 6 that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF 1 OR 2 in the applicable text box OR in the Remarks section, below (text box will expand to whatever extent is necessary).

1
2
3
4
5
6
UNSATISFACTORY
MARGINAL
SATISFACT ORY
VERY GOOD
EXCEPTIONAL
NEUTRAL
Performance did not meet most contractual requirements. There were serious problems and the contractor’s corrective actions were ineffective.
Performance did not meet some contractual requirements.

There were problems, some of a serious nature, for which corrective action was only marginally effective.

Performance met contractual requirements. There were some minor problems and corrective actions taken by the contractor are satisfactory.
Performance met all contract requirements and exceeded some to the government’s benefit. There were a few minor problems, which the contractor resolved in a timely, effective manner.
Performance met all contract requirements and exceeded many to the government’s benefit.

Problems, if any, were negligible and were resolved in a timely, highly effective manner.

No record of past performance or the record is inconclusive

The Contractor …
1
2
3
4
5
6
1.
Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.

Narrative:

☐
☐
☐
☐
☐
☐
2.
Demonstrated ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.

Narrative:

☐
☐
☐
☐
☐
☐
3.
Delegated authority to project managers and supervisors commensurate with contract requirements.

Narrative:

☐
☐
☐
☐
☐
☐
4.
Home office participated in solving significant local problems. Narrative:
☐
☐
☐
☐
☐
☐
5.
Followed approved quality control plan. Narrative:
☐
☐
☐
☐
☐
☐
6.
Provided effective quality control and/or inspection procedures to meet contract requirements.

Narrative:

☐
☐
☐
☐
☐
☐
7.
Corrected deficiencies in timely manner and pursuant to their quality control procedures.

Narrative:

☐
☐
☐
☐
☐
☐
8.
Provided timely resolution of contract discrepancies Narrative:
☐
☐
☐
☐
☐
☐
9.
Identified problems as they occurred. Narrative:
☐
☐
☐
☐
☐
☐
10.
Suggested alternative approaches to problems.

Narrative:

☐
☐
☐
☐
☐
☐
11.
Displayed initiative to solve problems. Narrative
☐
☐
☐
☐
☐
☐
12.
Developed realistic progress schedules. Narrative:
☐
☐
☐
☐
☐
☐
13.
Met established project schedules. Narrative:
☐
☐
☐
☐
☐
☐
14.
Provided timely resolution of warranty defects. Narrative:
☐
☐
☐
☐
☐
☐
15.
Was responsive to contract changes. Narrative:
☐
☐
☐
☐
☐
☐
16.
Provided adequate project supervision. Narrative:
☐
☐
☐
☐
☐
☐
17.
Obtained consent of surety for increases in bonding as work-in-progress increased.

Narrative:

☐
☐
☐
☐
☐
☐
18.
Paid subcontractors/suppliers in a timely manner. Narrative:
☐
☐
☐
☐
☐
☐
19.
Provided accurate and complete line item cost proposals including all aspects of work required for each task.

Narrative:

☐
☐
☐
☐
☐
☐
20.
Cooperated with Government personnel after award. Narrative:
☐
☐
☐
☐
☐
☐
21.
How would you rate the contractor's overall performance? Narrative:
☐
☐
☐
☐
☐
☐
22.
Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.”
☐
YES
☐
NO
23
Would you award another contract to this contractor? If not, please explain in “remarks.”
☐
YES
☐
NO
24
To the best of your knowledge, is the contractor rated in CPARS?
☐
YES
☐
NO

REMARKS (Please use as much space as is needed – the box will expand as you type).

Printed Name/ Title Signature

Source Selection Information--See FAR 2.101 and 3.104

File details come from the government source that posted it. Updated .