Paint IDIQ AF 3052 Contractor Cost Estimate.xlsx

XLSX spreadsheet 44 KB Posted

Attached to
Painting IDIQ Maxwell AFB and Gunter Annex 2026 - AMENDMENT 2
Solicitation number
FA330026R0020
Issued by

About this file

This is a Contractor Cost Estimate template in Excel format for a painting Indefinite Delivery Indefinite Quantity (IDIQ) contract at Maxwell Air Force Base and Gunter Annex. The solicitation FA330026R0020 is a competitive, 100% Total Economically Disadvantaged Women-Owned Small Business (EDWOSB) set-aside firm-fixed-price contract issued by the Department of the Air Force Air Education and Training Command. Contractors must be located within a 250-mile radius of Maxwell AFB, Alabama, and failure to meet this geographic requirement renders offerors ineligible for award. The solicitation references ten attachments and requires offerors to follow all instructions in the Request for Proposal posted to sam.gov under Notice ID FA330026R0029.

A mandatory site visit is scheduled for July 14, 2026 at 9:00 AM CDT at the University Inn (Building 1017), 545 S. Morris Avenue, Maxwell AFB-Gunter Annex, Alabama 36114. All attendees must submit their names by July 13, 2026 at 1:00 PM CDT to Shamekia Williams (shamekia.williams.1@us.af.mil) along with title and telephone number. Attendees are required to bring valid driver's licenses, proof of vehicle insurance, and vehicle registration. Offerors are encouraged to conduct site visits to ascertain work location, nature, and conditions that may affect work execution or costs.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base

CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACTOR DATE ADDRESS

CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
Painting IDIQ - Year 1$0.00
LOCATION (Work to be performed)PROJECT NUMBER/WORK ORDERWORK LOCATION
Maxwell
ITEMUNIT OF MEASUREQUANTITYMATERIAL/EQUIP. COSTSLABOR RATESOTHER
UNITAVERAGEDIRECTLINE
TOTALRATETOTALCOSTSTOTAL
DIVISION 1 (General Requirements)
Project ManagerMH$0.00$0.00$0.00
$0.00
DIVISION 9 (FINISHES)$0.00$0.00
$0.00
Lead Base Paint removal, InteriorSF$0.00$0.00$0.00
Patch walls, InteriorLot$0.00$0.00$0.00
Prepare Walls, InteriorSF$0.00$0.00$0.00
Prime Walls (per coat), InteriorSF$0.00$0.00$0.00
Paint walls (per coat), InteriorSF$0.00$0.00$0.00
Move furniture, InteriorLot$0.00$0.00$0.00
Paint Trim, InteriorLF$0.00$0.00$0.00
Paint Door, InteriorEA$0.00$0.00$0.00
Refinish Door, InteriorEA$0.00$0.00$0.00
$0.00
Lead Base Paint removal, ExteriorSF$0.00$0.00$0.00
Patch surfaces, ExteriorLot$0.00$0.00$0.00
Prepare surfaces, ExteriorSF$0.00$0.00$0.00
Prime surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Paint surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Pressure wash surfaces, ExteriorSF$0.00$0.00$0.00
Paint Trim, ExteriorLF$0.00$0.00$0.00
Paint Door, ExteriorEA$0.00$0.00$0.00
Refinish Door, ExteriorEA$0.00$0.00$0.00
$0.00$0.00$0.00
TOTAL$0.00$0.00$0.00$0.00
$0.00$0.00$0.00
Material Costs$0.00$0.00
Tax on Materials10%$0.00$0.00
TOTAL MATERIAL COST$0.00$0.00
$0.00$0.00$0.00
Labor Cost$0.00$0.00
Insurance & Tax on Labor20%$0.00$0.00
TOTAL LABOR COST$0.00$0.00
$0.00$0.00$0.00
Total Other Direct Costs$0.00$0.00$0.00
Total Material, Labor, Tax & Insurance$0.00$0.00
TOTAL DIRECT COSTS$0.00$0.00$0.00
$0.00$0.00$0.00
Overhead10%$0.00$0.00$0.00
Subtotal$0.00$0.00$0.00$0.00
Profit10%$0.00$0.00$0.00
Sub Total$0.00$0.00
TOTAL$0.00$0.00$0.00
Bonds2.5%$0.00$0.00
TOTAL$0.00$0.00$0.00
$0.00
I acknowledge the above cost estimate has been estimated to the best of my ability and means.

Signature: ______________________________________

Year 2

CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACTOR DATE ADDRESS

CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
Painting IDIQ - Year 2$0.00
LOCATION (Work to be performed)PROJECT NUMBER/WORK ORDERWORK LOCATION
Maxwell
ITEMUNIT OF MEASUREQUANTITYMATERIAL/EQUIP. COSTSLABOR RATESOTHER
UNITAVERAGEDIRECTLINE
TOTALRATETOTALCOSTSTOTAL
DIVISION 1 (General Requirements)
Project ManagerMH$0.00$0.00$0.00

DIVISION 9 (FINISHES)

Lead Base Paint removal, InteriorSF$0.00$0.00$0.00
Patch walls, InteriorLot$0.00$0.00$0.00
Prepare Walls, InteriorSF$0.00$0.00$0.00
Prime Walls (per coat), InteriorSF$0.00$0.00$0.00
Paint walls (per coat), InteriorSF$0.00$0.00$0.00
Move furniture, InteriorLot$0.00$0.00$0.00
Paint Trim, InteriorLF$0.00$0.00$0.00
Paint Door, InteriorEA$0.00$0.00$0.00
Refinish Door, InteriorEA$0.00$0.00$0.00
Lead Base Paint removal, ExteriorSF$0.00$0.00$0.00
Patch surfaces, ExteriorLot$0.00$0.00$0.00
Prepare surfaces, ExteriorSF$0.00$0.00$0.00
Prime surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Paint surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Pressure wash surfaces, ExteriorSF$0.00$0.00$0.00
Paint Trim, ExteriorLF$0.00$0.00$0.00
Paint Door, ExteriorEA$0.00$0.00$0.00
Refinish Door, ExteriorEA$0.00$0.00$0.00
TOTAL$0.00$0.00$0.00
ERROR:#VALUE!
Material Costs$0.00
Tax on Materials10%$0.00
TOTAL MATERIAL COST$0.00
$0.00
Labor Cost$0.00
Insurance & Tax on Labor20%$0.00
TOTAL LABOR COST$0.00
$0.00
Total Other Direct Costs$0.00
Total Material, Labor, Tax & Insurance$0.00
TOTAL DIRECT COSTS$0.00
ERROR:#VALUE!
Overhead10%$0.00
Subtotal$0.00
Profit10%$0.00
Sub Total$0.00
TOTAL$0.00
Bonds2.5%$0.00
TOTAL$0.00

I acknowledge the above cost estimate has been estimated to the best of my ability and means.

Signature: ______________________________________

Year 3

CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACTOR DATE ADDRESS

CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
Painting IDIQ - Year 3$0.00
LOCATION (Work to be performed)PROJECT NUMBER/WORK ORDERWORK LOCATION
Maxwell
ITEMUNIT OF MEASUREQUANTITYMATERIAL/EQUIP. COSTSLABOR RATESOTHER
UNITAVERAGEDIRECTLINE
TOTALRATETOTALCOSTSTOTAL
DIVISION 1 (General Requirements)
Project ManagerMH$0.00$0.00$0.00

DIVISION 9 (FINISHES)

Lead Base Paint removal, InteriorSF$0.00$0.00$0.00
Patch walls, InteriorLot$0.00$0.00$0.00
Prepare Walls, InteriorSF$0.00$0.00$0.00
Prime Walls (per coat), InteriorSF$0.00$0.00$0.00
Paint walls (per coat), InteriorSF$0.00$0.00$0.00
Move furniture, InteriorLot$0.00$0.00$0.00
Paint Trim, InteriorLF$0.00$0.00$0.00
Paint Door, InteriorEA$0.00$0.00$0.00
Refinish Door, InteriorEA$0.00$0.00$0.00
Lead Base Paint removal, ExteriorSF$0.00$0.00$0.00
Patch surfaces, ExteriorLot$0.00$0.00$0.00
Prepare surfaces, ExteriorSF$0.00$0.00$0.00
Prime surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Paint surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Pressure wash surfaces, ExteriorSF$0.00$0.00$0.00
Paint Trim, ExteriorLF$0.00$0.00$0.00
Paint Door, ExteriorEA$0.00$0.00$0.00
Refinish Door, ExteriorEA$0.00$0.00$0.00
TOTAL$0.00$0.00$0.00$0.00
$0.00
Material Costs$0.00
Tax on Materials10%$0.00
TOTAL MATERIAL COST$0.00
$0.00
Labor Cost$0.00
Insurance & Tax on Labor20%$0.00
TOTAL LABOR COST$0.00
$0.00
Total Other Direct Costs$0.00
Total Material, Labor, Tax & Insurance$0.00
TOTAL DIRECT COSTS$0.00
$0.00
Overhead10%$0.00
Subtotal$0.00
Profit10%$0.00
Sub Total$0.00
TOTAL$0.00
Bonds2.5%$0.00
TOTAL$0.00

I acknowledge the above cost estimate has been estimated to the best of my ability and means.

Signature: ______________________________________

Year 4

CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACTOR DATE ADDRESS

CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
Painting IDIQ - Year 4$0.00
LOCATION (Work to be performed)PROJECT NUMBER/WORK ORDERWORK LOCATION
Maxwell
ITEMUNIT OF MEASUREQUANTITYMATERIAL/EQUIP. COSTSLABOR RATESOTHER
UNITAVERAGEDIRECTLINE
TOTALRATETOTALCOSTSTOTAL
DIVISION 1 (General Requirements)
Project ManagerMH$0.00$0.00$0.00

DIVISION 9 (FINISHES)

Lead Base Paint removal, InteriorSF$0.00$0.00$0.00
Patch walls, InteriorLot$0.00$0.00$0.00
Prepare Walls, InteriorSF$0.00$0.00$0.00
Prime Walls (per coat), InteriorSF$0.00$0.00$0.00
Paint walls (per coat), InteriorSF$0.00$0.00$0.00
Move furniture, InteriorLot$0.00$0.00$0.00
Paint Trim, InteriorLF$0.00$0.00$0.00
Paint Door, InteriorEA$0.00$0.00$0.00
Refinish Door, InteriorEA$0.00$0.00$0.00
Lead Base Paint removal, ExteriorSF$0.00$0.00$0.00
Patch surfaces, ExteriorLot$0.00$0.00$0.00
Prepare surfaces, ExteriorSF$0.00$0.00$0.00
Prime surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Paint surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Pressure wash surfaces, ExteriorSF$0.00$0.00$0.00
Paint Trim, ExteriorLF$0.00$0.00$0.00
Paint Door, ExteriorEA$0.00$0.00$0.00
Refinish Door, ExteriorEA$0.00$0.00$0.00
TOTAL$0.00$0.00$0.00$0.00
$0.00
Material Costs$0.00
Tax on Materials10%$0.00
TOTAL MATERIAL COST$0.00
$0.00
Labor Cost$0.00
Insurance & Tax on Labor20%$0.00
TOTAL LABOR COST$0.00
$0.00
Total Other Direct Costs$0.00
Total Material, Labor, Tax & Insurance$0.00
TOTAL DIRECT COSTS$0.00
$0.00
Overhead10%$0.00
Subtotal$0.00
Profit10%$0.00
Sub Total$0.00
TOTAL$0.00
Bonds2.5%$0.00
TOTAL$0.00

I acknowledge the above cost estimate has been estimated to the best of my ability and means.

Signature: ______________________________________

Year 5

CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACTOR DATE ADDRESS

CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
Painting IDIQ - Year 5$0.00
LOCATION (Work to be performed)PROJECT NUMBER/WORK ORDERWORK LOCATION
Maxwell
ITEMUNIT OF MEASUREQUANTITYMATERIAL/EQUIP. COSTSLABOR RATESOTHER
UNITAVERAGEDIRECTLINE
TOTALRATETOTALCOSTSTOTAL
DIVISION 1 (General Requirements)
Project ManagerMH$0.00$0.00$0.00

DIVISION 9 (FINISHES)

Lead Base Paint removal, InteriorSF$0.00$0.00$0.00
Patch walls, InteriorLot$0.00$0.00$0.00
Prepare Walls, InteriorSF$0.00$0.00$0.00
Prime Walls (per coat), InteriorSF$0.00$0.00$0.00
Paint walls (per coat), InteriorSF$0.00$0.00$0.00
Move furniture, InteriorLot$0.00$0.00$0.00
Paint Trim, InteriorLF$0.00$0.00$0.00
Paint Door, InteriorEA$0.00$0.00$0.00
Refinish Door, InteriorEA$0.00$0.00$0.00
Lead Base Paint removal, ExteriorSF$0.00$0.00$0.00
Patch surfaces, ExteriorLot$0.00$0.00$0.00
Prepare surfaces, ExteriorSF$0.00$0.00$0.00
Prime surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Paint surfaces (per coat), ExteriorSF$0.00$0.00$0.00
Pressure wash surfaces, ExteriorSF$0.00$0.00$0.00
Paint Trim, ExteriorLF$0.00$0.00$0.00
Paint Door, ExteriorEA$0.00$0.00$0.00
Refinish Door, ExteriorEA$0.00$0.00$0.00
TOTAL$0.00$0.00$0.00$0.00
$0.00
Material Costs$0.00
Tax on Materials10%$0.00
TOTAL MATERIAL COST$0.00
$0.00
Labor Cost$0.00
Insurance & Tax on Labor20%$0.00
TOTAL LABOR COST$0.00
$0.00
Total Other Direct Costs$0.00
Total Material, Labor, Tax & Insurance$0.00
TOTAL DIRECT COSTS$0.00
$0.00
Overhead10%$0.00
Subtotal$0.00
Profit10%$0.00
Sub Total$0.00
TOTAL$0.00
Bonds2.5%$0.00
TOTAL$0.00

I acknowledge the above cost estimate has been estimated to the best of my ability and means.

Signature: ______________________________________

File details come from the government source that posted it. Updated .