Attachment 8 Task Order Specifications -JUBJ 24-7621 Paint Ext Bldg 1017 Gunter.pdf
PDF 3 MB Posted
- Solicitation number
- FA330026R0020
About this file
This document is the Task Order Specifications for JUBJ 24-7621, a pressure washing and exterior painting project for Lodging Building 1017 at Maxwell Air Force Base, Gunter Annex, Alabama. The contractor must furnish all labor, materials, equipment, and plant necessary to pressure wash and paint the exterior of Building 1017, including all stairs, ramps, railings, retaining walls, EFIS banisters, planters, and clock tower area features. The work must be completed within 180 calendar days, performed primarily during normal working hours (7:00 AM to 4:00 PM) with coordination required for weekend or holiday work. The building will remain occupied during construction, requiring the contractor to coordinate closely with facility management to minimize interference with necessary activities.
The specifications incorporate strict environmental protection requirements, including compliance with Maxwell Air Force Base's Lead-Based Paint Protocol and Storm Water Best Management Practices for both latex and oil-based paints. The contractor must register all hazardous materials with the Maxwell AFB Hazardous Material Manager and implement comprehensive erosion control measures, waste management plans, and pollution prevention protocols. Additional requirements include obtaining necessary security clearances and identification for personnel, maintaining insurance coverage (workers' compensation, general liability, and automobile liability with specified minimum limits), providing equipment operating manuals, as-built drawings, and geospatial deliverables in specified formats. The contractor is responsible for daily site cleanup, protection of existing landscape and trees, repair of any damage caused during construction, and final inspection preparations with a punchlist correction process before contract completion.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 00005
SECTION 00005
SCHEDULE OF BID ITEMS
ITEM 0001: Furnish all plant, labor, materials and equipment necessary to perform all work in connection with JUBJ 24-
7621, Paint Ext, Lodging Bldg 1017, Maxwell AFB, Gunter Annex, Alabama, in accordance with the attached specifications.
Item No. Description Unit of
Issue Total Amount
1 Pressure Wash & Paint Building & 1017 EA $
Total Bid Items:1 $________________________
COMPANY NAME: ___________________________________
PRINTED NAME: _____________________________________
SIGNATURE: _________________________________________
DATE: ________________________________________________
JUBJ 24-7621 Pressure Wash & Paint Building 1017
42 CES/CEN, MAXWELL AFB, GUNTER ANNEX ALABAMA
GENERAL REQUIREMENTS 01000-1
DIVISION 1: Section 01000: General Requirements
1.0 SUMMARY OF WORK
1.1 The work covered by these specifications consists of furnishing all plant, labor, equipment and materials and performing all operations in connection with the JUBJ 24-7621 PAINT
EXTERIOR, LODGING BLDG 1017 to include all areas as indicated in strict accordance with these specifications and applicable drawings and subject to terms and conditions of the contract.
The work generally consists of the following:
1.2 Service provider shall perform all work in accordance with Specification Section 09900, 07120 ELASTOMERIC COATING (or equal), Maxwell LBP Protocol, Maxwell Storm Water
BMPS for Latex Paint, and Maxwell Storm Water BMPs for Oil Based Paint, Polyurethane, and
Cleaning Solutions.
1.3 The contractor will be responsible for removing debris from jobsite daily. The contractor must ensure that the workplace is safe from hazards so that daily operations can be maintained, and the buildings occupied during the painting/pressure washing process. The contractor is responsible for all quantities to establish bid proposals.
1.4 The service provider will work with the facility manager to coordinate work with the areas to avoid interference with necessary activities.
1.5 Protect fire alarm/ mass notification / fire suppression devices from damage during high pressure water stream during pressure washing/painting.
1.6 Service provider shall furnish all necessary equipment, materials, labor, and transportation necessary to repair, pressure wash and paint exterior building1017, including all stair/ramps, railings, retaining walls and EFIS banisters connected to building 1017.
1.7 Include all planters/retaining walls in the clock tower area.
2.0 BUILDING OCCUPANCY
2.1 Building will be occupied during construction. The Contractor shall perform the majority of work during normal working hours.
3.0 SCHEDULE OF WORK
3.1 SCHEDULING: The Contractor shall be responsible for establishing a schedule to meet construction time. Contractor shall prepare a work schedule on forms provided for schedule of work. Contractor cannot start on site without submitting an initial schedule. Contractor shall have 180 calendar days to complete the work.
GENERAL REQUIREMENTS 01000-2
3.2 PHASING OF WORK: The work herein will be completed in one phase
4.0 GENERAL
4.1 The contractor shall coordinate work with the government to avoid interference with necessary activities within and adjacent to the construction site. The Contractor shall coordinate the work of all trades to prevent any conflicts. The Contractor, before proceeding with the construction, shall resolve any conflicts of components.
4.2 The Contractor will perform all work during work hours between 7:00 A. M. and 4:00
P.M (normal working hours). The Contractor will not normally be permitted to work on weekends or on the following legal holidays (or the day the federal government observes these holidays) unless the contractor has coordinated such work with the
Technical Monitor/Contract Administrator at least 72 hours in advance:
a. New Year's Day g. Labor Day
b. Martin Luther King, Jr.'s Birthday h. Columbus Day
c. Washington’s Birthday i. Veteran's Day
d. Memorial Day
e. Juneteenth j. Thanksgiving Day
f. Independence Day k. Christmas Day
5.0 SITE VISIT
Contractor is responsible for site investigation in accordance with the contract clause entitled
"Site Investigation and Conditions Affecting the Work" (FAR 52.236-3).
6.0 CONTRACT DRAWINGS AND SPECIFICATIONS
The Contractor must comply with the contract clause entitled "Specifications and Drawings for
Construction" (FAR 52.236-21). See paragraph 19.01 entitled "INTENT OF DRAWINGS".
7.0 DESCRIPTIVE DATA
7.1 The Contractor shall submit three (3) copies of AF Form 3000, Material Submittal
Approval, to the Contracting Officer (CO) for approval. Included shall be manufacturer's descriptive data for materials, fixtures, and equipment the Contractor proposes to incorporate in the work. The submittal shall include catalog numbers, diagrams, drawings, and additional descriptive data and samples required to properly evaluate all items. When specifications require materials to conform to Federal, Military, Commercial, American Society for Testing Materials (ASTM), or other specifications and standards, the Contractor shall submit supplier's or manufacturer's
Certification of Conformance in addition to other descriptive data. Catalog numbers and trade names specified indicate examples of a standard product. Other manufacturers' products may be substituted contingent upon approval. Approval of all items must be obtained prior to fabrication or purchase. Payment for work incorporating these materials will not be made if required material submittals have
GENERAL REQUIREMENTS 01000-3
not been approved. Approval of materials, fixtures, and equipment will be based on manufacturer's published ratings and conformance with specifications.
7.1.1 The Material Descriptive Data Submittal shall include the information indicated in each specification section.
7.1.2 The Shop Drawing Submittal shall include the information indicated in each specification section.
7.1.3 The Samples Submittal shall include the information indicated in each specification section.
7.2 CONTRACTOR DEVIATION
When data is submitted for approval, the CO approval of such data shall not relieve the Contractor from responsibility for errors or deviation from contract drawings and specifications. In the case of a deviation, the Contractor shall inform the Contracting
Officer in writing of the request for deviation with all the specific data related to the change.
8.0 REAL PROPERTY SUBMITTAL DATA
Provide data as requested by the Government to complete real property records.
8.1 REMOVAL PROCEDURES:
No items removed will be reused in this contract unless specifically listed in these specifications and/or on the drawings. All removed equipment becomes the property of the Contractor unless noted otherwise. The Contractor will be required to furnish lifting equipment as necessary to remove the equipment and shall provide all equipment to transport the removed items off base. All unused material or debris will be removed from
Government-controlled property. Use of Government-contracted dumpsters is prohibited.
Unused materials, debris and rubbish shall be disposed of off base in a permitted landfill.
The Contractor shall comply with Alabama Department of Environmental Management
(ADEM) Code, Division 13, Solid Waste Program, and Chapter 335-13-1, through 335-
13-8; Adopted November 18, 1981; Amended July 26, 1996.
8.2 REFRIGERANTS
All refrigerants must remain the possession of the Air Force. Refrigerants removed from any refrigeration systems must be turned over to the Refrigerant Manager, 42CES/CEOH, 400 Cannon Street, Maxwell AFB.
REFER TO SPECIFICATION SECTION 01001 ENVIRONMENTAL PROTECTION
EXHIBIT L
9.0 GOVERNMENT-FURNISHED ITEMS: n/a
GENERAL REQUIREMENTS 01000-4
10.0 REFERENCED PUBLICATIONS
All publications referenced in this specification but not shown in each part under paragraph entitled "APPLICABLE PUBLICATIONS", also form a part of these specifications to the extent referenced.
11.0 HEALTH STANDARDS
The following specified guidance is essential to maintaining compliance with the health standards on this base. This contract must adhere to all of the following.
11.1 Radioactive Materials (RAM): Air Force requirements for the management are listed in AFI 40-201, Management Radioactive Materials in the USAF. All contractors who intend to bring RAM (such as the materials in the soil density gauges, X-ray fluorescence meters, etc.) onto Maxwell AFB must first obtain written approval from the Base Radiation Safety Officer (RSO), in the Bioenvironmental
Engineering (BEE) Flight 334-953-5848. To provide this approval, the RSO needs a written request no later than 30 days prior to initiating any work requiring radioactive material. The request must include the following information:
11.1.1 A copy of your NRC license (or State license with a current NRC FonD
241) that authorizes your use of radioactive material on this installation.
11.1.2 Training certificate(s) for individual(s) who will use the instrument on base.
11.1.3 The most recent leak/wipe test for the instrument(s) that will be used on base.
11.1.4 A signed document on company letterhead paper that includes:
11.1.5 A brief description of your proposed activities including instruments to be used and their purpose, the contract number and title under which you will work, location of the work (closest building number, annotated map, or similar identification), and anticipated start and end dates (with the understanding that actual days of use are difficult to specify in advance).
11.1.6 The name, local address, and telephone number of both the local representative responsible and the RSO.
11.1.7 Name and phone number of the Maxwell AFB inspector overseeing the project.
11.1.8 An acknowledgement that the Maxwell AFB RSO can make periodic
Checks to ensure contractor personnel follow radiation safety practices to prevent exposure to Air Force personnel and avoid contamination of government property as well as an understanding that the Maxwell AFB
RSO has the authority to suspend any contractor operation believed to be unsafe.
GENERAL REQUIREMENTS 01000-5
11.2 Asbestos/Lead-Based Paint
Contractors who will perform asbestos and or lead-based paint abatement work must comply with all OSHA regulations and be certified by Safe State of Alabama. In particular, after all visible debris has been removed and the abatement area has been appropriately decontaminated, the contractor must perform clearance sampling verifying the area is clean before re-occupancy can be allowed. BEE must review all clearance sample results prior to government acceptance of abatement areas as clean. Contractors can expedite this process by faxing copies of clearance results directly to the BEE for review.
11.3 Drinking Water:
11.3.1 If a facility is to be constructed in which sources of drinking water are provided (sinks, water fountains, showers, etc.), the water lines must be flushed thoroughly prior to occupancy. BEE approval is required before the water is declared potable. The contractor is required to test the interior water lines, provide BEE the documentation at two weeks prior to occupancy of the facility. If the contractor is not required to do bacteriological testing of the interior water lines, the BEE office should be contacted at least two weeks prior to occupancy so that we may schedule our testing of the system.
11.3.2 If water mains are constructed or repaired, disinfection of the lines must be conducted as stated in ANSI/AWWA C651-92, American Water Works Association for Disinfecting Water Mains prior to putting into service. Provide our office with a copy of the documentation that demonstrates compliance with the above requirements. We recommend coordination of the plan to disinfect water mains prior to construction to ensure that we agree with the disinfection and testing method.
11.4 HAZARDOUS MATERIALS
All hazardous chemicals (including paint, cleaning solutions, solvents and so on) used by the contractor must be registered with the Maxwell AFB Hazardous Material
Manager, which can be contacted at 953-5260.
REFER TO SPECIFICATION SECTION 01001 ENVIRONMENTAL
PROTECTION EXHIBIT L
12.0 EXCAVATION
Prior to excavating for any purpose, the Contractor shall obtain an approved Construction
Permit, AF Form 103 (dated July 1982), from the 42CES/CE, 400 Cannon Street, Maxwell
Air Force Base. The purpose of this form is to give the Contractor clearance to excavate a given area, to protect the underground facilities, and to protect personnel from injury. The
Government will determine what facilities are beneath the surfaces and discuss their locations with the Contractor prior to issuing the AF Form 103. The Contractor is required to
GENERAL REQUIREMENTS 01000-6
determine the exact location to be excavated in relation to the underground facilities prior to excavating. The AF Form 103 may note cable, pipe, etc., in the area; if this occurs, Contractor will be responsible for digging in such a manner so as not to damage the hidden facility. Contractor will place particular emphasis on the site inspection prior to proposing to determine which facilities are obviously in the area. After receipt of the approved AF Form
103, the Contractor will not perform any excavation work without specific approval by the
Contracting Officer.
13.0 GROUND FAULT CIRCUIT INTERRUPTERS
Whenever the Contractor uses portable electrical tools or equipment in an outside location or in an interior wet location where floor is conductive such as concrete, the Contractor shall provide and use a portable ground fault circuit interrupter (GFCI). This shall apply wherever electric power is supplied through Government-controlled facilities. The Contractor shall be responsible for maintaining the GFCI in operating condition and testing it before each use.
14.0 EQUIPMENT OPERATING, MAINTENANCE, AND REPAIR MANUALS
14.1 1 copy of each manual shall be submitted for approval to the Contracting Officer.
The submittal schedule shall be as shown on the submittal register. Each manual shall include the following:
14.1.1 The manuals shall be bound in a 3-ring binder with a hard cover, or 3-hole portfolio for small projects. The following identification shall be inscribed on the cover: "EQUIPMENT OPERATING, MAINTENANCE, AND REPAIR MANUAL" and the building name and number, location, and indication of utility or system covered. Manuals shall be approximately 8 1/2 by 11 inches with large sheets folded in and capable of being easily pulled out for reference.
14.1.2 A warning page shall be provided to warn of potential dangers (it they exist), such as high voltage, toxic chemicals, flammable liquids, explosive materials, carcinogens, or high pressures. The warning page shall be placed inside the front cover, in front of the title page.
14.1.3 The title page shall show the name, address and phone number of the
Contractor, the contract number and the date of publication.
14.1.4 Provide a table of contents in accordance with standard commercial practice.
14.1.5 Performance sheets and graphs showing capacity data, efficiencies, electrical characteristics, pressure drops, and flow rates. Marked-up catalogs or catalog pages do not satisfy this requirement. Performance information shall be presented as concisely as possible and contain only data pertaining to equipment actually installed.
14.1.6 Operation and maintenance requirements. Include adequate illustrative material to identify and locate operating controls, indicating devices and
GENERAL REQUIREMENTS 01000-7
locations of areas or items requiring maintenance. Describe, in detail, starting and stopping procedures for components, adjustments required to obtain optimum equipment performance, and corrective actions for malfunctions. Maintenance instructions describing the nature and frequency of routine maintenance and procedures to be followed. Indicate any special tools, materials, and test equipment that may be required.
14.1.7 Repair information including diagrams and schematics, guidance for diagnosing problems, and detailed instructions for making repairs.
Provide trouble-shooting information that includes a statement of the indication or symptom of trouble and the sequential instructions necessary.
Include test hookups to determine the cause, special tools, and test equipment, and methods for returning the equipment to operating conditions. Information may be in chart form or in tabular format with appropriate headings.
14.1.8 Parts list, names and addresses of the two closest parts supply agencies.
14.1.9 Names and addresses of the local manufacturer representatives and the parent company.
15.0 OTHER EQUIPMENT
The Contractor will be required to furnish a brochure, catalog cut sheet, parts list, manufacturer's spec sheet, and/or other printed information that shows detailed parts data, and the manufacturer's name, address, and telephone number, for all other equipment (such as hardware, lighting fixtures, etc.) subject to repair or maintenance procedures. The data shall be furnished in three (3) copies (for each building) to the C.O. at the final inspection.
This requirement is in addition to the requirements for material submittals specified elsewhere in this contract. Information submitted as a part of "Equipment Operating, Maintenance, and Repair Manuals" will be considered a part of this requirement.
16.0 FIRE REGULATIONS
The Contractor shall comply with all aspects of the National Fire Protection Association
(NFPA) publication 241, "Safeguarding Building Construction, Alteration and Demolition
Operations; EM 385-1-1, Safety and Health Requirements Manual; and Maxwell AFB
Instruction 32-2005, Fire Prevention and Protection During Construction, Alteration, Demolition, and Repair Operations.
17.0 ASBESTOS
No friable asbestos containing materials will be installed as a part of this contract. Spray application of asbestos or asbestos-containing materials to exposed walls, ceilings, ducts, columns, etc. is prohibited. In the event friable asbestos containing materials are encountered during "rip out" and demolition operations, the Contractor shall stop work immediately and notify the TM/Contract Administrator who will take appropriate action.
REFER TO SPECIFICATION SECTION 01001 ENVIRONMENTAL
PROTECTION EXHIBIT L
GENERAL REQUIREMENTS 01000-8
18.0 INTENT OF DRAWINGS
All drawings are diagrammatic and are intended to qualify the materials specified and indicate their intended relationship to each other. The drawings are not to be scaled; rather field conditions should dictate placement. The various scales used on the drawings may not allow the indications of all fittings, offsets, and accessories that may be required. The Contractor is to carefully investigate the conditions that would affect the work to be performed and shall arrange such work accordingly.
19.0 AS-BUILT DRAWINGS
The Contractor shall provide to the Government marked drawings commonly referred to as
"as-builts" indicating conditions that differ from that shown on the contract plans. The
Contractor will review with the CO the "as-builts" as needed to ensure an accurate up-to-date set of documents is being kept. Changes are to be noted as the work progresses. The
Contractor will utilize a government-furnished copy of the contract drawings with the changes neatly indicated in red using the drafting standards and legends indicated in the contract drawings. One copy is required and will be submitted to the CO at the final inspection. If there are no changes, a title sheet (from the contract drawings) will only be required with the note "NO CHANGES" marked appropriately.
If it is performance specification and the contractor is doing the layout of the facility infrastructure, they need to furnish AutoCAD drawing for approval prior to construction and
Auto Cad AS BUILT DRAWINGS at the end of the project. The drawings will be delivered in a useable electronic format as an AutoCAD “.dwg” file, 2024 or greater
20.0 GEOSPATIAL DELIVERABLES
This defines the required geospatial deliverables for all work performed under this requirement on Maxwell and Gunter Annexes that affects or interacts with linear structures
(e.g., roads, sidewalks, utility lines, fences) and building features (e.g., building footprints, entryways, attachments). The Contractor shall capture, update, and provide accurate geospatial data to improve the quality of existing data layers related to these features within the Government's Geographic Information System (GIS).
The Contractor shall provide geospatial data that reflects the "as-is" conditions of linear structures and building features that are impacted by the work performed under this requirement. To include:
New construction or demolition.
Modifications to existing exterior structures.
Relocation or installation of utilities.
Changes in building footprints or site features.
Data Requirements:
Data Format:
All geospatial data shall be delivered in Geo Database (Aprx.) or ESRI Shapefile format
(.shp, .shx, .dbf, .prj). The use of other file formats must be approved by the Government in advance.
Coordinate System:
GENERAL REQUIREMENTS 01000-9
Data shall be projected in State plane coordinate system (NAD83 datum) or WGS 1984 UTM
Zone 16N_1. Failure to adhere to the appropriate coordinate system will result in rejection of the delivery.
Date of Data Capture/Update:
The date the feature was surveyed or updated.
Data Source:
Specify the method and data source used to capture or update the feature (e.g., GPS survey, aerial imagery, CAD drawing).
Condition:
Assessment of the current condition of the feature (e.g., "Good," "Fair," "Poor").
Accuracy Standards:
The data shall meet or exceed +/- 1 foot horizontal accuracy
All linear structures and building features impacted by the work shall be captured.
The Contractor is responsible for implementing a QC/QA process to ensure the accuracy, completeness, and consistency of the geospatial data.
Metadata:
The Shapefile must include a completed metadata file to include (.shp, .shx, .dbf, .prj) files.
Government Furnished Information (GFI):
The Government will provide the Contractor with access to existing geospatial data layers for Maxwell and Gunter Annexes as GFI.
Acceptance Criteria:
Geospatial deliverables will be accepted by the Government upon verification that they meet the requirements outlined in this section, including format, attribute data, accuracy, and completeness.
The Government will review the submitted data for compliance with the requirements outlined in this section. Data that does not meet these requirements will be returned to the
Contractor for correction.
Delivery:
The data delivery method that will be acceptable is digital transfer or disk drives. Delivery to be made to the GeoBase manager.
21.0 TRAFFIC CONTROL
The Contractor shall always be responsible for the orderly handling of traffic through the work during the life of the construction contract. This shall be accomplished in conformity with Sub article (d). "HANDLING OF TRAFFIC," of Article 104.04, "Sequence of
Construction for Handling Traffic Through the Work and Construction and Maintenance of
Detours," of Section 104, "SCOPE OF WORK," of the Alabama Highway Department
"Standard Specifications for Highway Construction," 1992 Edition. In this specification, the word "Engineer" Shall be replaced with the words CO.
22.0 CONTRACTOR MAINTENANCE
At the end of each working day the Contractor shall clean up the work site which includes the construction area(s), construction office area(s), material storage area(s), parking and eating area(s), and any other area(s) affected by the construction process. Stacked material shall not be within 8m (25-feet) of an active roadway. Tracking of soil, mud or other construction debris or substances on any Base Street, parking area, sidewalk, patio, driveway, GENERAL REQUIREMENTS 01000-10 turf, or other area shall not be permitted. The Contractor shall keep all turfed areas mowed and clean within the construction limits, and shrubs and other elements in the landscape shall be maintained.
23.0 ENVIRONMENTAL PROTECTION
REFER TO SPECIFICATION SECTION 01001 ENVIRONMENTAL PROTECTION
EXHIBIT L
24.0 ENVIRONMENTAL RELEASE REPORTING
An environmental release report shall be completed for all environmental releases that are caused by an Air Force activity, or which occur on an Air Force installation or facility.
Examples of environmental releases are listed as follows but not limited to oil releases to navigable waters, hazardous substance release above the reportable quantity, vinyl chloride releases, excessive emissions over amount allowed in permits, hazardous material incidents occurring during transportation, underground storage tank spills and releases, and any emergency incidents of environmental contamination. The Contractor shall immediately notify the TM/Contract Administrator in the event of any environmental release. The following information shall be documented with the time, type, amount, and cause of release.
25.0 PROTECTION OF EXISTING LANDSCAPE DURING CONSTRUCTION
REFER TO SPECIFICATION SECTION 01001 ENVIRONMENTAL PROTECTION
EXHIBIT L
26.0 REPAIR OR REPLACEMENT OF DAMAGED LANDSCAPE
The following requirements shall be observed by the Contractor to protect existing landscape
(to include trees, shrubs, flowers, turf, flower beds, sidewalks, patios, fences, etc.) during construction operations.
If there is any failure to comply with this General Requirements Section or any other
Contract Specification or provision or term of this contract occurs during installation, maintenance, or warranty, the Contractor shall be held responsible. The repair work shall be inspected and accepted by the Government. Any discrepancies shall be fixed before acceptance.
26.1 The following requirements shall be observed by the Contractor to protect existing landscape (to include trees, shrubs, flowers, turf, flower beds, sidewalks, patios, fences, etc.) during construction operations.
26.2 No vehicle parking is allowed under canopies or within the drip-line root zone of protected trees. All trees are to be protected unless they are shown to be removed on the plans.
26.3 No storage of materials will be allowed under protected tree canopies or beside existing shrub plantings.
26.4 No storage of materials on turf areas shall be allowed unless the has given the
Contractor approval. If any lawn damage occurs (even with special permission), the
Contractor shall restore the lawn per
GENERAL REQUIREMENTS 01000-11
26.5 No driving across, parking, or other equipment operations on existing turf shall be permitted unless prior approval has been obtained from the TM/Contract
Administrator. If any lawn damage occurs (even with special permission), the
Contractor shall restore the lawn per par. 25.02.2.4.05 below.
26.6 No pruning or breaking off existing trees or shrubs shall be permitted unless prior approval has been obtained from the TM/Contract Administrator. If prior approval is not obtained, the Contractor is liable for the repair/replacement of any damaged landscape items.
26.7 No work shall damage the health of any tree whose roots extend into the construction area. No fences, ropes, cables, signs, or devices of any kind shall be attached to any tree.
26.8 The TM shall be notified immediately of any damage occurring to a tree in the construction site, or any tree damaged by Contractor personnel. The TM/Contract
Administrator shall take direct measures, if any, to treat the injury. The Government shall incur no cost for any corrective measures, including, but not limited to, removal and replacement of the tree.
26.9 If the Contractor causes the death or 60% decline to any protected tree(s) within a
24-month period, the Contractor shall remove and replace the damaged tree(s) with size and species of tree(s) directed by the TM. The size of the new tree(s) shall equal caliper size of removed tree(s).
26.10 Damaged turf areas shall be replaced with sod. The use of grass seed to repair turf damage at Maxwell AFB or Gunter Annex is not permitted.
27.0 STAGING AREA
The Contractor will be provided space as indicated for an office trailer and a 6’ wood fence with lockable gates around the staging of materials in support of this project and must provide protection and security for it in that area.
28.0 TESTING
Where specific tests are required by this contract, the Contractor shall notify the CO at least
24 hours prior to testing. The Contractor shall turn in a test report, if required, to the
TM/Contract Administrator as soon as possible. The Contractor shall not proceed with any work that would cover up the work being tested until the TM/Contract Administrator has approved the work being tested.
29.0 WARRANTIES
All workmanship, materials, and equipment shall be under warranty for at least one year as set forth in the contract clause entitled "Warranty of Construction" (FAR 52.246-21). See specs for warranties extending beyond the one-year period.
30.0 PROTECTION OF GOVERNMENT PROPERTY AND PERSONNEL
WORK AREAS INCLUDED:
GENERAL REQUIREMENTS 01000-12
30.1 Construction site: Area or areas in which the work of the contract is accomplished or performed.
30.2 Storage areas: Area or areas used for the storage of materials, devices, appliances, and equipment to be used in the work.
30.3 Office and shed areas: Area or areas for placing or setting of temporary field office, tool sheds, or storage sheds.
30.4 Transportation areas: Area or areas that are defined as streets, roads, driveways, parking areas, etc., paved, treated, and unpaved; area or areas not paved, such as grass plots or grass areas used for transportation purposes.
31.0 CONDUCT OF WORK
The Contractor shall conduct work so the Government property and personnel, other personnel, and work areas shall be protected at all times from inconvenience, damage of any nature, or injury caused by this work until completion of the contract.
32.0 REPAIR OR REPLACEMENT OF DAMAGED PROPERTY
In the event of damages of any nature caused by this work (including maintenance and warranty operations) due to improper protection, precaution, or safety measures, such damages shall be repaired or such property shall be replaced by the Contractor at no expense, cost, or charge to the Government. In the event the Contractor does not satisfactorily repair or replace such damage caused by the work of the contract, the Government reserves the right to make the necessary corrections and deduct from the contract price the cost to the
Government for inconveniences, labor material, etc. involved. Reference contract clause
"Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements"
(FAR 52.236-9).
33.0 BARRICADES
The Contractor shall furnish, place and maintain all required barricades as directed by the
Safety Office and the TM/Contract Administrator, and access driveways and doors will always remain clear.
34.0 FINAL CLEANING
Execute final cleaning prior to the final inspection.
34.1 Clean surfaces exposed to view.
34.2 Remove temporary labels, stains, and foreign substances; polish transparent and glossy surfaces; wet mop tile or sealed concrete floors, vacuum carpeted floors, broom clean other floors.
34.3 Clean equipment and fixtures to a sanitary condition.
34.4 Clean or replace filters of mechanical equipment.
34.5 Any additional cleaning as specified in other sections.
34.6 Clean sites of all construction related and project related debris.
34.7 Remove waste and surplus materials, rubbish, and construction facilities from the work areas and the site.
GENERAL REQUIREMENTS 01000-13
35.0 CLOSEOUT PROCEDURES
When the Contractor is ready for final inspection, the Contractor shall notify the CO (in writing) within two (2) working days of the desired inspection date. During the inspection, the Contractor and the CO shall document all deficiencies on a "punchlist." The CO will provide a formal copy of the punchlist to the Contractor. The Contractor shall be responsible for correcting all punchlist items prior to the end of the contract completion date and notify the CO (in writing) when the contractor is ready for re-inspection.
36.0 SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS
37.0 The Contractor shall notify 42 SFS/SPAI, Maxwell AFB AL, no later than 10 days after contract award. The notification shall include:
37.1 Name, address, and telephone number of each company representative.
37.2 The contract number and contracting agency (e.g., 42 CONS/PKC).
37.3 The description of the work to be performed/construction project number.
37.4 The location(s) of the construction work (i.e., street address or other description of the construction site).
37.5 The date contract performance begins.
37.6 Any updates to information previously provided under this paragraph.
38.0 LIST OF EMPLOYEES
The Contractor shall maintain a current listing of employees. The list shall include employees’ names, social security number, and level of security clearance (if contract work involves unescorted entry to Air Force restricted or other sensitive areas designated by the installation commander). The list shall be validated and signed by the company Facility
Security Officer (FSO) and provided to the TM/Contract Administrator, Maxwell AFB, AL, prior to the contract start date. An updated list shall be provided when an employee's status or information changes. 42 CONS/PKC will brief specific instructions during the
Preconstruction Conference
39.0 PASS AND IDENTIFICATION
The Contractor shall obtain the following pass and identification items:
39.1.1 DD Form 1172, "Application for Uniformed Services Identification Card"
(AFI 36-3001 and AETCR 30-1). Forms shall be supplied by the
Contracting Office Customer Service Station. The Contractor shall fill out the forms and take them to Pass and Identification, Building 502, 10 North
Pine Street, Maxwell AFB.
39.1.2 AETC Form 58, "Civilian Identification Card" (AETCR 30-1). Pass and
Identification will issue this to each Contractor employee.
39.1.3 AF Form 2219 (series), "Registered Vehicle Expiration Tab", (AFI 31-
204), "Motor Vehicle Traffic Supervision" and DD Form 2220, "DOD
Registered Vehicle and Installation Tab" (AFI 31-204). The Security
GENERAL REQUIREMENTS 01000-14
Forces, Pass and Registration Section, building 502, 10 North Pine Street
(at the Maxwell Boulevard entrance) will issue vehicle registration decals, upon proof of employment, insurance, ownership of vehicle, and a valid driver's license. A temporary decal will be issued if employment is for six months or less.
39.1.4 AF Form 1199, USAF Restricted Area Badge, or a locally developed badge (if applicable).
39.1.5 AF Form 75, Visitor/Vehicle Pass (AFI 31-204)
The Contractor shall retrieve all identification media, including vehicle decals from employees who depart for any reason before the contract expires (e.g., terminated for cause, retirement, etc.)
40.0 PHYSICAL SECURITY; KEY CONTROL; LOCK COMBINATIONS &
CONTROLLED/RESTRICTED AREAS
Physical security. The Contractor shall be responsible for safeguarding all Government property and controlled forms provided for the Contractor's use. At the end of each work period, all Government facilities, equipment, and materials shall be secured. The Contractor shall be also responsible for the security of his own facilities, equipment, and material.
40.1 Key control
40.1.1 The Contractor shall establish and implement methods of making sure all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. The following shall apply:
40.1.2 The Contractor shall not duplicate any keys issued by the Government
40.1.3 The Contractor shall immediately report any occurrences of lost or duplicated keys to the Government.
40.1.4 In the event of lost or duplicated keys, the Contractor may be required, upon written direction of the Government, to re-key or replace the affected lock or locks without cost to the Government. The Government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from payment due the Contractor. In the event a master key is lost or duplicated, the Government shall replace all locks and keys for that system and the total cost deducted from payment due the Contractor.
40.1.5 The Contractor shall prohibit the use of Government issued keys by any persons other than the Contractor's employees and the opening of locked areas by Contractor employees to permit entrance of persons other than
Contractor employees engaged in performance of contract work requirements in those areas.
40.2 Controlled/Restricted Areas: The Contractor shall implement local Base procedures for entry to Air Force control/restricted areas where Contractor personnel will work.
GENERAL REQUIREMENTS 01000-15
40.3 Lock combinations: The Contractor shall control access to all Government-provided lock combinations to preclude unauthorized entry.
41.0 OPERATING INSTRUCTION
If applicable, the Contractor shall develop an OI for internal circulation control, protection of resources, and regulated entry into Air Force controlled areas during normal, simulated, and actual emergency operations. The OI shall be coordinated through 42 SFS/SPAIR located at
130 W. Selfridge Street, Maxwell AFB, and shall be written in accordance with AFI 31-209
("Air Force Resource Protection Program"), the local Base Operations Plan, and AFI 31-210
("Anti-Terrorism Program").
42.0 REPORTING THREATS TO SECURITY
The Contractor shall comply with the requirements of AFI 71-101V1, "Counterintelligence
Awareness and Briefing Program." Contractor personnel shall report to an appropriate authority any information or circumstances of which they are aware that may pose a threat to the security of DOD or Contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment.
43.0 WEAPONS, FIREARMS, AND AMMUNITION
Contractor employees are prohibited from possessing weapons, firearms, or ammunition on themselves or within Contractor-owned or privately owned vehicles while on Maxwell AFB or Gunter Annex.
44.0 TRAFFIC LAWS
All Contractor personnel shall comply with Base traffic regulations.
45.0 SUITABILITY INVESTIGATIONS
Contractor personnel shall successfully complete, as a minimum, National Agency Check
(NAC), before operating government furnished workstations that have access to Air Force e-mail systems. These investigations shall be submitted by the government at no additional cost to the contractor. The contractor shall comply with the DOD 5200.2-R, Personnel
Security Program, and AFI 33-119, Electronic Mail (E-Mail) Management and Use, requirements.
46.0 REQUIRED INSURANCE
46.1 Reference FAR clause 52.228-5 entitled “Insurance...” the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
46.2 Workmen’s Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen’s
GENERAL REQUIREMENTS 01000-16
Compensation insurance shall extend to cover employer’s liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of
$100,000.
46.3 General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of the policy.
46.4 Automobile Liability Insurance. The insurance shall be required on the comprehensive form of policy and shall provide bodily and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000, per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required. This insurance shall cover the operation of automobiles by Contractor employees and authorized Government employees and third parties.
47.0 CLAUSES AND PROVISIONS
Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.
47.1 Even though most of the clauses and provisions are incorporated by reference, some clauses and provisions are required to be completed and submitted by the offeror with offer. The full text of the clauses and provisions may be seen at https://www.acquisition.gov/
47.2 Clauses and provisions in this document will be numbered in sequence.
47.3 Sections K, L and M will be physically removed from any resultant award, but will be deemed to be incorporated, by reference, in that award.
48.0 SMOKING IN FACILITIES
Contractors are advised that the Commander has placed restrictions on the smoking of tobacco products in AETC facilities. AFI 40-102, Tobacco Use in the Air Force, and its
AETC supplement 1, outline the procedures used by the commander to control smoking in our facilities. Contractor employees and visitors are subject to the same restrictions as government personnel. Smoking is permitted only in designated smoking areas.
49.0 INSPECTION AND ACCEPTANCE
42 CES/CEN is designated as the office responsible for inspecting the work while the CO is responsible for final acceptance of the work.
END OF SECTION
https://www.acquisition.gov/
BUS
STOP
B U S
STO
P
North Turner Blvd.
South Turner Blvd.
Butler Ave
McCrackin Ave
Ct
Pitsenbarger
Hodges Ave
S pa a tz S t
O gden C ourt
Libby St
R enfroe S treet
Butler Ave
Burge Ct.
S pa a tz S t
T im berla ke
S t
W a rd S t
V osler C t
Smith St
Morris Ave
M cDonald St
W illiamson St
Erwin Ct
Morris Avenue
Galbraith Mill Creek
C
SX
R A
ILR
O A D
Libby St
Morris Avenue
C om puter L oop D rive
F isher D rive
C omputer Loop Drive
W est M oore D rive
Ramp Road
Sneed R oad
Fisher Drive
F isher D rive
Butler Ave
S pa a tz S t
Ramp Road
S need R oa d
Computer Loop Drive
Butler Ave
Heritage Loop
E M oore Drive
E M oore Drive
PRO
JECT LO
CATIO
N
S
APPEN
DIX 1
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text T
AutoCAD SHX Text
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text E
AutoCAD SHX Text
AutoCAD SHX Text Wall
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
PLAYGROUND
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text S852
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text Persons Drive
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text X
AutoCAD SHX Text Persons
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
GATE
AutoCAD SHX Text
GATE
ENVIRONMENTAL PROTECTION 01001 Page 1 of 16
SECTION 01001
EXHIBIT L
ENVIRONMENTAL PROTECTION
October 2025
PART 1 GENERAL
1.0 DESCRIPTION
The work covered by this section consists of furnishing all labor, materials, and equipment and performing all work required for the prevention of environmental degradation during and as a result of construction operations under this contract. These requirements are in addition to any environmental protection requirements elsewhere in these specifications.
For the purpose of this specification, environmental pollution is defined as the presence of chemical, physical, or biological elements or agents, not naturally occurring at the site, which adversely affect human health or welfare; unfavorably alter ecological balances;
negatively affect plant or animal species; or degrade the utility of the environment for aesthetic and recreational purposes. The control of environmental pollution by the contractor requires consideration of air, water, and land, and involves noise control, solid waste management and management of radiant energy and radioactive materials, as well as other pollutants. This section also requires the protection of natural, cultural and historic resources.
1.1 ACRONYMS AND DEFINITIONS
ADEM – Alabama Department of Environmental Management CAA – Clean Air Act CO – Contracting Officer CERCLA – Comprehensive Environmental Response, Compensation and Liability Act CWA – Clean Water Act EPA – Environmental Protection Agency MAFB – Maxwell Air Force Base and Gunter Annex. Throughout this environmental protection section, MAFB (including Gunter Annex) may commonly be referred to as the base or installation.
Media – Any soil, water, or air that is moved, disturbed, or released from a site OSHA – Occupational Safety and Health Administration TM – Technical Manager RCRA – Resource Conservation and Recovery Act SDWA – Safe Drinking Water Act TSCA – Toxic Substances Control Act 42 CES/CEIE – Maxwell Air Force Base Civil Engineering Squadron, Environmental Section. Throughout this environmental protection section, this office will commonly be referred to as the “installation environmental office.”
The terms hazardous, waste, pollutant, contaminant, and substance have the same meanings and usage here as they commonly do in the CAA, CERCLA, RCRA, SDWA, and TSCA.
ENVIRONMENTAL PROTECTION 01001 Page 2 of 16
1.2 CONTRACTOR’S GENERAL ENVIRONMENTAL COMPLIANCE OBLIGATIONS
1.2.1. Work under this contract is to be performed on a government facility. All environmental rules applying to contractor operations elsewhere shall also apply on the government facility. Contractor (and any of their additional contractors, agents or representatives) shall comply with all applicable Federal, State, and local laws and regulations providing for environmental protection and pollution control and abatement. These include but are not limited to: the Clean Air Act, Clean Water Act, Resource Conservation and Recovery Act, Comprehensive Environmental Response, Compensation and Liability Act, Toxic Substances Control Act, Federal Insecticide Fungicide and Rodenticide Act, Coastal Zone Management Act, Endangered Species Act, Migratory Bird Treaty Act, National Historic Preservation Act, Archeological Resources Protection Act, Safe Drinking Water Act, Emergency Planning and Community Right-to-Know Act, Oil Pollution Act, and Pollution Prevention Act. Contractor has the duty to determine for himself/herself where such laws and regulations apply. Although the contractor may request assistance from the TM/Contract Administrator or the installation environmental office in delineating applicable environmental laws and regulations, contractor has an independent responsibility to make its own determination and to do so in a timely fashion. Environmental Management System (EMS) significant aspect is Hazardous Waste Compliance. Please ensure all personnel are aware of applicable RCRA requirements and have reviewed the Commander’s Policy at the end of this section.
1.2.2. Contractors are responsible to implement their own environmental compliance programs, to ensure that individuals working at the site are properly trained and aware of potential hazards and proper operating procedures, and to ensure that all personnel follow the guidelines of OSHA, EPA, ADEM, and the Air Force’s policies, in addition to any…