GOGA - 149952 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS – 2A
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS - 2A
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
1.2 DEFINITIONS
A. Unit price: a price per unit of measurement for materials and services necessary to perform the Work defined below and in the Contract Documents, include all necessary material, cost for delivery, protection, engineering & testing, access, installation, insurance, supervision, overhead, and profit.
1.3 PROCEDURES
A. Payment for unit price work will be made only for the actual quantities of work installed.
B. For each unit price the approved Schedule of Values will establish defined subtasks and an associated percentage completion of the unit price work in order to receive partial payment of unit price items.
C. The Contracting Officer reserves the right to reject Contractor’s measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government’s expense, by an independent surveyor mutually acceptable to the Government and Contractor.
D. The Line Item descriptions of work below are in outline form and are intended only to present an overview of the of the work included under each item.
PART 2 - PRODUCTS (Not Used)
PART 3 - LIST OF CONTRACT LINE ITEMS
3.1 CONTRACT LINE ITEM NO. 1: GENERAL REPAIRS
A. Contract Line Item No. 1 Includes the Following: Mobilization, Demobilization, General Conditions, Exterior Wall Painting, Roofing On Parapet Wall, View Port Repair, Floor Vent Repair, Floor Vent Replacement, Parapet Replacement, Additional Supplemental Structural Reinforcement, Repair Of Exterior Stairs, Impressed Current Cathodic Protection, Window And Door Repairs (All Types), Interior Cement Plaster Repairs - Furred And Parged Systems, GOGA - 149952 01 27 00 - 2
Ceramic Tile Repairs, Interior Painting Pilaster Strengthening, and all other work not defined in other Line Items. An outline summary of the work included, and unit of measure for each item follows:
1. Mobilization & Demobilization:
a. The work for this item consists of onetime tasks needed to setup and support the overall work and onetime tasks needed to close out the project, demobilize and move off of the site. Examples include, but are not limited to:
1) Visual barriers and setup of staging areas
2) Temporary offices
3) Gull exclusion netting and Protection of Natural Features
4) Temporary roof access stairs
5) Initial installation of scaffold
6) Initial setup for water & power facilities
7) Worker orientations
8) Installation of visitor and staff protection measures
9) Relocation/protection of benches and other
b. No separate measurement of quantities will be made
2. General Conditions
a. The work for this item consists of tasks needed to support the overall project but not specifically associated with and single Line Item, such as:
1) Scaffold rental cost
2) Maintenance of Temporary Facilities
3) Daily transport of crew to the island
4) Delivery and storage of water
5) Provisions to supply power for the work
6) Submittals and mockups
7) Supervision
8) Coordination
b. No separate measurement of quantities will be made
3. Paint Removal and Repainting of Exterior Concrete Walls & Historic Fixtures
a. This work for this item consists of removing and disposing of the paint coatings, including lead based paint on the exterior concrete walls and attached historic fixtures, and preparing and repainting the historic fixtures and the walls with a new coating. The work includes, but is not limited to, the following:
1) Protection
2) Inspection and documentation
3) Removal of abandoned bird netting anchors per 3/S504
4) Coating removal and disposal of lead based paint
5) Cleaning and preparing substrates for painting
6) Installing new coating systems
7) Repair of defects
8) Clean up
b. No separate measurement of quantities will be made
4. Roofing Work on Parapet Wall
a. The work for this item consists of roofing work on the inside face of the roof parapet wall. Patching concrete is not included in this line item. The work includes, but is not limited to, the following:
1) Protection & shoring
2) Temporary support and protection of conduit and other utilities attached to parapet, GOGA - 149952 01 27 00 - 3
3) Removal and disposal of all roofing layers on parapet including top, inside face, and top of cornice. Roofing on the back wall face of the parapet contains asbestos,
4) Removal of roofing adjacent to parapet of wall,
5) Removal, repair and reinstallation of light support brackets
6) Installation of new roofing and flashings
7) Installation of bird deterrent system
8) Repair of defects
9) Clean up and disposal of waste materials
b. No separate measurement of quantities will be made.
5. View Port Repair:
a. The work for this item consists all work needed to repair existing view ports per 2/S506 including but not limited to:
1) Protection
2) Remediation of hazardous materials
3) Cutting, patching and repair of adjacent finishes
4) Dismantling components
5) Repair or replacement of deteriorated, damaged or missing components
6) Adjustment and alignment of doors
7) Paint removal and repainting
b. The unit of measure will be each view port. The base contract amount is 0 view ports.
6. Floor Vent Repair
a. The work for this item consists all work needed to repair existing floor vents per
3/S506 including but not limited to:
1) Protection
2) Remediation of hazardous materials
3) Cutting, patching and repair of adjacent interior finishes, exterior wall patching is not included in this line item
4) Dismantling components
5) Repair or replacement of deteriorated, damaged or missing components
6) Adjustment and alignment of deformed or inoperable components
7) Installation of replacement components
8) Paint removal and repainting
9) Cleanup and disposal of waste materials
b. The unit of measure will be each floor vent. The base contract amount is 0 floor vent.
7. Floor Vent Replacement
a. The work for this item consists all work needed to repair existing floor vents per
4/S506 including but not limited to:
1) Protection
2) Remediation of hazardous materials
3) Cutting, patching and repair of adjacent interior finishes, exterior wall patching is not included in this line item
4) Dismantling components
5) Repair or replacement of deteriorated, damaged or missing components
6) Adjustment and alignment of deformed or inoperable components
7) Installation of replacement components
8) Paint removal and repainting
9) Cleanup and disposal of waste materials
GOGA - 149952 01 27 00 - 4
b. The unit of measure will be each floor vent. The base contract amount is 0 floor vent.
8. Parapet Replacement
a. The work for this item consists of installing full thickness concrete patches at parapet locations per 1/S501, and 2/S503. The work includes incorporating galvanic anodes into the patches. The work includes, but is not limited to, the following:
1) Protection & supporting/rerouting water and power
2) Protection of Rooftop PV systems
3) Inspection
4) Concrete removal
5) Concrete and embedded steel surface preparation
6) Anticorrosion coating
7) Installation of dowels
8) Installation of supplemental reinforcing bars
9) Installation of galvanic anodes
10) Concrete installation and finishing
11) Repair of defects
12) Curing
13) Clean up and disposal of waste materials
b. Measurement will be made on a lineal foot basis. The base contract amount is 5 feet.
9. Added Supplemental Structural Reinforcement
a. The work for this item consists of installing supplemental structural reinforcing bars within all types of concrete patches per 1/S501, and 4/S504. Patch reinforcing such as wire mesh, hairpin anchors and small diameter anchors required in the basic patch types (i.e. Type E patches, Type F patches etc.) is not included in this line item. The cost for the concrete demolition, surface preparation etc. is included under other line items. The base price for added supplemental reinforcing includes materials, drilling and setting the new bars. The work includes, but is not limited to, the following:
1) Protection & shoring
2) Inspection
3) Installation of dowels
4) Installation of supplemental reinforcing bars
5) Repair of defects
6) Curing
7) Clean up and disposal of waste materials
b. Measurement will be made per lineal foot of bar. The base contract amount is 183 lineal feet.
10. Repair of Exterior Stairs to Recreation Yard.
1) This item consists of all work associated with repairing the exterior concrete stairs to the recreation yard as presented in Sheets S507 & S508, including but not limited to: Protection, coordinating alternate exit routes, removal of existing shoring, concrete demolition, rebuilding and patching concrete, removal and relocation of support strut, salvage & reinstallation of existing railings, clean up and disposal of waste material.
b. No separate measurement of quantities will be made.
11. Impressed Current Cathodic Protection System for West Pilasters
GOGA - 149952 01 27 00 - 5
a. This item consists of design build impressed current cathodic protection system for the exterior concrete pilasters on the west side of the building. The work includes, but is not limited to, the following:
1) System design for a minimum 30 year service life
2) Component fabrication
3) Installation of anodes including concrete saw cutting and patching
4) Testing
5) Installation of rectifiers and connection to power supply
6) Clean up and disposal of waste material
7) System adjustment
8) First year of service and warranty
b. No separate measurement of quantities will be made.
12. Impressed Current Cathodic Protection System for West Windows
a. This item consists of design build impressed current cathodic protection system for the window perimeters on the west side of the building. The work includes, but is not limited to, the following:
1) System design for a minimum 30 year service life
2) Component fabrication
3) Installation of anodes including concrete saw cutting and patching
4) Testing
5) Installation of rectifiers and connection to power supply
6) Clean up and disposal of waste material
7) System adjustment
8) First year of service and warranty
b. No separate measurement of quantities will be made.
13. Window Repair - Type 1
a. The Work for this item consists of installing Type 1 Window Repairs per the Window Schedule on Sheets A601 - A603, and per detail sheets A501 and A506.
Removal, repair and reinstallation of exterior bars is included in a separate line item. Repair of concrete around perimeter of window is included in separate line items. The work includes, but is not limited to, the following:
1) Protection
2) Removal and disposal of old storm windows, as applies.
3) Inspection
4) Removal of paint, including disposal of lead based paint, and repainting
5) Fabricating and installing custom fit aluminum storm windows
6) Clean up and disposal of waste material
b. Measurement will be made on a per window basis.
14. Window Repair - Type 2
a. The Work for this item consists of installing Type 2 Window Repairs per the Window Schedule on Sheets A601 - A603, and per detail sheets A501 and A502.
Removal, repair and reinstallation of exterior bars or interior bars, where shown, is included in a separate line item. Repair of concrete around perimeter of window is included in separate line items. The work includes, but is not limited to, the following:
1) Protection
2) Removal and disposal of old storm windows, as applies
3) Inspection
4) Removal of paint, including disposal of lead based paint, and repainting
5) Reglazing with salvaged and new glass
GOGA - 149952 01 27 00 - 6
6) Reconstructing severely corroded sills,
7) Restoring operability to vents,
8) Installing sealant joints
9) Clean up and disposal of waste material
10) Removing, repairing and reinstalling miscellaneous screens, fan housing etc, on exterior side of windows.
b. Measurement will be made on a per window basis.
15. Window Repair - Type 3
a. The Work for this item consists of installing Type 3 Window Repairs per the
Window Schedule on Sheets A601 - A603, and per detail sheets A501 and A503.
Removal, repair and reinstallation of exterior bars or interior bars, where shown, are included in a separate line item. Repair of concrete around perimeter of window is included in separate line items. The work includes, but is not limited to, the following:
1) Protection
2) Removal and disposal of old storm windows, as applies
3) Inspection
4) Removal of existing window, including disposal of lead based paint
5) Patching window opening
6) Fabricating and installing custom fit steel window
7) Glazing
8) Painting
9) Installing sealant joints
10) Clean up and disposal of waste material
b. Measurement will be made on a per window basis.
16. Window Repair - Type 4
a. The Work for this item consists of installing Type 4 Window Repairs to stabilize existing hollow metal windows per the Window Schedule on Sheets A601 - A603.
Removal, repair and reinstallation of exterior bars or interior bars, where shown, are included in a separate line item. Repair of concrete around perimeter of window is included in separate line items. The work includes, but is not limited to, the following:
1) Protection
2) Removal and disposal of old storm windows, as applies
3) Inspection
4) Paint removal and repainting
5) Reglazing with salvaged and new glass
6) Restoring operability to sashes,
7) Installing sealant joints
8) Clean up and disposal of waste material
b. Measurement will be made on a per window basis.
17. Window Repair - Type 5
a. The Work for this item consists of installing Type 5 Glass Block Repairs per the Window Schedule on Sheets A601 - A603, and per detail sheet A504. Removal, repair and reinstallation of exterior bars or interior bars, where shown, are included in a separate line item. Repair of concrete around perimeter of window is included in separate line items. The work includes, but is not limited to, the following:
1) Protection
2) Shoring of glass block during the work
3) Removal and disposal of old storm windows, as applies
4) Inspection
GOGA - 149952 01 27 00 - 7
5) Removal of original window flange
6) New dowels at perimeter of glass block windows
7) Replacing damaged glass block
8) Repointing mortar joints
9) Repair and sealing of vents
10) Installing sealant joints
11) Clean up and disposal of waste material
12) Removing, repairing and reinstalling miscellaneous screens, fan housing etc, on exterior side of windows.
b. Measurement will be made on a per window basis.
18. Window Repair - Type 6
a. The Work for this item consists of installing Type 6 Glass Block Repairs per the
Window Schedule on Sheets A601 - A603, and per detail sheet A505. Removal, repair and reinstallation of exterior bars or interior bars, where shown, are included in a separate line item. The work includes, but is not limited to, the following:
1) Protection
2) Removal and disposal of old storm windows, as applies
3) Inspection
4) Dismantling and salvaging glass block
5) Removal of original window flange and concrete patching around perimeter of window
6) New dowels at perimeter of glass block windows
7) Replacing damaged glass block
8) Reinstalling new and salvaged glass block
9) Repair, reinstallation and sealing of vents
10) Installing sealant joints
11) Clean up and disposal of waste material
b. Measurement will be made on a per window basis.
19. Miscellaneous Window & Door Repairs
a. The Work for this item consists of installing repairs to miscellaneous doors per sheets A509 - 511. Removal, repair and reinstallation of exterior bars or interior bars, where shown, are included in a separate line item. Repair of concrete around perimeter of windows and doors is included in separate line items. The work includes, but is not limited to, the following:
1) Protection
2) Inspection
3) Documentation
4) Removal of paint, including disposal of lead based paint, and repainting
5) Replacing missing or broken components
6) Reglazing with salvaged and new glass
7) Restoring operability
8) Fabrication and installation of new bar door
9) Sealing vents
10) Installing sealant joints
11) Clean up and disposal of waste material
12) Removing, repairing and reinstalling miscellaneous screens, fan housing etc, on exterior side of windows or doors.
b. No separate measurement of quantities will be made
20. Repair of Interior Window Bars
GOGA - 149952 01 27 00 - 8
a. The Work for this item consists of removing and repairing interior window bars where shown in the Drawings per 4/A507. Repair of windows is included in separate Line Items. The work includes, but is not limited to, the following:
1) Protection
2) Inspection
3) Removal of paint, including disposal of lead based paint, and repainting
4) Dismantling and salvaging sound components for reinstallation
5) Fabrication and installation of replacement parts
6) Reinstallation of repaired bars
7) Clean up and disposal of waste material
b. Measurement will be made on a per window basis. The base contract amount is 4 windows.
21. Repair of Exterior Window Bars
a. The Work for this item consists of removing and repairing exterior window bars where shown in the Drawings per Sheet A507. Repair of windows is included in separate Line Items. The work includes, but is not limited to, the following:
1) Protection
2) Inspection
3) Removal of paint, including disposal of lead based paint, and repainting
4) Dismantling and salvaging sound components for reinstallation
5) Fabrication and installation of replacement parts
6) Reinstallation of repaired bars
7) Clean up and disposal of waste material
b. Measurement will be made on a per window basis. The base contract amount is 5 windows.
22. Interior Cement Plaster Repair - Furred System
a. The work for this item consists of repairing furred interior cement plaster finish as shown on Sheet S509. This line item does not include interior plaster repair associated with concrete wall patching and pilaster strengthening line items. The work includes, but is not limited to, the following:
1) Protection
2) Shoring of windows, as required
3) Inspection
4) Removal of interior finish
5) Installation of furring and support anchors
6) Installation of cement plaster and all accessories
7) Repair of defects
8) Curing
9) Clean up and disposal of waste material
b. Measurement will be made on a square foot basis.
23. Interior Cement Plaster Repair - Parged System
a. The work for this item consists of repairing interior cement plaster finish parged directly onto a concrete substrate as shown on Sheet S509. This line item does not include interior plaster repair associated with concrete wall patching and pilaster strengthening line items. The work includes, but is not limited to, the following:
1) Protection
2) Inspection
3) Removal of interior finish
4) Installation of lath and tie wires
5) Installation of cement plaster and all accessories
6) Repair of defects
GOGA - 149952 01 27 00 - 9
7) Curing
8) Clean up and disposal of waste material
b. Measurement will be made on a square foot basis. The base contract amount is 65 square feet.
c. Payment will be made at the contract unit price per square foot
24. Interior Ceramic Tile Repair
a. The work for this item consists of repairing interior ceramic tile finish set directly onto a concrete substrate. This line item does not include ceramic tile repair associated with concrete wall patching and pilaster strengthening line items. The work includes, but is not limited to, the following:
1) Protection
2) Inspection
3) Documentation
4) Removal and salvage of existing tile
5) Replacement of damaged tiles
6) Installation of tile including all accessories
7) Repair of defects
8) Curing
9) Clean up and disposal of waste material
b. Measurement will be made on a square foot basis.
25. Interior Painting
a. The work for this item consists of removing interior paint, including lead based paint, preparing substrates and installing new paint coatings on the interior walls.
This line item does not include painting associated with concrete interior wall patching and pilaster strengthening line items. The work includes, but is not limited to, the following:
1) Protection
2) Inspection
3) Removal and disposal of paint, including lead based paint
4) Surface preparation
5) Installation of new paint coatings
6) Repair of defects
7) Curing
8) Clean up and disposal of waste material
b. Measurement will be made on a square foot basis. The base contract amount is 1469 square feet.
26. Pilaster Strengthening
a. The work for this item consists of strengthening pilasters by adding retrofit concrete ties as shown on Sheets S513 - S515. The work includes, but is not limited to, the following:
1) Protection
2) Inspection
3) Removal of interior finish beyond the repair area as needed to perform concrete repair consistent with contractor’s means and methods
4) Removal and salvage of interior tile finishes
5) Removal of concrete
6) Installation of new ties and associated steel
7) Installation of concrete
8) Installation of the various interior wall concrete patches is addressed in separate Line Items
9) Repair and re-installation of interior finishes
GOGA - 149952 01 27 00 - 10
10) Repair of defects
11) Curing
12) Clean up and disposal of waste material
b. Measurement will be made on a per pilaster basis, first floor to roof. The base contract amount is 11 pilasters.
B. Measurement for Line Item 1, sub-items 1 - 26 will be made as described for each sub-item.
C. Payment for Line Item 1 will be made at the contract lump sum price.
3.2 CONTRACT LINE ITEM NO. 2: TYPE F CONCRETE PATCHES WITH GALVANIC
ANODES
A. The work for this item consists of installing Type F concrete patches per 1/S501 and 2/S501.
The base price includes incorporating galvanic anodes into the patches per Sheet S505. A separate price for Type F patches without galvanic anodes is required. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Installation of galvanic anodes as applies
7. Concrete installation and finishing
8. Repair of defects
9. Curing
10. Clean up and disposal of waste concrete
B. Measurement will be made on a square foot basis. The base contract amount for F patches with anodes is 1137 square feet.
C. Payment will be made at the contract unit price per square foot.
3.3 CONTRACT LINE ITEM NO. 3: TYPE F CONCRETE PATCHES WITHOUT GALVANIC
ANODES
A. The work for this item consists of installing Type F concrete patches per 1/S501 and 2/S501.
The base price excludes galvanic anodes. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Installation of ties
7. Installation of galvanic anodes as applies
8. Concrete installation and finishing
9. Repair of defects
10. Curing
GOGA - 149952 01 27 00 - 11
11. Clean up and disposal of waste materials.
B. Measurement will be made on a square foot basis. The base contract amount for F patches without anodes is 106 square feet.
C. Payment will be made at the contract unit price per square foot
3.4 CONTRACT LINE ITEM NO. 4: TYPE FT CONCRETE PATCH WITH GALVANIC
ANODES
A. The work for this item consists of installing Type FT concrete patches per 1/S501 and 3/S501.
The base price includes incorporating galvanic anodes into the patches per Sheet S505. The work includes, but is not limited to, the following:
1. Protection and shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Installation of ties
7. Installation of galvanic anodes as applies
8. Concrete installation and finishing
9. Repair of defects
10. Curing
11. Clean up and disposal of waste materials.
B. Measurement will be made on a square foot basis. The base contract amount for FT patches with anodes is 2 square feet.
C. Payment will be made at the contract unit price per square foot.
3.5 CONTRACT LINE ITEM NO. 5: TYPE FT CONCRETE PATCH WITHOUT GALVANIC
ANODES
A. The work for this item consists of installing Type FT concrete patches per 1/S501 and 3/S501.
The base price includes incorporating galvanic anodes into the patches per Sheet S505. A separate price for Type FT patches without galvanic anodes is required. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Installation of ties
7. Concrete installation and finishing
8. Repair of defects
9. Curing
10. Clean up and disposal of waste materials
B. Measurement will be made on a square foot basis.
GOGA - 149952 01 27 00 - 12
1. The base contract amount for FT patches without anodes is 66 square feet.
C. Payment will be made at the contract unit price per square foot.
3.6 CONTRACT LINE ITEM NO. 6: TYPE E CONCRETE PATCH WITH GALVANIC
ANODES
A. The work for this item consists of installing Type E concrete patches per 1/S501 and 4/S501, and 2/S503. The base price includes incorporating galvanic anodes into the patches per Sheet S505. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Installation of ties
7. Installation of galvanic anodes
8. Concrete installation and finishing
9. Repair of defects
10. Curing
11. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount for E patches with anodes is 255 lineal feet.
C. Payment will be made at the contract unit price per lineal foot.
3.7 CONTRACT LINE ITEM NO. 7: TYPE E CONCRETE PATCH WITHOUT GALVANIC
ANODES
A. The work for this item consists of installing Type E concrete patches per 1/S501 and 4/S501, and 2/S503. The base price excludes galvanic anodes. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Installation of ties
6. Concrete installation and finishing
7. Repair of defects
8. Curing
9. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount for E patches without anodes is 199 lineal feet.
C. Payment will be made at the contract unit price per lineal foot.
GOGA - 149952 01 27 00 - 13
3.8 CONTRACT LINE ITEM NO. 8: TYPE T CONCRETE PATCH
A. The work for this item consists of installing new hairpin ties and associated concrete patching per 1/S501 and 5/S501. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection & layout
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Installation of hairpin ties
6. Concrete patching and finishing
7. Repair of defects
8. Curing
9. Clean up and disposal of waste materials
B. Measurement: The hairpin ties are specified to be installed at specific spacing, measurement will be made on a square foot basis at the specified rate of installing ties. The base contract amount is 66 square feet.
C. Payment will be made at the contract unit price per square foot.
3.9 CONTRACT LINE ITEM NO. 9: TYPE W EXTERIOR CONCRETE PATCH WITH
GALVANIC ANODES
A. The work for this item consists of installing Type W concrete patches per 1/S501 and 1/S502.
The base price includes incorporating galvanic anodes into the patches per Sheet S505. The work includes, but is not limited to, the following:
1. Protection
2. Shoring of windows, as required
3. Inspection
4. Concrete removal
5. Concrete and embedded steel surface preparation
6. Anticorrosion coating
7. Installation of ties
8. Installation of galvanic anodes as applies
9. Concrete installation and finishing
10. Repair of defects
11. Curing
12. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount for W patches with anodes is 5 lineal feet.
C. Payment will be made at the contract unit price per lineal foot.
GOGA - 149952 01 27 00 - 14
3.10 CONTRACT LINE ITEM NO. 10: TYPE W EXTERIOR CONCRETE PATCH WITHOUT
GALVANIC ANODES
A. The work for this item consists of installing Type W concrete patches per 1/S501 and 1/S502.
The base price excludes galvanic anodes. The work includes, but is not limited to, the following:
1. Protection
2. Shoring of windows, as required
3. Inspection
4. Concrete removal
5. Concrete and embedded steel surface preparation
6. Installation of ties
7. Concrete installation and finishing
8. Repair of defects
9. Curing
10. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount for W patches without anodes is 561 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
3.11 CONTRACT LINE ITEM NO. 11: TYPE WS CONCRETE PATCH
A. The work for this item consists of installing Type Ws concrete patches per 1/S501 and 2/S502.
The base price includes incorporating galvanic anodes into the patches per Sheet S505. The work includes, but is not limited to, the following:
1. Protection
2. Shoring of windows, as required
3. Inspection
4. Concrete removal
5. Concrete and embedded steel surface preparation
6. Anticorrosion coating
7. Installation of ties and added reinforcing
8. Installation of galvanic anodes
9. Concrete installation and finishing
10. Repair of defects
11. Curing
12. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount is 113 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
3.12 CONTRACT LINE ITEM NO. 12: TYPE P CONCRETE PATCHES
A. The work for this item consists of installing Type P concrete patches per 1/S501, 5/S502 and 6/S502. The work includes, but is not limited to, the following:
1. Protection & shoring
GOGA - 149952 01 27 00 - 15
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Concrete installation and finishing
7. Repair of defects
8. Curing
9. Clean up and disposal of waste materials
B. Measurement will be made on a square foot basis. The base contract amount is 303 square feet.
C. Payment will be made at the contract unit price per square foot.
3.13 CONTRACT LINE ITEM NO. 13: TYPE FF CONCRETE PATCH
A. The work for this item consists of installing Type FF concrete patches per 1/S501, and 1A, 1B & 1C/S503. The base price includes incorporating galvanic anodes into the patches. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Installation of dowels
7. Installation of hairpin anchors
8. Installation of galvanic anodes
9. Concrete installation and finishing
10. Repair of defects
11. Curing
12. Clean up and disposal of waste materials
B. Measurement will be made on a square foot basis. The base contract amount is 90 square feet.
C. Payment will be made at the contract unit price per square foot
3.14 CONTRACT LINE ITEM NO. 14: TYPE O CONCRETE PATCH
A. The work for this item consists of installing Type O concrete patches per 1/S501, and 3/S503.
The base price includes incorporating galvanic anodes into the patches. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Installation of dowels
7. Installation of galvanic anodes
8. Concrete installation and finishing
9. Repair of defects
GOGA - 149952 01 27 00 - 16
10. Curing
11. Clean up and disposal of waste materials
B. Measurement will be made on the basis of a lineal foot of projected area. The base contract amount is 48 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
3.15 CONTRACT LINE ITEM NO. 15: TYPE CB CONCRETE PATCH
A. The work for this item consists of installing Type Cb concrete patches per 1/S501 and 4/S503.
The work includes, but is not limited to, the following:
1. Protection
2. Inspection
3. Concrete removal
4. Concrete and embedded steel surface preparation
5. Anticorrosion coating
6. Concrete installation and finishing
7. Repair of defects
8. Curing
9. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount is 10 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
3.16 CONTRACT LINE ITEM NO. 16: TYPE CI CRACK REPAIR - EPOXY INJECTION
A. The work for this item consists of installing Type CI concrete repair per 1/S501 and 5/S503.
The work includes, but is not limited to, the following:
1. Protection
2. Inspection
3. Routing Crack
4. Installation of injection ports and sealing cracks
5. Epoxy Injection
6. Removal of ports and crack seals
7. Pointing crack
8. Repair of defects
9. Curing
10. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount is 45 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
GOGA - 149952 01 27 00 - 17
3.17 CONTRACT LINE ITEM NO. 17: TYPE CP CRACK REPAIR - ROUT & POINT
A. The work for this item consists of installing Type CP concrete repair per 1/S501 and 6/S503.
The work includes, but is not limited to, the following:
1. Protection
2. Inspection
3. Routing crack
4. Pointing crack
5. Repair of defects
6. Curing
7. Clean up and disposal of waste materials
B. Measurement will be made on a lineal foot basis. The base contract amount is 10 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
3.18 CONTRACT LINE ITEM NO. 18: TYPE AI ABANDONED INSERT REPAIR
A. The work for this item consists of installing Type AI Abandoned Insert Repair per 1/S501 and 1/S504. The work includes, but is not limited to, the following:
1. Protection
2. Inspection
3. Concrete removal
4. Removal of insert
5. Concrete patching
6. Repair of defects
7. Curing
8. Clean up and disposal of waste materials
B. Measurement will be made on the basis of each insert removed. The base contract amount is 554 inserts.
C. Payment will be made at the contract unit price per each insert removed
3.19 CONTRACT LINE ITEM NO. 19: TYPE W CONCRETE PATCH - INTERIOR
A. The work for this item consists of installing Type W concrete patches on the interior side of the exterior walls per 3/S509 and associated referenced details. The base price includes incorporating galvanic anodes into the patches. The work includes, but is not limited to, the following:
1. Protection
2. Shoring of windows, as required
3. Inspection
4. Removal and reinstallation of interior bars, if needed, preferred scope is to accomplish repair without removing interior bars
5. Removal of interior finish beyond the patch area as needed to perform concrete repair consistent with contractor’s means and methods
6. Concrete removal
7. Concrete and embedded steel surface preparation
GOGA - 149952 01 27 00 - 18
8. Anticorrosion coating
9. Installation of ties and dowels
10. Installation of galvanic anodes
11. Concrete installation and finishing
12. Patching & painting of interior finish
13. Repair of defects
14. Curing
15. Clean up and disposal of waste material
B. Measurement will be made on a lineal foot basis. The base contract amount is 15 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
3.20 CONTRACT LINE ITEM NO. 20: TYPE W CONCRETE PATCH - THROUGH WALL
A. The work for this item consists of installing through wall Type W concrete patches on exterior walls per 3/S502 and associated referenced details. The base price includes incorporating galvanic anodes into the patches. The work includes, but is not limited to, the following:
1. Protection
2. Shoring of windows, as required
3. Inspection
4. Removal and reinstallation of interior bars if needed, preferred scope is to accomplish repair without removing interior bars
5. Removal of interior finish beyond the patch area as needed to perform concrete repair consistent with contractor’s means and methods
6. Concrete removal
7. Concrete and embedded steel surface preparation
8. Anticorrosion coating
9. Installation of ties and dowels
10. Installation of galvanic anodes
11. Concrete installation and finishing
12. Patching & painting of interior finish
13. Repair of defects
14. Curing
15. Clean up and disposal of waste material
B. Measurement will be made on a lineal foot basis. The base contract amount is 33 lineal feet.
C. Payment will be made at the contract unit price per lineal foot
3.21 CONTRACT LINE ITEM NO. 21: TYPE F CONCRETE PATCHES - INTERIOR
A. The work for this item consists of installing Type F concrete patches per 1/S501 and 2/S501 on the interior side of the exterior walls. The base price includes incorporating galvanic anodes into the patches. The work includes, but is not limited to, the following:
1. Protection
2. Inspection
3. Removal of interior finish beyond the patch area as needed to perform concrete repair consistent with contractor’s means and methods
GOGA - 149952 01 27 00 - 19
4. Concrete removal
5. Concrete and embedded steel surface preparation
6. Anticorrosion coating
7. Installation of ties and dowels
8. Installation of galvanic anodes
9. Concrete installation and finishing
10. Patching & painting of interior finish
11. Repair of defects
12. Curing
13. Clean up and disposal of waste material
B. Measurement will be made on a square foot basis. The base contract amount is 31 square feet.
C. Payment will be made at the contract unit price per square foot.
3.22 CONTRACT LINE ITEM NO. 22: TYPE E- CONCRETE PATCH - INTERIOR
A. The work for this item consists of installing Type E concrete patches per 1/S501 and 4/S501.
The base price includes incorporating galvanic anodes into the patches per Sheet S505. A separate price for Type E patches without galvanic anodes is required. The work includes, but is not limited to, the following:
1. Protection & shoring
2. Inspection
3. Removal of interior finish beyond the patch area as needed to perform concrete repair consistent with contractor’s means and methods
4. Concrete removal
5. Concrete and embedded steel surface preparation
6. Anticorrosion coating
7. Installation of ties
8. Installation of galvanic anodes, as applies
9. Concrete installation and finishing
10. Patching & painting of interior finish at repair area only
11. Repair of defects
12. Curing
13. Clean up and disposal of waste material
B. Measurement will be made on a lineal foot basis. The base contract amount for E patches with anodes is 109 lineal feet.
C. Payment will be made at the contract price per lineal foot.
3.23 CONTRACT LINE ITEM NO. 23: OPTION 1 - EXTEND WORK TO OPTION 1 WALL
AREA SHOWN IN DRAWINGS.
A. The work for this item consists of installing all repair work outlined in Line Items 1 - 22, as applies, to the exterior and interior face of the wall area identified in the Drawings.
B. Measurement will be made on the same basis as described in the Line Items above. The quantities are given in the Drawings and in the Contract Price Schedule.
GOGA - 149952 01 27 00 - 20
C. Payment will be made on the same basis as described for the Line Items above.
3.24 CONTRACT LINE ITEM NO. 24: OPTION 2 - EXTEND WORK TO OPTION 2 WALL
AREA SHOWN IN DRAWINGS.
A. The work for this item consists of installing all repair work outlined in Line Items 1 - 22, as applies, to the exterior and interior face of the wall area identified in the Drawings.
B. Measurement will be made on the same basis as described in the Line Items above. The quantities are given in the Drawings and in the Contract Price Schedule.
C. Payment will be made on the same basis as described for the Line Items above.
3.25 CONTRACT LINE ITEM NO. 25: OPTION 3 - EXTEND WORK TO OPTION 3 WALL
AREA SHOWN IN DRAWINGS.
A. The work for this item consists of installing all repair work outlined in Line Items 1 - 22, as applies, to the exterior and interior face of the wall area identified in the Drawings.
B. Measurement will be made on the same basis as described in the Line Items above. The quantities are given in the Drawings and in the Contract Price Schedule.
C. Payment will be made on the same basis as described for the Line Items above.
3.26 CONTRACT LINE ITEM NO. 26: OPTION 4 - EXTEND WORK TO OPTION 4 WALL
AREA SHOWN IN DRAWINGS.
A. The work for this item consists of installing all repair work outlined in Line Items 1 - 22, as applies, to the exterior and interior face of the wall area identified in the Drawings.
B. Measurement will be made on the same basis as described in the Line Items above. The quantities are given in the Drawings and in the Contract Price Schedule.
C. Payment will be made on the same basis as described for the Line Items above.
END OF SECTION 01 27 00
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins. |
| B. If no contract line item exists for a portion of the work, include the costs in a related item. |
| 1.2 DEFINITIONS |
| A. Unit price: a price per unit of measurement for materials and services necessary to perform the Work defined below and in the Contract Documents, include all necessary material, cost for delivery, protection, engineering & testing, access, installa... |
| 1.3 PROCEDURES |
| A. Payment for unit price work will be made only for the actual quantities of work installed. |
| B. For each unit price the approved Schedule of Values will establish defined subtasks and an associated percentage completion of the unit price work in order to receive partial payment of unit price items. |
| C. The Contracting Officer reserves the right to reject Contractor’s measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government’s expense, by an independent surveyor mutually acceptable to t... |
| D. The Line Item descriptions of work below are in outline form and are intended only to present an overview of the of the work included under each item. |
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - LIST OF CONTRACT LINE ITEMS |
| 3.1 CONTRACT LINE ITEM NO. 1: General Repairs |
| A. Contract Line Item No. 1 Includes the Following: Mobilization, Demobilization, General Conditions, Exterior Wall Painting, Roofing On Parapet Wall, View Port Repair, Floor Vent Repair, Floor Vent Replacement, Parapet Replacement, Additional Supplem... |
| 1. Mobilization & Demobilization: |
| a. The work for this item consists of onetime tasks needed to setup and support the overall work and onetime tasks needed to close out the project, demobilize and move off of the site. Examples include, but are not limited to: |
| 1) Visual barriers and setup of staging areas |
| 2) Temporary offices |
| 3) Gull exclusion netting and Protection of Natural Features |
| 4) Temporary roof access stairs |
| 5) Initial installation of scaffold |
| 6) Initial setup for water & power facilities |
| 7) Worker orientations |
| 8) Installation of visitor and staff protection measures |
| 9) Relocation/protection of benches and other |
b. No separate measurement of quantities will be made
| 2. General Conditions |
| a. The work for this item consists of tasks needed to support the overall project but not specifically associated with and single Line Item, such as: |
| 1) Scaffold rental cost |
| 2) Maintenance of Temporary Facilities |
| 3) Daily transport of crew to the island |
| 4) Delivery and storage of water |
| 5) Provisions to supply power for the work |
| 6) Submittals and mockups |
| 7) Supervision |
| 8) Coordination |
b. No separate measurement of quantities will be made
| 3. Paint Removal and Repainting of Exterior Concrete Walls & Historic Fixtures |
| a. This work for this item consists of removing and disposing of the paint coatings, including lead based paint on the exterior concrete walls and attached historic fixtures, and preparing and repainting the historic fixtures and the walls with a new ... |
| 1) Protection |
| 2) Inspection and documentation |
| 3) Removal of abandoned bird netting anchors per 3/S504 |
| 4) Coating removal and disposal of lead based paint |
| 5) Cleaning and preparing substrates for painting |
| 6) Installing new coating systems |
| 7) Repair of defects |
| 8) Clean up |
b. No separate measurement of quantities will be made
| 4. Roofing Work on Parapet Wall |
| a. The work for this item consists of roofing work on the inside face of the roof parapet wall. Patching concrete is not included in this line item. The work includes, but is not limited to, the following: |
| 1) Protection & shoring |
| 2) Temporary support and protection of conduit and other utilities attached to parapet, |
| 3) Removal and disposal of all roofing layers on parapet including top, inside face, and top of cornice. Roofing on the back wall face of the parapet contains asbestos, |
| 4) Removal of roofing adjacent to parapet of wall, |
| 5) Removal, repair and reinstallation of light support brackets |
| 6) Installation of new roofing and flashings |
| 7) Installation of bird deterrent system |
| 8) Repair of defects |
| 9) Clean up and disposal of waste materials |
b. No separate measurement of quantities will be made.
| 5. View Port Repair: |
| a. The work for this item consists all work needed to repair existing view ports per 2/S506 including but not limited to: |
| 1) Protection |
| 2) Remediation of hazardous materials |
| 3) Cutting, patching and repair of adjacent finishes |
| 4) Dismantling components |
| 5) Repair or replacement of deteriorated, damaged or missing components |
| 6) Adjustment and alignment of doors |
| 7) Paint removal and repainting |
b. The unit of measure will be each view port. The base contract amount is 0 view ports.
| 6. Floor Vent Repair |
| a. The work for this item consists all work needed to repair existing floor vents per 3/S506 including but not limited to: |
| 1) Protection |
| 2) Remediation of hazardous materials |
| 3) Cutting, patching and repair of adjacent interior finishes, exterior wall patching is not included in this line item |
| 4) Dismantling components |
| 5) Repair or replacement of deteriorated, damaged or missing components |
| 6) Adjustment and alignment of deformed or inoperable components |
| 7) Installation of replacement components |
| 8) Paint removal and repainting |
| 9) Cleanup and disposal of waste materials |
b. The unit of measure will be each floor vent. The base contract amount is 0 floor vent.
| 7. Floor Vent Replacement |
| a. The work for this item consists all work needed to repair existing floor vents per 4/S506 including but not limited to: |
| 1) Protection |
| 2) Remediation of hazardous materials |
| 3) Cutting, patching and repair of adjacent interior finishes, exterior wall patching is not included in this line item |
| 4) Dismantling components |
| 5) Repair or replacement of deteriorated, damaged or missing components |
| 6) Adjustment and alignment of deformed or inoperable components |
| 7) Installation of replacement components |
| 8) Paint removal and repainting |
| 9) Cleanup and disposal of waste materials |
b. The unit of measure will be each floor vent. The base contract amount is 0 floor vent.
| 8. Parapet Replacement |
| a. The work for this item consists of installing full thickness concrete patches at parapet locations per 1/S501, and 2/S503. The work includes incorporating galvanic anodes into the patches. The work includes, but is not limited to, the following: |
| 1) Protection & supporting/rerouting water and power |
| 2) Protection of Rooftop PV systems |
| 3) Inspection |
| 4) Concrete removal |
| 5) Concrete and embedded steel surface preparation |
| 6) Anticorrosion coating |
| 7) Installation of dowels |
| 8) Installation of supplemental reinforcing bars |
| 9) Installation of galvanic anodes |
| 10) Concrete installation and finishing |
| 11) Repair of defects |
| 12) Curing |
| 13) Clean up and disposal of waste materials |
b. Measurement will be made on a lineal foot basis. The base contract amount is 5 feet.
| 9. Added Supplemental Structural Reinforcement |
| a. The work for this item consists of installing supplemental structural reinforcing bars within all types of concrete patches per 1/S501, and 4/S504. Patch reinforcing such as wire mesh, hairpin anchors and small diameter anchors required in the basi... |
| 1) Protection & shoring |
| 2) Inspection |
| 3) Installation of dowels |
| 4) Installation of supplemental reinforcing bars |
| 5) Repair of defects |
| 6) Curing |
| 7) Clean up and disposal of waste materials |
b. Measurement will be made per lineal foot of bar. The base contract amount is 183 lineal feet.
| 10. Repair of Exterior Stairs to Recreation Yard. |
| 1) This item consists of all work associated with repairing the exterior concrete stairs to the recreation yard as presented in Sheets S507 & S508, including but not limited to: Protection, coordinating alternate exit routes, removal of existing shori... |
| b. No separate measurement of quantities will be made. |
| 11. Impressed Current Cathodic Protection System for West Pilasters |
| a. This item consists of design build impressed current cathodic protection system for the exterior concrete pilasters on the west side of the building. The work includes, but is not limited to, the following: |
| 1) System design for a minimum 30 year service life |
| 2) Component fabrication |
| 3) Installation of anodes including concrete saw cutting and patching |
| 4) Testing |
| 5) Installation of rectifiers and connection to power supply |
| 6) Clean up and disposal of waste material |
| 7) System adjustment |
| 8) First year of service and warranty |
b. No separate measurement of quantities will be made.
| 12. Impressed Current Cathodic Protection System for West Windows |
| a. This item consists of design build impressed current cathodic protection system for the window perimeters on the west side of the building. The work includes, but is not limited to, the following: |
| 1) System design for a minimum 30 year service life |
| 2) Component fabrication |
| 3) Installation of anodes including concrete saw cutting and patching |
| 4) Testing |
| 5) Installation of rectifiers and connection to power supply |
| 6) Clean up and disposal of waste material |
| 7) System adjustment |
| 8) First year of service and warranty |
b. No separate measurement of quantities will be made.
| 13. Window Repair - Type 1 |
| a. The Work for this item consists of installing Type 1 Window Repairs per the Window Schedule on Sheets A601 - A603, and per detail sheets A501 and A506. Removal, repair and reinstallation of exterior bars is included in a separate line item. Repair ... |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .